OSG at Fermilab: Grid Coordination Meeting, 2/27/07 - PowerPoint PPT Presentation

1 / 4
About This Presentation
Title:

OSG at Fermilab: Grid Coordination Meeting, 2/27/07

Description:

Provides the underlying distributed infrastructure in the ... Daily Validation and Software ... STAR: Migration of 80% of simulation to OSG. 6/15/07 ... – PowerPoint PPT presentation

Number of Views:13
Avg rating:3.0/5.0
Slides: 5
Provided by: Rut198
Category:

less

Transcript and Presenter's Notes

Title: OSG at Fermilab: Grid Coordination Meeting, 2/27/07


1
OSG at Fermilab Grid Coordination Meeting,
2/27/07
  • OSG
  • Provides the underlying distributed
    infrastructure in the US for US LHC
  • Supports the use of distributed resources in the
    US by all Fermilab users.
  • Works on interoperability across Grids in US and
    other countries (especially EGEE in Europe).
  • OSG effort at Fermilab is funded by
  • Externally funded SciDAC-2/NSF OSG Project
  • CD and CMS contributions to Joint Project
    Activities
  • OSG External Projects Accounting, VO Services,
    Resource Selection Workload Management.
  • FermiGrid testing, Integration Test bed, hosting
    of OSG VO mgmt services etc.
  • Contributed by US CMS SC
  • Daily Validation and Software Quality Assurance.
  • Information services interoperability and
    outreach support

2
Date A OSG Milestones in Fermilab Statement of Work Responsible Party
12/15/06 N Project Baseline Internal Assessment. FNAL Executive Team (Primary)
12/15/06 N Validate the SRM/dCache prototype deployment candidate. FNAL together with UCSD (secondary)
12/15/06 N Specify transfer metrics for viewing on the first OSG transfer aggregation prototype. FNAL with UCSD and Cornell (secondary)
1/1/07 Y Deliver the OSG Security Plan FNAL with LBNL, SLAC,Security Team (Primary)
2/15/07 N Final release of SRM/dCache for deployment in VDT for OSG 0.6.0 release FNAL with Wisconsin (Primary)
2/27/07 Y OSG 0.6.0 Release Together with others
3/1/07 N Complete site functional tests for SRM/dcache production release candidate FNAL with LBNL (Primary)
3/1/07 N User documentation for OSG 0.6 FNAL with UCSD (shared)
3/1/07 N Client tools for site testing of OSG 0.6 site FNAL with UCSD (shared)
3/5/07 N Deliver First Security Training FNAL with LBNL, SLAC and Security Team (Primary)
4/1/07 N Document performance baseline for OSG data transfer. UCSD with BNL and FNAL (shared)
5/1/07 N First audit of OSG asset FNAL with LBNL, SLAC and Security Team (Primary)
6/1/07 N Document performance baseline for OSG job submission. UCSD with BNL (primary)
8/15/07 Y OSG 0.8.0 Release Together with others
8/15/07 Y Year 1 OSG Project Progress Review FNAL and Executive Team (Primary)
9/1/07 N User documentation for OSG 0.8 UCSD with FNAL (shared)
9/1/07 N Client tools for site testing of OSG 0.8 site FNAL with UCSD (shared)
9/30/07 N Improved Forensic Tools to investigate Security breach at sites, and across OSG FNAL with UCSD and external efforts at LBNL(secondary)
3
Name Description FTE OSG Activities
Ruth Pordes PI executive director 575 Y Coordination
Don Petravick Security Officer 30 Y Security
Gene Oleynik Storage Management Leader 50 Y VDT and Extensions
TBD(Until replacment for Vikram Andem understood filled by Igor Sfiligoi, Irwin Gaines, Keith Chadwick) Staff to Security Officer 70 Y Security plans and processes.
Chris Green Developer 50 Y User Support and Users Group
Ted Hesselroth Integrator and Developer 100 Y VDT and Extensions dCache and SRM
Neha Sharma Integrator and Developer 50 Y VDT dCache and SRM
Michael Zalokar Integrator and Developer 25 Y VDT dCache
TBD (when reorganization is complete will rationalize this and above effort) Storage and Data Management, Site Coordinator 25 Y Extensions
Anne Heavey Technical Writer 50 Y OSG Communications /Technical Writing
Marcia Teckenbrock Web Designer 50 Y Webmaster, Document Librarian, OSG News and Communications.
Forrest Christian (full time for 6 months10/1/06-6/1/07) Technical Writer 50 Y Provisioning documentation, technical write-ups, training materials.
Chander Sehgal Project Budget Specialist 100 Y Plans, Reports, Financial tracking
Danielle Venton iSGTW 50 Y International Science Grid This Week Editor. (rest of salary from EGEE TeraGrid contribution)
Penelope Constanta Assistant to Executive Director 50 N Arrange Consortium meetings, brochures, reports etc. (possible funding from Education Activity)
Job posted. Hiring in progress
4
Science Milestones Year 1(from WBS)
LIGO Binary Inspiral Analysis runs on OSG (see first milestone reported) Warren Anderson 6/15/07
ATLAS Validation of OSG infrastructure and extensions in full-chain production challenge. Jim Shank 6/15/07
CMS Full support for opportunistic use of OSG resources for MC production and data processing. Lothar Bauerdick 6/15/07
STAR Migration of gt80 of simulation to OSG Jerome Lauret 6/15/07
CDF Full use of OSG for MC Ashutosh Kotwal 6/15/07
D0 Full use of OSG sites for D0 reprocessing in 2007 (in progress 2/1/2007) Brad Abbott 6/15/07
SDSS Fit all spectra beyond data release 5, QSO fitting project (now DES simulations/data transfer) Chris Stoughton 6/15/07
  • All have demands on the OSG infrastructure. -
    All same date because at the time better
    estimates were not available. - General work
    being done towards these goals - final specific
    plans at March All Hands meeting.