LHC%20Status%20 - PowerPoint PPT Presentation

About This Presentation
Title:

LHC%20Status%20

Description:

LHC Status – PowerPoint PPT presentation

Number of Views:67
Avg rating:3.0/5.0
Slides: 41
Provided by: stefanor
Category:
Tags: 20status | lhc | pil

less

Transcript and Presenter's Notes

Title: LHC%20Status%20


1
LHC Status Plans
  • V. Kain, LHC Operations
  • Input from J. Wenninger, F. Zimmermann, R.
    Assmann, S. Myers, J.P. Koutchouk, L. Evans, A.
    Verwej, H. Burkhardt....
  • SLAC SLUO workshop 16th 17th of July

2
Outline
  • Beam Commissioning
  • September 19th Incident
  • The cause, the problem...a cure?
  • 2009/10 LHC run
  • ...And beyond LHC Upgrade
  • Summary

3
LHC Cool-down
Cool-down time to 1.9 K 4-6 weeks/sector sector
1/8 LHC
4
LHC Hardware Commissioning
  • February to September 2008
  • (Re-)commissioning of the magnets circuits
    (power converter, quench protection,
    interlocking..) following predefined test steps.
  • 1700 circuits, 10000 magnets
  • LHC was commissioned to 5.5 TeV (5 TeV target for
    physics in 2008).
  • Magnet re-training required above 6 TeV.
  • Commissioning of other equipment (kickers,
    instrumentation, RF,)

11122 test steps
5
Injection Tests
  • August September 2008
  • Injection tests up to 4 adjacent sectors
  • Almost all HW systems involved
  • Essential checks for
  • Control system
  • Beam Instrumentation
  • Optics (magnetic model) and aperture

6
September 10th
7
Beam Threading
  • Threading by sector
  • One beam at a time AND one beam per hour
  • Collimators used to intercept beam (1 bunch, 2
    109 protons per bunch, 2 of nominal bunch)
  • Beam through sector (1/8 of ring), correct
    trajectory, move out collimators, carry on.

Beam 2 threading
BPM availability 99
8
ATLAS CMS events
  • Beam-on-collimator events, synchronized to beam
    timing

Courtesy of CMS
9
Beam Commissioning Progress
  • September 10th
  • 1030 Beam 1 around the ring (in 1 hour). Beam
    makes 3 turns
  • 1500 Beam 2 around the ring. Beam makes 3-4
    turn
  • 2200 Beam 2 circulates for 100s of turns
  • September 11th
  • Late evening beam 2 captured by RF.
  • First emergency dump correctly executed.
  • September 12th
  • All basic instrumentation operational BPMs,
    BLMs, Tune, BCTs,...
  • Good beam lifetime (gt 1 hour)
  • Beta-beating measured

10
Magnetic model beta-beating
  • A sophisticated magnetic model (FIDEL) was
    developed to predict transfer functions and field
    errors for all magnets, backed by measurements
    and integrated into the control system for online
    corrections.

Beta-beat tolerance 20
  • Horizontal beating 30
  • Vertical beating up to 90-100

11
September 19th incident
12
Event sequence on 19th of September
  • Last commissioning step on main dipole circuit in
    Sector 34 ramp to 9.3 kA (5.5 TeV)
  • At 8.7 kA an electrical fault developed in the
    dipole bus bar in the interconnect between
    Q24.R34 and the neighbouring dipole
  • Later correlated to a resistance of that splice
    in the interconnect of 220 nW (0.35 nW
    nominally)
  • An electrical arc developed which punctured the
    He enclosure
  • Secondary arcs developed along the circuit
  • Around 400 MJ out of the 600 MJ stored in the
    circuit were dissipated into the coldmass and in
    electrical arcs.
  • Tons of He were released into the insulation
    vacuum
  • Pressure wave along the magnets in the insulation
    vacuum ? collateral damage

13
Interconnection
Vac. chamber
Dipole busbar
14
After the incident...
Dipole bus bar
15
Collateral damage pressure wave
  • He-pressure wave travels along magnet inside
    insulation vacuum up to vacuum barriers (every 2
    cells)
  • Self actuating relief valves could not handle
    pressure
  • Designed for 2 kg He/s incident 20 kg He/s
  • Large forces exerted on vacuum barriers
  • Designed for 1.5 bar incident 8 bar
  • Several quadrupoles displaced by 50 cm
  • Connection to cryo-line damaged
  • Beam vacuum atmospheric pressure

16
Collateral damage - beam vacuum
  • Beam vacuum affected over entire length of arc
    2.7 km

Clean surface
Covered with MLI flakes 60 of all chambers
Covered with soot. 20 of all chambers
17
LHC Repair
18
The Cause, the problem...a cure?
19
Incident cause poor quality joint
  • Cryogenic measurements indicate local resistance
    of superconducting cable joint of 220 nOhm in
    cell where incident occured.
  • Simulation of fatal ramp thermal runaway at
    8700 A
  • 1 V detection threshold of OLD quench
    protection system (QPS) not adequate
  • ? 0.3 mV is required to protect busbars ? new
    QPS system

20
Busbar quench current through Cu stabilizer
21
Bad connection in Cu stabilizer? New QPS does
not protect
22
Bad Cu stabilizer bus bar quench
  • Has to be measured at warm.

23
Measurement at cold 1.9 K
  • Goal for next run beam energy 4 TeV 5 TeV
  • Splices above inadequate resistance have to be
    fixed

Cold 1.9K
24
Measurement at300 K (80 K)
  • Copper stabilizers... simulations are only as
    good as their input conditions...

25
Measurement status strategy
  • SC joint measurements calorimetry (down 40
    nOhm), high precision voltage (down to 1 nOhm)
    measurements,...
  • 3 sectors still to be tested (S34, S23, S45) so
    far
  • two bad internal joints found (50 nOhm, 100
    nOhm)
  • Cu stabilizers
  • 3 sectors still to be tested (S 23, S 78, S 81)
    so far
  • MB 10 joints repaired gt 35 mOhm
  • MQ 10 joints repaired gt 80 mOhm
  • Strategy
  • Measure remaining sectors
  • Determine which splices need to be repaired as a
    function of safe current
  • Discuss safe operating energy vs. start-date
    with beam

NEW QPS TO PROTECT!
DANGEROUS IN CASE OF QUENCH
26
LHC run 2009/10 - Plans
27
Current Planning
  • Machine fully hardware-tested end of October.
  • First beam end of October.
  • ...followed by a long LHC run until November 2010
    with a short break around Christmas/New Year.
  • Target energy 4 5 TeV

Cool-Down
Low cur. powering
High cur. powering
28
Luminosity Goals
  • Present 4-stage collimation system limits
    intensity to 10 of nominal.
  • Operational goals 2009/10
  • End of 2010 short Pb ion run foreseen

No. bunches/ beam Protons/ bunch of nominal intensity b (m) Peak L (cm-2 s-1)
43 5?1010 0.7 2 6.9x1030
156 5?1010 2.4 1 5.0x1031
156 1?1011 4.8 1 2.0x1032
720 (50 ns) 5?1010 11.1 2 1.2x1032
No crossing angle
29
...And beyond LHC upgrade
  • sLHC Luminosity upgrade

30
Upgrade for Nominal - Collimation
  • Issue loss of off-momentum particles in the
    dispersion suppressor right downstream of
    collimation zones.
  • Coming either
  • 2010/11 or 2013/14
  • cryo-collimators
  • low impedance collimators ? HiRadMat
  • in-built BPMs

31
LHC Luminosity Upgrade
  • Luminosity upgrade ? sLHC

Limitations Nb, en injector chain nb electron
cloud effect F beam separation
schemes b insertion
sLHC Phase I
sLHC Phase II
32
Plans...
33
Phase I and Phase II
  • Phase I - 2014
  • New NbTi larger apterure triplets, new quadrupole
    absorbers (TAS), new separation dipoles ? b
    25 cm
  • Linac4 ? ultimate intensity 1.7 1011 p per
    bunch
  • Luminosity 3 1034 cm-2s-1
  • Phase II - 2018
  • Two new injectors SPL and PS2 ? 2x ultimate beam
    brightness (Nb/e)
  • New triplets? Nb3Sn? More robust, larger aperture
    ? b 15 cm
  • New separation schemes? Other compensatory
    measures?
  • Luminosity 1035 cm-2s-1

Still open questions
34
Phase II new separation scheme required
for nominal crossing angle (9.5 s), only modest
luminosity gain from reduced ß, if
not complemented by other measures
Crossing angle reduces beam-beam tune shift but
also luminosity.
Geometric factor
Piwinski angle
35
Beam separation schemes/ Compensatory measures
possibilities
  • Low emittance 1- 2mm
  • Draw back limited by beam-beam tune shift and
    IBS
  • Work against lumi-decrease from geometric overlap
    reduction different possibilities
  • Long-range beam-beam compensation
  • Early separation dipole magnets in experiment
  • Plus possible crab cavities
  • Full crab crossing with dedicated crab cavities
  • Large Piwinski angle at beam-beam limit
    larger Piwinski angle (and/or larger emittance)
    increases luminosity 50 ns, 4.9 1011 p per
    bunch

Beam-beam compensation
1.7-2.3 1011 per bunch, 25 ns
Crab crossing
36
Contact Names - Upgrade
  • http//project-slhc.web.cern.ch/project-slhc/conta
    cts/
  • sLHC project leader L. Evans
  • Linac4 M. Vretenar, A. Lombardi
  • SPL R. Garoby, A. Lombardi
  • PS2 M. Benedikt, Y. Papaphilippou
  • SPS upgrade E. Shaposhnikova
  • IR upgrade (phase I) R. Ostojic, S. Fartoukh
    http//slhc-irp1.web.cern.ch/SLHC-IRP1/
  • EuCARD Coordinator J.-P. Koutchouk
    https//eucard.web.cern.ch/EuCARD/about/
  • Crab cavities J. Tuckmantel, F. Zimmermann
  • Collimators R. Assmann
  • High field magnets L. Rossi
  • ....
  • Other things
  • Machine protection, operational issues,
    software,... J. Wenninger, R. Schmidt, V. Kain

37
Summary
  • With beam the LHC is a wonderful machine.
  • All key systems were operational
  • Remarkable performance of the beam
    instrumentation
  • The incident of the 19th of September was most
    probably due to the poor quality of a bus-bar
    joint.
  • ? Quench protection system upgrade
  • ? Improvement of the pressure relief system
  • ? Measurement campaign for all splices and
    stabilizers systematic problem
  • Repair and further measurements are well under
    way
  • We will start-up in autumn this year. The goal is
    to run until autumn 2010.
  • Upgrade luminosity upgrade in several stages.
    Different work packages have been defined.
  • Collimators need upgrade to go to nominal
    intensity
  • The first upgrade phase is planned for 2014

38
Reserve slides
39
Bad surprise...voids in joints
  • Voids are present in most of the joints. Solder
    (SnAg) flows out when soldering in situ.

40
Splice and Stabilizer Measurements (Status June 5)
Sector Status on June 5 2009 Splices Calorimetric Ohmic Splices Calorimetric Ohmic Stabilizers Biddle R16 Stabilizers Biddle R16 Stabilizers Biddle Stabilizers Biddle
Sector Status on June 5 2009 1.9K 7kA 1.9K 7kA Warm Warm 80K 80K
Sector Status on June 5 2009 Dipoles Quads Dipoles Quads Dipoles Quads
12 warm Done Done Done Done No need No need
23 2K
34 warm Done Done No need No need
45 80K Analysis Problems
56 warm Done Done Done Done No need No need
67 warm Done Done Done Done No need No need
78 40K Done Done
81 40K Done Done
Write a Comment
User Comments (0)
About PowerShow.com