Title: Review
1LAT Environmental Test Planning and Design
Review 3-4 May 2005 MGSE Design
Martin Nordby Mike Foss Marc Campell John Ku
2Environmental Test MGSE Design Concept
- Test Interface Plate
- LAT is mounted to the TIP at SLAC, and stays
mounted to it until integration on the SC - This eliminates the need for complex load
transfers and additional MGSE - Test Stand
- For all tests but the sine vibe test, the LAT is
mounted to the Test Stand - This serves as a support, transport cart, and
frame off of which ancillary MGSE and STE is
mounted - Transport Container
- This is comprised of a pallet with a
base-isolated mount plate and a cover - The LAT is bolted to the mount plate by way of
the TIP - The pallet also serves as a storage base for the
LAT at NRL and Spectrum - All other MGSE is secondary to these 3
LAT
Test Interface Plate
Test Stand
SC Flexures
LAT on Test StandSupported by the Test Interface
Plate
3TIP / Test Stand Preliminary Design and Operations
- This is home base for the LAT
- Used for all tests
- Easy to add to or adapt for test-specific needs
- The Test Stand provides all functions needed for
handling the LAT - Moving, hoisting, and turn-overare all done
using the Test Stand - Casters, jacks, and extension beams are all
removable to accommodate any test configuration - All load transfers are straightforward, with
simple bolted joints and standard hoisting and
rigging
Cross-Bars for load-sharing during turn-over
SC Top Deck Acoustic Sim
Extension Beams for -above cg lifting
-turning over -horiz lifting -horiz support
in T-Vac
Test Interface Plate
Empty TIP on Test Stand
LAT Uprighting Operation After T-Vac
4Transport and Storage Container
- Transport Container provides isolated environment
for the LAT during transport - Wire rope coils isolate LAT from shock and
medium/high frequency vibrations - Air-tight container allows for purging to
maintain low humidity in the box - Insulated cover isolates LAT from ambient
temperature extremes - Pallet doubles as a work platform
- With the cover removed, the pallet provides clear
access to the LAT for pre- and post-ship testing - We may use this as a storage location for the LAT
between operations at NRL
Vibration isolating wire rope coils
Mount plate
Transport Container Pallet
Cover mounts around perimeter of pallet
Test Interface Plate
LAT on Transport Container Pallet
5Environmental Test Flow and MGSE/STE Use
Mount on Test Stand
X-axis Sine VibeLPTY-axis Sine VibeLPT
Receive LATfrom SLAC
Unpack, Prep, CPT
Z-axis Sine VibeLPT
EMI/EMC TestLPT
Mount RadiatorsLAT LPTRadiator CPT
Turn Over
Prep for T-Vac
Acoustic TestLPT
Measure Mass, X/Y C.G.
CPT, SVACThermal-Vac TestCPT, SVAC
Pack, Prep, and Ship to SASS
PackRadiators
Rotate Upright
Remove RadiatorsDe-Mount off Test Stand
6MGSE List
- The table shows a complete list of all known MGSE
needed for environmental testing at NRL and
transporting the LAT
MGSE/STE Needed for Environmental Testing
7Test Interface Plate (TIP) Design
- The TIP is permanently mounted to the LAT after
LAT integration - This is done at SLAC
- Mounting procedure for SC flexures
- All 4 flexures are positioned using Spectrums
master gauge tool (the slave was used for
machining our Grid holes) - Mount brackets are positioned and bolted
- Flexure-Bracket holes are match-reamed and
hardware installed - (Still needs Spectrum review)
- The Grid Perimeter Ring is used for hoisting the
LAT - This means that the TIP hangs from under the LAT
- The TIP needs to be light enough to not cause any
loading issues - Design status
- Detailed drawings complete and in check
- Preliminary analysis in process
- Final structural analysis not started
- Plan for completion early enough to use in Grid
Qual testing
Aluminum interface plate carries no loads, but
only locates Flexures
SC Flexure
Mounting hardware and method is identical to
Spectrum plans
Mounting hardware passes through plate
SC Flexure mounted to plate by way of Mount
Bracket
8TIP Design Requirements Summary from Test Plans
- Loads and Capabilities
- Capable of handling inertial loads of LAT during
sine vibe test and transport - Carries LAT when horizontal or vertical, plus
thermal stresses due to temp variations in T-Vac - Total TIP mass not to exceed 200 kg (current
estimate 129.5 kg), so LAT TIP can be lifted
using the Grid Perimeter Ring - Interfaces
- Provides alignment of flexures that matches
Spectrum alignment - Compatible with vibe table expander head and slip
table bolt patterns - Mounts to Test Stand, Transport Container
pallet, Mass properties mount plate - Accommodations
- Accommodates a top deck acoustic simulator
- Accommodates installation of a SC top deck sink
plate between TIP and X-LAT Plate
9TIP Structural Analysis
10Test Stand Design
- Test Stand is designed to be simple to fabricate
and test - Welded box beam construction is welded clean then
painted - Sub-assemblies are machined to provide accurate
mounting hole patterns - Assembly is proof- and operationally tested
independent of the LAT, using Spectrum test
weights (TBR) - Design status
- Detailed drawings complete and in check
- Preliminary analysis in process
- Final structural analysis not started
- Completion tied to Pathfinder schedule
TIP interface bolt plates
Extender Beam bolt plates
Test Stand Assembly
Removable casters for moving LAT
Test Stand Weldment
11Test Stand Design Requirements Summary from Test
Plans
- Loads and Capabilities
- Supports LAT in horizontal configuration during
hoisting, transport, and on T-Vac trolley - Capable of leveling the LAT to an accuracy of 0.1
degrees in both principal axes - Functions over temp range of TBD to TBD degC
while maintaining angular stability of LAT to
within /- 0.1 degrees - Includes active heating to stabilize average
temps - Interfaces
- Extension Beams compatible with T-Vac trolley
mounting and floor loading capabilities - Accommodations
- Accommodates SC simulator sink plates during
T-Vac - Provides clear access around LAT perimeter and
underside for EMI test antennae
12Test Stand Structural Analysis
13Transport Container Design
- Some preliminary features
- LAT is ship weight is 7500 lbs
- Construction
- 2-piece Aluminum with Base Pallet and Lid Box
- Lid is hoisted on and off
- 6 min (TBR) clearance from instrument
- Design status
- Proof-of-concept design complete
- Re-working design to spec as a turn-key
design/build contract - In the process of specifying LAT design and
performance constraints, then the spec and
statement of work will be bid for design, fab,
and testing
Mount plate provides rigid mount for LAT
Base-isolation coil springs
Base Pallet(LAT TIP removed)
Cover Box provides clearance for LAT dynamic
motion
LAT on Base Pallet(Cover Box removed)
TIP mounts directly to Pallet mount plate
LAT in Transport Container
14Transport Container Design Requirements Summary
- Loads and Capabilities
- Capable of handling transportation loads of LAT
TIP by air or truck - Capable of storing LAT for 24 hours (TBR) outside
- Capable of being lifted by forklift or moved by
air bearings - Provides base isolation to protect LAT from
accelerations exceeding fight design levels,
given an input of ground- or air-transport
acceleration spectra - Interfaces
- Compatible with Test Interface Plate
- Standard skids, lifting features, and tie-downs
for transportation equipment - Accommodations
- Provides clearance around LAT to allow for
relative motion due to base-isolation system - Cover includes port for mounting purge line,
two-way pressure relief valve and filter for
incoming air, feedthroughs for environmental
monitors (TBR) - Internal cleanliness level Class 10,000 TBRLAT
is not bagged TBR (cant contact ACD MLI) - Environmental monitors to track temperature,
humidity, and 3-axis accelerations during
transport (on container and LAT mount plate)
15NRL Environmental Test Facilities
- Facilities drawings are being developed for all
areas where LAT will be located or tested - Intended to capture all facility-specific
information needed for LAT testing - This includes power and network tie-in points for
testing LAT - All drawings are in work now, with either
advanced check prints or released versions (in
NRL configuration management system)
NRL Facility Drawings
16MGSE Development Timeline
17MGSE and Facilities Issues List
- Summary
- The three key pieces of MGSE have been designed
and are in the process of being analyzed and
finalized - Concepts exist for most of the remaining MGSE
- Issues
- Our pathfinder program is keyed to receiving the
TIP and Test Stand by mid-September. These are
big parts which will take time to fab, inspect,
and test ? Marc Campell is developing a detailed
design and fab schedule for these - STE sink plates for T-Vac are still poorly
designe, thermally. These need to be specd out
to confirm that we have preserved enough space
for them, and that the Test Stand works
as-designed ? Martin Nordby actively working
with thermal people to lock in the thermal design
and spec out the design of these