Throughput maximization by improved bottleneck control - PowerPoint PPT Presentation

About This Presentation
Title:

Throughput maximization by improved bottleneck control

Description:

Department of Chemical Engineering, Norwegian University of ... Price, Lyman and Georgakis (1994). Throughput manipulation. in plantwide control structures. ... – PowerPoint PPT presentation

Number of Views:36
Avg rating:3.0/5.0
Slides: 16
Provided by: aske
Category:

less

Transcript and Presenter's Notes

Title: Throughput maximization by improved bottleneck control


1
Throughput maximization by improved bottleneck
control
  • Elvira Marie B. Aske, Sigurd Skogestad and
    Stig Strand
  • Department of Chemical Engineering, Norwegian
    University of Science and Technology, Trondheim,
    Norway
  • Statoil RD, Process Control, Trondheim, Norway

2
Outline
  • Modes of optimal operation
  • Maximum throughput
  • Throughput manipulator (TPM)
  • Max-flow min-cut theorem
  • Realizing maximum throughput
  • Single-loop
  • MPC
  • Back off
  • Conclusions

3
Depending on marked conditions Two main modes of
optimal operation
  • Mode 1. Given throughput (nominal case)
  • Given feed or product rate
  • Maximize efficiency Unconstrained
    optimum (trade-off)
  • Mode 2. Max/Optimum throughput
  • Throughput is a degree of freedom good
    product prices
  • 2a) Maximum throughput
  • Increase throughput until constraints give
    infeasible operation
  • Constrained optimum - identify active
    constraints (bottleneck!)
  • 2b) Optimized throughput
  • Increase throughput until further increase is
    uneconomical
  • Unconstrained optimum

4
Mode 2a Maximum throughput
  • Typical profit function
  • Feed flows are set in proportion to F and assume
    constant efficiencies
  • Leads to
  • Maximize profit ? Maximize throughput F

5
Throughput manipulator (TPM)
Buckley (1964). Techniques of Process
Control Price, Lyman and Georgakis (1994).
Throughput manipulation in plantwide control
structures. Ind. Eng. Chem. Res. 33, 11971207.
6
From network theory Max-flow min-cut theorem
Maximum flow through the network is equal to the
capacity of the minimal cut (Ford and Fulkerson,
1962)
7
Bottleneck
  • Maximum throughput achieved by maximizing the
    flow through the bottleneck
  • If the flow for some time is not at its maximum
    through the bottleneck, then this loss can never
    be recovered
  • ? Maximum throughput requires tight control of
    the bottleneck unit

8
Rules for achieving maximum throughput
  • Maximize flow F through bottleneck at all times
  • Use TPM for control of bottleneck unit
  • Locate TPM to achieve tight control at bottleneck
  • Back off usually needed to ensure feasibility
    dynamically

Fmax
F
Fset point
Back off
Time
9
Realize maximum throughput
Best result (minimize back-off) if TPM
permanently is moved to bottleneck unit
Max bottleneck
Skogestad (2004) Control structure design for
complete chemical plants Comp. Chem. Eng 28
p.219-234
10
Realize maximum throughput in more complex cases
  • Bottleneck moves
  • Multiple feeds and crossovers
  • Proposed solution Coordinator MPC
  • Estimate of remaining capacity in each unit is
    obtained from local MPCs
  • Coordinator MPC manipulate TPMs ( crossovers) to
    maximize flow through bottlenecks

Aske et al. (2007) Coordinator MPC for
maximizing plant throughput Submitted to Comp.
Chem. Eng
11
Coordinator MPC
- maximize throughput (CV with high, unreachable
set point with lower priority) - TPMs as MVs -
keep columns within their capacity (CV
constraints) - disturbances moves the bottlenecks
CV
CV
CV
CV
MV
MV
MV
CV
MV
CV
CV
CV
MV
CV
MV
CV
12
Back off loss (in throughput)
  • Back off can be reduced by
  • Improved control (to some extent)
  • Limited by network dynamics from TPM to
    bottleneck
  • Obtain TPM closer to bottleneck
  • Move TPM (Change in base control)
  • Add buffer tanks to get dynamic TPMs (Design
    change)
  • or use existing buffer volumes
  • Estimate back off to find economic incentive
  • Worst case amplification

13
Example estimation of back off
  • Compare TPM at feed and at bottleneck
  • Feedback controller K tuned by Skogestads tuning
    rules, tc3?eff
  • Disturbance rejection as function of frequency

14
Back off as a function of frequency
  • Peak unavoidable
  • Effect of disturbances reduced

15
Conclusions
  • Tighter bottleneck control can reduce back off
  • TPM should be used for control of the bottleneck
    unit to obtain maximum flow
  • Bottleneck fixed ?single-loop control sufficient
  • Bottleneck moves ? multivariable control
  • Consider moving/adding TPM if back off is large
Write a Comment
User Comments (0)
About PowerShow.com