Artisan input -Shop visits -O/I level visits ... heavy reliance on interaction with artisans/technicians ... corrected, artisans trained on test. procedures, ... – PowerPoint PPT presentation

Number of Views:48
Avg rating:3.0/5.0
Slides: 30
Provided by: Coll166
Category:

less

Transcript and Presenter's Notes

Title: Make It Last Longer and Cost Less Naval Air Systems Command Integrated InService Reliability Program


1
Make It Last Longer and Cost LessNaval Air
Systems Command Integrated In-Service
Reliability Program (IISRP) Brief to SOLE
Les Wetherington leslie.wetherington _at_ navy.mil /
240-538-6993 IISRP PM 5/18/2006
2
Agenda
  • Purpose
  • IISRP Mission/Background
  • IISRP is Aligned and Credible
  • IISRP Cost Wise Readiness
  • IISRP Process
  • Results
  • Examples
  • Going Forward
  • Summary

3
Purpose
  • To provide an overview of the IISRP Program and
    associated activities

4
IISRP Mission
SUPPORT THE WARFIGHTER BY IMPROVING RELIABILITY
  • I will remain committed in 2006 to
    thesepriorities
  • Sustain combat readiness with the right combat
    capabilitiesaccess, speed, agility,
    adaptability, persistence and lethality for the
    right cost
  • M. G. MULLEN
  • Admiral, U.S. Navy
  • Chief of Naval Operations
  • CNO Guidance for 2006
  • Meeting the Challenge of a New Era

5
IISRP Background
  • AMSR Issue 16 identified poor AVDLR component
    reliability as a major cost driver
  • NAVAIR BPR 3-3 Component Reliability Improvement
    Project initiated 1st qtr FY99
  • AIR-6.0 (Industrial) leadership, TYCOMs, NAVICP,
    AIR-3.0/4.0 (Logistics/Engineering) participation
  • Integrated teams in work at 3 depot sites since
    1999
  • Transitioned to an institutionalized program May
    2002
  • AIR 6.0/4.0/3.0 (Industrial/Engineering/Logistics)
    Team

6
IISRP is Aligned and Credible
IISRP MISSION Support the Warfighter by
Improving Component Reliability Reducing Fleet
Cost Enhancing Readiness Implementing Fleet
Driven Metrics
NAVAIR GOALS Balance Current and future
readiness Reduce cost of doing business Improve
Agility Align with CNOs transformational
initiatives Implement Fleet Driven metrics
6.0D CORPORATE FOCUS AREAS Reliability Turn
Around Time Financial Story CO/XO
Accountability Material Management
Sustain combat readiness for the right
cost CNO Guidance 2006
7
IISRP Cost Wise Readiness
Focus mainly on high value AVDLRs - Identify
poor performers - Optimize support practices -
Balance increased reliability vs. cost
  • Objectives
  • Improve component reliability
  • increase TOW by enhancing fielded reliability
  • Reduce Weapon System life-cycle costs
  • reduce component demand, lower MMH/FH, optimize
    O/I/D capabilities, increase readiness

8
IISRP Process
Key enablers - Stakeholder buy-in - Integrated
systems and tools - Training and expertise
Cost Wise Readiness
  • Redesign is expensive and time consuming
  • ROIs typically 9 years
  • Reliability improvement must begin with
    removing inherent reliability barriers.
  • That is done by optimizing logistics support
    elements.

9
IISRP Process
  • Analyzes components worked in organic
  • activities
  • Primary focus on improving process
    effectiveness
  • Achieve goals by maximizing component Time on
    Wing
  • Ensure support processes restore component
    resistance to failure

10
IISRP Process
Root Cause Analysis to determine performance
degraders
Current behavior -3M data -MAL Code -Removal
Code -Action Taken Code -Artisan input -Shop
visits -O/I level visits
ID and Quantify Failure Modes -A Mode -B Mode
Failure Mechanisms
Corrective Action -FST -NAVICP -Fleet -DLA Concurr
ence
Monitor TOW BCM Impacts
Cooperative effort IISRP Team, O/I/D
maintainers, FST, NAVICP, DLA
11
IISRP Process Select
  • Component selection criteria established with
    stakeholders
  • Target High value x low reliability
    components
  • IISRP teams at O/I/D sites work closely with the
    Fleet, FSTs, NAVICP and DLA on selecting
    components for analysis
  • Concurrence required to initiate study on
    components

12
IISRP Process Analyze
  • IISRP Process Review
  • Normally performed in parallel with data
    collection and analysis
  • Observation of all aspects of O/I/D maintenance
    processes
  • hands-on examination of entire process
  • heavy reliance on interaction with
    artisans/technicians
  • evaluates everything from removal through
    reinstallation

13
IISRP Process Fix
  • Consensus meeting held with all involved
    stakeholders to
  • Review observations
  • Review recommendations for feasibility and reach
    consensus to accept or reject
  • Reach agreement on assignment of action items to
    cognizant personnel
  • IISRP team establishes and maintains action item
    tracking file
  • Coordinate milestone development
  • Coordinate timeline for action item completion

14

IISRP Process Measure
  • We analyze results after recommendations
    implemented
  • At the completion of every reliability study
  • Project a do nothing trend line based on
    previous 20 quarters of data
  • Estimate the impact of reliability improvements
  • Track actual performance data
  • Re-analyze non-improving components as part of
    sustainment efforts

15
Effective Reliability Investments Reverse or Slow
Cost Growth.. Over Time
IISRP Process Measure
  • Instantaneous Implementation

Real World Improvement
Function of support decisions

NOTIONAL RATE OF COST GROWTH
AVDLR / FHR TY
Implementation by Attrition
FISCAL YEAR
16
Results
17
Study Statistics
  • Through 1st qtr FYO6
  • Delivered 279 component studies
  • 122 have been on the AFAST 500
  • Other Sources include
  • AMSR, OI, FST, IWST, others
  • Generated 1457 Actions

Combined Actions with both Internal and
External requirements.
18
Studies by Platform
Total Number of Studies 279
19
Actions By Category
Total Number of Studies 279
20
Turning The Tide
Pre Study Trend
Post Study Trend
Demonstrates Improvement in Fielded Reliability
Pre Study Trend
Post Study Trend
21
Return on Investment
  • Type 1 Savings gt 21
  • Type 2 Savings gt 41
  • Overall gt 61

22
Examples
  • The following studies were completed by local
    IISRP Teams at the Naval Air Depots
  • These IISRP Teams coordinated with local FSTs,
    Fleet Maintainers, Depot production managers, and
    artisans to complete the analyses

23
E-2/C-2 Propeller
Problem Repair capability at depot
limited -unable to repair foam core due to lack
of automated foam pouring machine
Solution Provided IISRP funds
to Procure/install foam pouring Machine. FST
developed LES for repair of blades.
  • Results
  • BCM/kFH rate decreased by 39 from existing trend
    since 1Q FY03
  • Without this capability, blades exhausted by
    Sep04 with aircraft down
  • 8.7M Cost Avoidance
  • 31.7M Total Savings through 3rd qtr FY05

24
AV-8B Stab Servo-cylinder
Problem Chronic Top Ten AV-8 readiness degrader,
identified many tech pub deficiencies, O level
not following static leak limits, depot
processes not IAW manual
Solution O level trained, depot pub corrected,
artisans trained on test procedures, Depot test
stand upgraded, new seal technology
  • Results
  • 19 decrease in BCM rate since 2QFY00,
  • Depot RFIed 26 units previously in G condition
    eliminating holes in a/c and procurement of new
    servo cylinders
  • Sustainment identified new failure mode fixed
    via updated replacement solenoid found on IISRP
    sponsored OEM visit
  • Units with new type seal/ solenoid have an avg
    TOW of 900 hours, a 200 improvement

25
P-3 Fuel Flow Transmitter
Problem Number one on P-3 Top Ten Degrader list.
Multiple holes in Acft, Over 100 backorders at
time of study
Solution Corrected multiple errors in Tech pub
and retrained artisans on Test procedures.
Worked with fleet to Improve troubleshooting
procedures.
  • Results Major improvement in item availability
  • Pulled more than 400 coil assemblies back from
    scrap and retested, RFIed 310, saved 744K
    2.8M in recurring savings
  • 24 Bare firewalls and 147 backorders when study
    started all aircraft orders filled and 292 in A
    condition after study

26
F/A-18 Horizontal Servo-cylinder
Problem from 94-99 BCM rate increased 486.
Multiple O/D training issues/practices
identified, rework process steps omitted
Solution Issued LES directing 100 replacement
of dynamic seals and EHSVs, trained fleet on
allowable leakage rates, implemented
new heating/cooling procedures
  • Results
  • 39 reduction in BCM rate since 3QFY00
  • Additional reductions expected when new seals
    incorporated

27
Going Forward
  • Building Communication
  • Briefed PEO (T) APMLs 12/05
  • Briefed Air-1.0 APMLs 1/06
  • Scheduled to brief PEO (A) 5/06
  • Met with PET Team coordinator 11/05 to identify
    commonalities and
  • Review goals/objectives
  • Compare processes/tools/analysis methods
  • Develop strategy to capitalize on the each
    others strengths
  • Providing value added services to PMA/FSTs
  • Received/anticipating FY06 funding from PMA-234,
    PMA-257 and PMA-209 to conduct IISRP studies
  • Received FY06 funding from AERMIP to analyze
    results of completed analyses and look for cross
    platform applications

28
Going Forward
  • Focus turning towards common solutions vice
    individual component analysis
  • Working with AERMIP program to address
    multi-platform issues
  • Coordinate RM resource requirements- OMN, APN,
    RDTE

29
Summary
  • IISRP
  • is a key element of Cost Wise Readiness
  • has an aligned and credible process
  • has demonstrated results
  • BCM Rates - reducing or slowing the increase
  • TOW - improving or holding steady
  • continues to engage with all stakeholders to
    improve readiness and control costs
Write a Comment