Successes and Failures of PPP Projects - PowerPoint PPT Presentation

1 / 16
About This Presentation
Title:

Successes and Failures of PPP Projects

Description:

Objective of the presentation is to show some contributors of successful PPP ... finance, build and operate a section of the Autostrada A1 from Gdansk to Torun. ... – PowerPoint PPT presentation

Number of Views:78
Avg rating:3.0/5.0
Slides: 17
Provided by: WB1673
Category:

less

Transcript and Presenter's Notes

Title: Successes and Failures of PPP Projects


1
Successes and Failures of PPP Projects
  • Vickram Cuttaree
  • The World Bank
  • Europe Central Asia Region
  • Warsaw June 17, 2008

2
Introduction
  • Objective of the presentation is to show some
    contributors of successful PPP programs
  • Mexico and Chile PPP programs illustrate the
    importance of proper design of a PPP program
  • Experience in the region but also worldwide
    converge into the same essential elements
  • Strong public sector capacity
  • Appropriate PPP and sector Framework
  • Planning and solid feasibility study
  • Transparent and Competitive Procurement
  • Strong monitoring and flexibility towards
    unpredicted events

3
Investment is now less concentrated in Latin
America and East Asia
Countries with strong public sector institutions
have typically performed best. Examples include
the United Kingdom, South Africa, Australia and
Chile. These countries are not only good
examples but represent also competition for
Poland in PPP investment
Source PPIAF Database
4
Success Story Chile Road Concession Program
  • Between 1993 and 2001 Chile awarded 21 road
    concession worth US 5 billion on a competitive
    basis
  • Bidding started with smaller projects, in order
    to test the market and reduce the risk to the
    private sector
  • The bidding attracted 27 consortia and more than
    40 Chilean and foreign companies, from 10
    countries
  • PPP program is viewed as transparent and
    competitive, with only one minimum revenue
    guarantee called
  • Surveys of users, consultations with local and
    national leaders, and focus groups graded
    Concessions System at 6 on scale from 1 to 7

Source Hodges (2006)
5
(In)Famous PPP Failure Road Concession Program
in Mexico
  • Between 1987 and 1995, 52 projects (25
    competitively tendered) was awarded (largest PPP
    toll road program)
  • By the end of 1995, 34 projects had reached
    financial close for US 9.9 billion in private
    investment committed
  • Shortest concession period would win (max 15
    years), led to very high tolls
  • Concessioned roads obligated to have a parallel
    toll free road
  • Construction cost overruns averaged 25 and
    average actual revenues were about 30 below
    forecasts (only 5 projects met or exceeded
    targets)
  • Average toll road fee increased from US 0.02/km
    to US 0.17 after concessioning
  • Government took over 23 projects and paid
    outstanding debt to Mexican Banks (about US 5
    billion) and construction companies (about US
    2.6 billion)

Source Hodges (2006)
6
Lessons learned from Chile and Mexico
  • Chile
  • Procurement process was transparent
  • Focus on creating public awareness (tolling
    culture)
  • Government learned as program developed and made
    adjustments
  • Attracting international firms brought finance,
    credibility, know-how etc
  • Mexico
  • Combination of small contract duration and low
    traffic resulted in high tolls
  • Existence of free roads contributed to financial
    distress of concessionaires
  • Situation aggravated by Tequila crisis
  • Program resulted in massive Government bail-out

Source Hodges (2006)
7
International experience helps identify typical
causes of failure
Most PPP failures can be attributed to
inadequate or non-existent feasibility studies,
including unrealistic traffic forecasts and
undefined public contribution of funds.
  • Other common reasons for failure
  • Poor legal framework and enforcement
  • Weak institutional capacity and PPP strategy
  • Unrealistic revenue and cost estimations
  • Lack of thorough financial and economic analysis
  • Inappropriate sharing of risks
  • Lack of competitive procurement
  • Public resistance (willingness to pay not
    assessed)

8
Lesson Solid Revenue and Cost Estimations
Strong emphasis should be put on forecasting
revenues and costs as part of the feasibility
study. Overestimation of revenues can bankrupt
the concession
  • Hungary M1/M15 was the first toll motorway
    tendered and implemented in Central and Eastern
    Europe.
  • Construction of motorway was finished in 1995 on
    schedule and within budget.
  • Traffic volumes were about 40 lower than
    anticipated, despite the forecasts being prepared
    by independent experts.
  • High toll rate did not cover for low volume.
    Instead, it led to a court case by dissatisfied
    road users.
  • As a result, the concessionaire was unable to
    service its debt and ultimately the government
    had to take over the concession at a high cost.

CASE Hungary M1/M15 Toll Motorway Project
9
Lesson Assess willingness to pay and prepare a
communication plan
Widespread public opposition to a PPP project
can prematurely end the concession. The absence
of an assessment of willingness to pay can lead
to public dissatisfaction, and even violent
protests.
CASE Bolivia Cochabamba Water System
  • In 1999, the Bolivian government privatized the
    water system in Cochabamba by granting a 40-year
    concession to an international consortium called
    Aguas del Tunari
  • Rate structures were immediately modified, which
    resulted in increases of up to 20 in water bills
    for local families, many of whom often earn as
    little as 100/month
  • In October 1998, groups gathered in protests,
    which led to an outbreak of violence, when the
    Bolivian army killed as many as nine, injured
    hundreds and arrested several local leaders
  • Finally, Aguas del Tunari announced that the
    consortium was withdrawing from the project

10
Lesson Comply with contractual agreement
Financial profitability and sustainability is
heavily dependent on Governments respect of
contractual agreements
  • In 1989, the Don Muang Tollway (DMT) company
    received a 25-year concession from the Department
    of Highways of Thailand to build a 407 million
    segment of an elevated highway.
  • The DMT faced several problems due to
    non-fulfillment of pre-construction obligations
    by the government, which failed to remove a local
    road competing with toll revenues.
  • As a result, traffic volumes and revenues were
    less than forecast, and by October 1996 the
    tollway company could no longer service its debt.
  • The government had no option but to authorize a
    substantial toll increase and take over some of
    the DMTs existing loans

CASE Thailand Don Muang Tollway
11
Lesson Solid Legal Framework
A solid legal framework for PPP is needed to
specify the rules of the game for the private
sector and reduce the project risk , thus
improving the success rate of PPP projects.
  • In August 1997, Gdansk Transport Company obtained
    the concession to finance, build and operate a
    section of the Autostrada A1 from Gdansk to
    Torun.
  • However, the Concession Agreement could not be
    signed because key piece of PPP legislation was
    missing.
  • Multiple rounds of renegotiations and frequent
    adjustments to legislation took place in the
    following years.
  • The Concession Agreement was signed in August
    2004, 7 years after the beginning of
    negotiations.
  • The specifications of the project were
    significantly changed and the construction was
    divided into two projects, instead of the
    original plan of one project

CASE Poland A1 Toll MotorwayProject
12
Lesson Strong Institutional Arrangements
Institutional Arrangement should ensure
coordination, technical support and that checks
and balances are appropriately applied
CASE Portugal weak management of its PPP program
  • Portugal pursued its first PPPs in the mid-1990s
    to more efficiently build new infrastructure
  • The government PPP unit suffered from lack of
    experience with PPP projects and inexperienced
    staff
  • As a result, Portugals early PPPs were subject o
    constant delays and cost overruns by 2003, the
    countrys PPP-related liabilities amounted to 10
    of GDP
  • Weak public sector capacity was evident in
    insufficient risk transfer to the private sector
    and delays in giving government approvals on
    essential land and environmental aspects

13
Lesson Value of Competitive Procurement
Uncompetitive procurement gives a strong position
to the negotiating private party and can lead to
long delays and excessive cost to the government.
CASE Bulgaria Trakia Motorway Project
  • The Bulgarian Government awarded a concession
    without competitive bidding for financing,
    rehabilitating, constructing, tolling and
    operating the a section of the A1 motorway in
    2004
  • Opposition parties attacked the project on the
    basis of a lack of transparency, and high
    government contribution and construction price
  • The concessionaire asked to increase construction
    costs due to legal obstacles causing substantial
    delays and did not want to assume the risk of
    lower-than-expected traffic
  • As a result, the talks with the concessionaire
    collapsed in November 2006 and the financial
    closure is yet to be achieved

14
Lesson Mitigate Macro-economic risk and remain
flexible
An external macroeconomic shock can create an
unexpected situation for the government, whereby
it cannot comply with its contractual duties in
PPP
  • As part of a massive privatization program, the
    highest profile concession was signed in 1993
    with a consortium called Aguas Argentinas for
    water services of Buenos Aires
  • After the 2001 economic crisis, many concessions
    were renegotiated. Some were even terminated and
    the responsibility for service provision reverted
    to public entities, as was the case in Buenos
    Aires
  • When the government rescinded the concession in
    March 2006, it argued that Aguas Argentinas did
    not comply with obligations on expansion and
    quality.
  • The company replied that a freeze in tariffs when
    the Peso depreciated in 2001 substantially
    reduced the real value of tariff revenues and
    thus made it difficult to achieve the original
    targets

CASE Argentina Water System
15
Summary of Lessons from Successes and Failures
Strong international competition requires to use
international best practices in preparing,
procuring and monitoring PPP projects
Key success factors include 1. Careful planning
of PPP project 2. Solid revenue and cost
estimate 3. User willingness to pay and
communication plan 4. Extensive feasibility study
with use of PPP experts 5. Compliance with
contractual agreement 6. Appropriate Legal and
Regulatory Framework 7. Strong Institutions with
appropriate resources 8. Competitive and
transparent procurement 9. Mitigation and
flexibility in managing macro-risks
16
Success and Failures of PPP projects
THANK YOU !!! Vickram Cuttaree The World
Bank vcuttaree_at_worldbank.org
Write a Comment
User Comments (0)
About PowerShow.com