Pakistans Power Sector: Challenges faced What went wrong How to correct it - PowerPoint PPT Presentation

1 / 16
About This Presentation
Title:

Pakistans Power Sector: Challenges faced What went wrong How to correct it

Description:

Force majeure provisions have been revised and in some cases specific events ... from a Pakistan Political Force Majeure Event (Restoration) have been moved ... – PowerPoint PPT presentation

Number of Views:58
Avg rating:3.0/5.0
Slides: 17
Provided by: qamarzam
Category:

less

Transcript and Presenter's Notes

Title: Pakistans Power Sector: Challenges faced What went wrong How to correct it


1
Pakistans Power SectorChallenges faced What
went wrong How to correct it
November 21, 2007
  • Presentation by
  • Pervaiz Khan
  • CEO
  • Uch Power

2
  • Theme for Presentation
  • Challenges faced by the countrys power
    sector.
  • Question posed
  • What are the issues that are preventing foreign
    and local companies to invest in the power sector
    of Pakistan?
  • Presentation Outline
  • The presentation comprises of four parts
  • Macro level issues.
  • Recommendations.
  • Key Differences under 2002 Policy vs 1994

3
Macro Level Issues
Key Differences under 2002 Policy Vs 1994
Recommendations
Planning
  • Demandsupply projections turned out to be
    seriously flawed.

Shortages
Surplus
Shortage projected for 2007 1,457MWs
Actual shortage for 2007 2,400MWs
Source PPIB Presentation March 2005
4
Macro Level Issues
Key Differences under 2002 Policy Vs 1994
Recommendations
Planning
  • Power load centers versus fuel sources
    transmission network a balancing act.
  • Power shortages are being faced by large cities
    Karachi/Lahore.
  • Major indigenous sources of fuel gas located in
    the south of the country (e.g. Mari, Uch,
    Qadirpur)

The Tradeoff
Build plants closer to fuel Additional
investment in providing grid access and
increased transmission losses.
Build plants closer to load center Additional
investment in fuel transportation network and
reduced transmission losses.
5
Macro Level Issues
Key Differences under 2002 Policy Vs 1994
Recommendations
Planning
  • Rethink on the generation-fuel mix.
  • 67 of the installed capacity is thermal
    resulting in heavy reliance on imported liquid
    fuel and indigenous pipeline quality gas making
    it an expensive choice at US90 plus per barrel
    oil and dwindling gas reserves.
  • Lack of development of alternative indigenous
    thermal resource (coal).
  • Planning is almost non-existent for the promotion
    of ancillary industries.
  • Lack of focus on planning for the replacement of
    ageing infrastructure (transmission and
    distribution).

6
Macro Level Issues
Key Differences under 2002 Policy Vs 1994
Recommendations
Investment
  • Huge financing gap in the power sector.
  • Lack of foreign investor interest.
  • Public utilities are not profitable and are not
    able to raise finances for further investment.
  • IPPs have a limited ability to borrow money from
    the international market (multilaterals, ECAs)
    largely due to
  • 2002 policy security package
  • Macro economic stability
  • Country credit rating

7
Macro Level Issues
Key Differences under 2002 Policy Vs 1994
Recommendations
Investment
  • Investment (FDI and local), is largely
    concentrated in the generation (70) and much
    less in transmission (14). (Source Deloitte
    Touche Tohmatsu)
  • Fall in country credit rating has a positive
    correlation with the fall in FDI in the
    electricity. Zero investment at a rating level
    below CCC. (SP)

Policy
  • Power Policy 2002 a reinvention of the wheel.
  • Risk structure is not adequately balanced under
    new Policy.
  • Current policy does not cater separately for
    expansion projects.
  • Due to the overlapping roles of PPIB/NEPRA/WAPDA,
    Power Policy 2002 is not a one stop window.
  • The establishment of a final tariff has been
    subjected to several rounds of reduction
    negotiations.

8
Macro Level Issues
Key Differences under 2002 Policy Vs 1994
Recommendations
Planning
Short Term (2008 2009)
  • There is an urgent need to develop accurate
    forecasts of the power requirements. Estimates
    for the Peak and Base load requirements need
    to be developed for the short, medium and long
    term.
  • The institutional capacity of PPIB/NEPRA needs to
    be enhanced.
  • Well structured phased plan (short, medium, long
    term) should be put in place. Considering that we
    are behind schedule by 3 5 years in terms of
    adding a few thousands of MWs of additional
    capacity, rented turbines and IPPs in pipeline
    appears to be the most logical and probably the
    only choice.

9
Macro Level Issues
Key Differences under 2002 Policy Vs 1994
Recommendations
Planning
Medium Term (2010 2012)
  • Ministry of Petroleum and Natural Resources shall
    be asked to allocate additional gas for power
    generation to plug the medium term demand-supply
    gap. Estimated gas reserves are 27tcf. Generation
    of 2,000MWs over 25 years will consume 3.13tcf of
    pipeline quality gas. Conversely in todays RFO
    prices the same generation will require a foreign
    exchange import bill of US1.1 billion p.a.
  • Alternative energy sources should also be
    considered.

10
Macro Level Issues
Key Differences under 2002 Policy Vs 1994
Recommendations
Planning
Long Term (2012 onwards)
  • Diversification of generation fuel mix shall
    become part of the long term plans and
    alternative energy sources shall be developed
    (e.g. Wind).
  • Development and utilization of coal reserves is a
    feasible option in long term. Pakistans
    generation on coal is zero notwithstanding that
    we have one of the largest coal reserves in the
    world.
  • Pakistans hydel potential has remained largely
    untapped. Construction of large and small dams
    shall be considered.

11
Macro Level Issues
Key Differences under 2002 Policy Vs 1994
Recommendations
Investment
  • GoP shall consider dedicating a portion of
    infrastructure funds to bring equity to finance
    large scale IPPs.
  • Future investment requirement shall be
    forecasted, as accurately as possible, and steps
    shall be taken to ensure that the future gap
    could be plugged through
  • Private funds mobilization
  • Launching a PSEDF II of US500 million to US1
    billion with assistance of multilaterals and
    bilateral agencies.
  • Special funds shall be allocated in Annual
    Development Plan for upgrading and expanding the
    fuel transportation and electricity grid
    infrastructures.

12
Macro Level Issues
Key Differences under 2002 Policy Vs 1994
Recommendations
Investment
  • The liquidity in the sector shall be improved by
  • Setting a price structure that shall truly
    reflect cost
  • Reduce under collections and thefts
  • The security package offered in the policy shall
    be bankable.

Policy
  • PPIB shall be made a one window facility in a
    true sense. It should be given the mandate and
    authority to coordinate / facilitate project
    implementation.
  • The overlaps between various institutions shall
    be eliminated. (WAPDA PPIB NEPRA Ministry of
    Petroleum Natural Resources)

13
Macro Level Issues
Key Differences under 2002 Policy Vs 1994
Recommendations
Policy
  • Tariff should truly reflect cost of the power
    producer.
  • Existing projects should be the first port of
    call for capacity additions as they have the
    basic infrastructure already in place.
  • GoP shall introduce policies to promote ancillary
    industries in the country (operations and
    maintenance, engineering).

14
Macro Level Issues
Key Differences under 2002 Policy Vs 1994
Recommendations
Power Policy 2002 vs - 1994
  • Governing law is now Pakistan law instead of
    English law whereas arbitration is under UNCITRAL
    Rules instead of ICSID / ICC Rules.
  • The payment /performance obligations of fuel
    supplier by GoP withdrawn.
  • Lenders rights to assign and transfer have been
    substantially weakened. Lenders ability to sell
    and transfer the Complex in enforcement of their
    security is now subject to GoP approval.
  • Transfers by initial shareholder to another
    initial shareholder or to the Affiliates of
    initial shareholders during six year lock-in
    period have been made more restrictive.

15
Macro Level Issues
Key Differences under 2002 Policy Vs 1994
Recommendations
Power Policy 2002 vs 1994 contd
  • Force majeure provisions have been revised and in
    some cases specific events have been curtailed,
    amended or abridged (e.g Water Event, Lapse of
    Consent, availability of Fuel, political events
    occurring outside Pakistan).
  • Provisions related to the payment of special
    compensation in the case of a force majeure event
    has entirely been deleted.
  • Provisions in relation to the consequences of a
    Change in Law requiring a material modification
    or capital addition or damage to the Complex
    arising from a Pakistan Political Force Majeure
    Event (Restoration) have been moved from IA to
    PPA.
  • Indemnification provisions have been deleted
    including defense of claims and double jeopardy
    provisions. The Company can not challenge fines
    imposed by the GoP (section 9.2 to 9.7 of the
    existing IA).

16
Macro Level Issues
Key Differences under 2002 Policy Vs 1994
Recommendations
Power Policy 2002 vs 1994 contd
  • Cure periods are curtailed for Company Events of
    Default whereas in case of GoP Events of Default,
    cure periods are now more generous (grace period
    for a payment default by power purchaser has been
    extended from 5 to 30 days).
  • Delay in obtaining Consents does not result in
    extension of Required COD and Company has no
    termination rights in respect of prolonged delays
    in obtaining Consents.
  • The cap of US100,000 for additional security to
    meet unusual security requirements has been
    removed.
  • The Commissioning Tests have been restricted to
    10.
  • Significant increase in required Annual
    Availability of the Project.
Write a Comment
User Comments (0)
About PowerShow.com