Assessment of the safety upgrading for Unit 2 of Armenian NPP I - PowerPoint PPT Presentation

1 / 15
About This Presentation
Title:

Assessment of the safety upgrading for Unit 2 of Armenian NPP I

Description:

Assessment of the safety upgrading for Unit 2 of Armenian NPP I&C related issues ... Physical and galvanic isolation of measuring channels was performed though there ... – PowerPoint PPT presentation

Number of Views:26
Avg rating:3.0/5.0
Slides: 16
Provided by: shahenpo
Category:

less

Transcript and Presenter's Notes

Title: Assessment of the safety upgrading for Unit 2 of Armenian NPP I


1
Assessment of the safety upgrading for Unit 2 of
Armenian NPP IC related issues
  • Tsolak Malakyan, Nuclear Radiation Safety
    Centre (NRSC)
  • Gagik Matnishyan, Armenian Nuclear Regulatory
    Authority (ANRA)

Regional Workshop on Modernization Projects of
NPP Instrumentation and Control Systems Related
to Power Uprates and Licence Renewals Project
(RER/4/027)Portoroz, Slovenia14-18 April 2008
2
Introduction
  • Performed modernizations for IC improvement for
    ANPP were based on recommendations coming from
    IAEA-TECDOC-640
  • NRSC with GRS sponsorship in 2006 provided
    assessment of the safety upgrading of Unit 2 of
    Armenian NPP. General objective of the project is
    complex assessment of performed/planned
    safety-related modernisations for Armenian NPP
    Unit 2. To reach declared project goal following
    two stages/tasks were implemented
  • Task A Adaptation and completion of safety
    issues list presented in IAEA TECDOC 640 (Ranking
    of safety issues for WWER-440 model 230 NPP) was
    performed.
  • Task B Detailed analysis was performed for
    safety issues selected by GRS experts generally
    based on rank of particular issue presented in
    IAEA TECDOC-640 (mostly analysis was performed
    for III and IV category issues).

3
Task A Adaptation and completion of safety
issues list related of IC
  • 16 safety related issues for IC were assessed
  • 12 safety related issues from IAEA TECDOC-649
  • 3 additional safety related issues proposed by
    GRS/Riskaudit experts
  • And 1 additional safety related issue selected
    from IAEA TECDOC 1044 (IAEA Generic safety
    issues )

4
Task A Adaptation and completion of safety
issues list related of IC
  • Conclusion of this stage are that all considering
    issues escape of 1 are relevant for ANPP initial
    design

5
Task B Detailed analysis safety issues list
related of IC
  • The goals of task B2 is development of technical
    report with assessment of technical solutions
    completeness for elimination of safety
    deficiencies.
  • Here only information related safety issues of
    categories IV and III are presented
  • Reliability of IC Equipment (III)
  • IC Redundancy, Separation and Independence (IV)
  • IC / Electrical Equipment Qualification (III)
  • Control Room Habitability/Shutdown Panel (III)

6
Task B Detailed analysis safety issues list
related of IC
  • Reliability of IC Equipment (III)
  • Issue description IC equipment still used is
    very old fashioned (e.g. electrochemical
    switches, relays) and its reliability is
    questionable. The causes include deterioration
    with age, difficulty of maintenance and testing
    and the need for frequent attention.
  • Modernisation
  • The replacement of non-seismic relays in
    emergency protections and interlocks circuits was
    performed with seismic relays at ANPP.
  • The non-seismic sensors and secondary instruments
    operated in protection and interlock circuits
    were replaced with seismic ones.
  • New digital instruments were installed at MCR of
    Unit 2
  • network frequency, current frequency on 28NA,
    29NA buses
  • Unit total electrical output
  • measuring sets of TG-3,4 revolutions
  • electrical capacity of TG-3,4.
  • The instrumentation stock of ANPP main and
    auxiliary systems was significantly renewed
  • Additional P measuring instruments were
    installed in SG-RCP compartment and in this
    connection new interlocks on confinement
    ventilation systems were implemented.
  • The number of H measuring channels in 2SG-1?6
    was significantly increased.
  • Additional ?P measuring sets (two sets for
    every RCP) were installed on 2RCP-1?6 and in this
    connection the EP-III actuation logic was
    modified by 2 out of 3 logic.

7
Task B Detailed analysis safety issues list
related of IC
  • Reliability of IC Equipment (III)
  • Modernisation
  • Additional ?P between SG and MSH and P
    instrument sets were installed in MSH (to provide
    channelling principle).
  • The differential transformer sensors and
    transmitters were replaced with 0?5mA standard
    output sensors.
  • All IC sensors and instruments were replaced on
    DG-3, 4, 5, 6.
  • All protection removal keys were eliminated from
    reactor protection generation circuits.
  • Safety parameters display system were
    implemented at Unit 2 with their individual
    sensors qualified for operation in environmental
    and seismic conditions.
  • Physical and galvanic isolation of measuring
    channels was performed though there are still
    common circuits left.The whole instrumentation
    stock is subjected to departmental and laboratory
    tests in compliance with annual test schedule.
  • Modernization of SG level regulators (performed
    during 2006 outage)

8
Task B Detailed analysis safety issues list
related of IC
  • Reliability of IC Equipment (III)
  • Modernisation
  • Replacement of source range neutron flux
    monitoring instrumentation (performed during 2006
    outage)
  • There were installed four sets for level
    controlling and four sets of four-meter level
    controllers on each SG.
  • Upon the installation of these instruments the
    interlock and protection set-points were isolated
    though there are still some common circuits.
  • Modernization of old automatic reactor power
    regulation (ARM) system
  • Effectiveness of modernization
  • It is necessary to identify those IC which have
    significant influence on NPP safety and perform
    measures to increase their reliability. This
    analysis could be done using PSA model developed
    for ANPP.

9
Task B Detailed analysis safety issues list
related of IC
  • IC Redundancy, Separation and Independence (IV)
  • Issue description There are numerous instances
    where redundancy, physical and electrical
    separation and independence of safety related
    instrumentation channels are not adequately
    provided
  • Modernisation
  • The type of activation logic is that all the
    channels of emergency protection system are
    designed with logic 2 out of 3 (or 2 out of 6 for
    the steam generator protection for all 6 loops).
  • They mainly use de energize-to actuate technique.
    Only one channel (delta pressure on reactor
    coolant pump) use energize-to actuate technique.
  • All protections and interlocks of reactor are
    powered from six buses of 220V DC (3 bushings
    from 2BAB-1 and 3 bushings from BAB-2), the loss
    of even 4 corresponding bus wont effect the
    safety system operation.
  • The Unit 2 MCR, the process alarm circuits are
    powered from two I category reliability buses
    (according to Automatic Stand-by Start-up
    circuit) of 28NA and 29NA AC buses.
  • Modernization is foreseen in 2008 aimed to
    separation (physically and electrically) of
    emergency protection systems channels as
    possible (during implementation of modernization
    ANPP will fully follow and respect the
    international design rules (diversity,
    redundancy, physical separation etc.))
  • Effectiveness of modernization
  • Foreseen modernizations will increase
    independence of the existing safety related
    instrumentation, however modernization needs to
    include measurements which will assure total
    independency between A and B channels of
    emergency protection system. Otherwise planned
    modernization only partially will cover this
    issue.

10
Task B Detailed analysis safety issues list
related of IC
  • IC / Electrical Equipment Qualification (III)
  • Issue description At the time the design was
    made, the environmental and seismic qualification
    of instrumentation and electrical equipment was
    not addressed, and there was no backfitting
    program developed in that field up to now.
  • Modernisation
  • Measures are foreseen aimed to safety-related
    equipment qualification. It is planned to perform
    this work in 2008 based on current international
    qualification standards
  • The Engineered Seismic Protection System is
    replaced with a new Engineered Seismic Protection
    System-2, interlocking logic is simplified for
    the functioning of ESPS.
  • Cable lines, supply systems, protections,
    interlocks and other consumers of safety systems
    and safety related systems are reconstructed in
    the form of two divergent category I and II power
    supply systems.
  • Seismic non-qualified relay, detectors and gauges
    are replaced with seismic-resistant ones.
  • ANPP put into operation new diagnostic systems
  • acoustic primary leak detection system (ALUS)
  • primary loose object detection system (KUS).

11
Task B Detailed analysis safety issues list
related of IC
  • IC / Electrical Equipment Qualification (III)
  • Modernisation
  • Feasibility study has been done for replacement
    of an old ??-500?? information computing system
    with an advanced complete set that meets the
    current seismic requirements.
  • Cables and communication instrumentation of the
    unit were analysed in the view of their
    resistance to short circuits, recommendations
    were developed on improvement of reliability and
    thermal resistance of cables and instrumentation
  • automatic fire alarm for switchboard rooms,
    intake air-ducts of MCR, ECB implemented on the
    basis of seismic qualified components was
    documented
  • documentation was developed and ANPP
    reconstructed the snubber displacement control
    system
  • rooms containing IC and safety related electric
    equipment are seismic qualified against current
    requirements
  • up to 1976 both IC, electric equipment and
    switchboards were tested against seismic
    resistance.

12
Task B Detailed analysis safety issues list
related of IC
  • IC / Electrical Equipment Qualification (III)
  • Modernisation
  • The tests were performed on vibration stand in
    the frequency range of 0?30Hz and peak ground
    acceleration (0.4g and 1.08g). In 1976-1977 the
    second phase of tests was performed on vibration
    stand for seismic resistance of IC, electric
    equipment and switchboard devices with due
    consideration of their reinforcement and
    anchoring which demonstrated their seismic
    resistance.
  • seismic tests resulted in replacement of CK-40
    type batteries with seismic resistant VARTA
    type, mounted on seismic resistant stacks.
  • In 1998 motors on all Main Stop Valves were
    replaced with impermeable motors.
  • Effectiveness of modernization
  • A performed modernization allows qualifying
    seismically IC/Electrical equipment at ANPP.
    However other environmental hazards were not
    considered.

13
Task B Detailed analysis safety issues list
related of IC
  • Control Room Habitability/Shutdown Panel
  • Issue description There is insufficient
    provision to maintain control room habitability.
    In case of main control room inhabitability or
    unavailability, there is no other centralized
    location from where a safe shutdown can be
    performed .
  • Modernisation
  • In case of shut down and MCR unavailable, it is
    possible for the operators to monitor the plant
    with following parameters Level in SG-1-6,
    Primary pressure, Level in Prz, Temperature in
    cold and hot legs, Temperature difference between
    hot and cold legs, Temperature in Prz. Neutron
    flux could be monitored from reactor building
    central hall (Shelter room - reserve emergency
    cooldown panels IC is qualified as
    safety-related equipment), from the shelter room,
    which is located in the reactor building. These
    parameters are displayed in MCR during normal
    operation (same sensors used for MCR and reserve
    emergency cooldown panel)
  • Implementation of adequate air filtering,
    supplied to MCR is foreseen in 2009 as well as
    flying objects protection installation
  • Implementation of reserve control panel is
    foreseen in 2009

14
Task B Detailed analysis safety issues list
related of IC
  • Control Room Habitability/Shutdown Panel
  • Modernisation
  • By design following measures were implemented to
    address this issue
  • Separation of scram buttons - MCR, SUZ-2 panel
    and Central control panel.
  • Measures are taken for rooms and buildings
    seismic stability increase.
  • Replacement of single-wing doors in cable tunnels
    and in turbine hall on the door with 90 min.
    fire-resistance is performed.
  • Gas masks, air bottles, and communication are
    existing at MCR.
  • Emergency personnel protection procedures are
    developed related
  • Effectiveness of modernization
  • The original design of MCR at ANPP provides
    sufficient base to maintain control room
    habitability in case of main control room
    inhabitability or unavailability.
    Implementation of reserve control panel will
    allows performing safe shutdown in case of
    unavailability of MCR.

15
Conclusion
  • Performed modernizations for IC improvement for
    ANPP were based on recommendations coming from
    IAEA-TECDOC-640
  • Most of recommendations for III and IV category
    issues were addressed
  • Implementation of the rest recommendations is
    included in modernization program for 2006-2016
  • Further modernizations on IC will be developed
    based on safety assessments (SAR and PSA results)
Write a Comment
User Comments (0)
About PowerShow.com