Title: Assessment of the safety upgrading for Unit 2 of Armenian NPP I
1Assessment of the safety upgrading for Unit 2 of
Armenian NPP IC related issues
- Tsolak Malakyan, Nuclear Radiation Safety
Centre (NRSC) - Gagik Matnishyan, Armenian Nuclear Regulatory
Authority (ANRA)
Regional Workshop on Modernization Projects of
NPP Instrumentation and Control Systems Related
to Power Uprates and Licence Renewals Project
(RER/4/027)Portoroz, Slovenia14-18 April 2008
2Introduction
- Performed modernizations for IC improvement for
ANPP were based on recommendations coming from
IAEA-TECDOC-640 - NRSC with GRS sponsorship in 2006 provided
assessment of the safety upgrading of Unit 2 of
Armenian NPP. General objective of the project is
complex assessment of performed/planned
safety-related modernisations for Armenian NPP
Unit 2. To reach declared project goal following
two stages/tasks were implemented - Task A Adaptation and completion of safety
issues list presented in IAEA TECDOC 640 (Ranking
of safety issues for WWER-440 model 230 NPP) was
performed. - Task B Detailed analysis was performed for
safety issues selected by GRS experts generally
based on rank of particular issue presented in
IAEA TECDOC-640 (mostly analysis was performed
for III and IV category issues).
3Task A Adaptation and completion of safety
issues list related of IC
- 16 safety related issues for IC were assessed
- 12 safety related issues from IAEA TECDOC-649
- 3 additional safety related issues proposed by
GRS/Riskaudit experts
- And 1 additional safety related issue selected
from IAEA TECDOC 1044 (IAEA Generic safety
issues )
4Task A Adaptation and completion of safety
issues list related of IC
- Conclusion of this stage are that all considering
issues escape of 1 are relevant for ANPP initial
design
5Task B Detailed analysis safety issues list
related of IC
- The goals of task B2 is development of technical
report with assessment of technical solutions
completeness for elimination of safety
deficiencies. - Here only information related safety issues of
categories IV and III are presented - Reliability of IC Equipment (III)
- IC Redundancy, Separation and Independence (IV)
- IC / Electrical Equipment Qualification (III)
- Control Room Habitability/Shutdown Panel (III)
6Task B Detailed analysis safety issues list
related of IC
- Reliability of IC Equipment (III)
- Issue description IC equipment still used is
very old fashioned (e.g. electrochemical
switches, relays) and its reliability is
questionable. The causes include deterioration
with age, difficulty of maintenance and testing
and the need for frequent attention. - Modernisation
- The replacement of non-seismic relays in
emergency protections and interlocks circuits was
performed with seismic relays at ANPP. - The non-seismic sensors and secondary instruments
operated in protection and interlock circuits
were replaced with seismic ones. - New digital instruments were installed at MCR of
Unit 2 - network frequency, current frequency on 28NA,
29NA buses - Unit total electrical output
- measuring sets of TG-3,4 revolutions
- electrical capacity of TG-3,4.
- The instrumentation stock of ANPP main and
auxiliary systems was significantly renewed - Additional P measuring instruments were
installed in SG-RCP compartment and in this
connection new interlocks on confinement
ventilation systems were implemented. - The number of H measuring channels in 2SG-1?6
was significantly increased. - Additional ?P measuring sets (two sets for
every RCP) were installed on 2RCP-1?6 and in this
connection the EP-III actuation logic was
modified by 2 out of 3 logic.
7Task B Detailed analysis safety issues list
related of IC
- Reliability of IC Equipment (III)
- Modernisation
- Additional ?P between SG and MSH and P
instrument sets were installed in MSH (to provide
channelling principle). - The differential transformer sensors and
transmitters were replaced with 0?5mA standard
output sensors. - All IC sensors and instruments were replaced on
DG-3, 4, 5, 6. - All protection removal keys were eliminated from
reactor protection generation circuits. - Safety parameters display system were
implemented at Unit 2 with their individual
sensors qualified for operation in environmental
and seismic conditions. - Physical and galvanic isolation of measuring
channels was performed though there are still
common circuits left.The whole instrumentation
stock is subjected to departmental and laboratory
tests in compliance with annual test schedule. - Modernization of SG level regulators (performed
during 2006 outage)
8Task B Detailed analysis safety issues list
related of IC
- Reliability of IC Equipment (III)
- Modernisation
- Replacement of source range neutron flux
monitoring instrumentation (performed during 2006
outage) - There were installed four sets for level
controlling and four sets of four-meter level
controllers on each SG. - Upon the installation of these instruments the
interlock and protection set-points were isolated
though there are still some common circuits. - Modernization of old automatic reactor power
regulation (ARM) system - Effectiveness of modernization
- It is necessary to identify those IC which have
significant influence on NPP safety and perform
measures to increase their reliability. This
analysis could be done using PSA model developed
for ANPP.
9Task B Detailed analysis safety issues list
related of IC
- IC Redundancy, Separation and Independence (IV)
- Issue description There are numerous instances
where redundancy, physical and electrical
separation and independence of safety related
instrumentation channels are not adequately
provided - Modernisation
- The type of activation logic is that all the
channels of emergency protection system are
designed with logic 2 out of 3 (or 2 out of 6 for
the steam generator protection for all 6 loops). - They mainly use de energize-to actuate technique.
Only one channel (delta pressure on reactor
coolant pump) use energize-to actuate technique. - All protections and interlocks of reactor are
powered from six buses of 220V DC (3 bushings
from 2BAB-1 and 3 bushings from BAB-2), the loss
of even 4 corresponding bus wont effect the
safety system operation. - The Unit 2 MCR, the process alarm circuits are
powered from two I category reliability buses
(according to Automatic Stand-by Start-up
circuit) of 28NA and 29NA AC buses. - Modernization is foreseen in 2008 aimed to
separation (physically and electrically) of
emergency protection systems channels as
possible (during implementation of modernization
ANPP will fully follow and respect the
international design rules (diversity,
redundancy, physical separation etc.)) - Effectiveness of modernization
- Foreseen modernizations will increase
independence of the existing safety related
instrumentation, however modernization needs to
include measurements which will assure total
independency between A and B channels of
emergency protection system. Otherwise planned
modernization only partially will cover this
issue.
10Task B Detailed analysis safety issues list
related of IC
- IC / Electrical Equipment Qualification (III)
- Issue description At the time the design was
made, the environmental and seismic qualification
of instrumentation and electrical equipment was
not addressed, and there was no backfitting
program developed in that field up to now. - Modernisation
- Measures are foreseen aimed to safety-related
equipment qualification. It is planned to perform
this work in 2008 based on current international
qualification standards - The Engineered Seismic Protection System is
replaced with a new Engineered Seismic Protection
System-2, interlocking logic is simplified for
the functioning of ESPS. - Cable lines, supply systems, protections,
interlocks and other consumers of safety systems
and safety related systems are reconstructed in
the form of two divergent category I and II power
supply systems. - Seismic non-qualified relay, detectors and gauges
are replaced with seismic-resistant ones. - ANPP put into operation new diagnostic systems
- acoustic primary leak detection system (ALUS)
- primary loose object detection system (KUS).
11Task B Detailed analysis safety issues list
related of IC
- IC / Electrical Equipment Qualification (III)
- Modernisation
- Feasibility study has been done for replacement
of an old ??-500?? information computing system
with an advanced complete set that meets the
current seismic requirements. - Cables and communication instrumentation of the
unit were analysed in the view of their
resistance to short circuits, recommendations
were developed on improvement of reliability and
thermal resistance of cables and instrumentation - automatic fire alarm for switchboard rooms,
intake air-ducts of MCR, ECB implemented on the
basis of seismic qualified components was
documented - documentation was developed and ANPP
reconstructed the snubber displacement control
system - rooms containing IC and safety related electric
equipment are seismic qualified against current
requirements - up to 1976 both IC, electric equipment and
switchboards were tested against seismic
resistance.
12Task B Detailed analysis safety issues list
related of IC
- IC / Electrical Equipment Qualification (III)
- Modernisation
- The tests were performed on vibration stand in
the frequency range of 0?30Hz and peak ground
acceleration (0.4g and 1.08g). In 1976-1977 the
second phase of tests was performed on vibration
stand for seismic resistance of IC, electric
equipment and switchboard devices with due
consideration of their reinforcement and
anchoring which demonstrated their seismic
resistance. - seismic tests resulted in replacement of CK-40
type batteries with seismic resistant VARTA
type, mounted on seismic resistant stacks. - In 1998 motors on all Main Stop Valves were
replaced with impermeable motors. - Effectiveness of modernization
- A performed modernization allows qualifying
seismically IC/Electrical equipment at ANPP.
However other environmental hazards were not
considered.
13Task B Detailed analysis safety issues list
related of IC
- Control Room Habitability/Shutdown Panel
- Issue description There is insufficient
provision to maintain control room habitability.
In case of main control room inhabitability or
unavailability, there is no other centralized
location from where a safe shutdown can be
performed . - Modernisation
- In case of shut down and MCR unavailable, it is
possible for the operators to monitor the plant
with following parameters Level in SG-1-6,
Primary pressure, Level in Prz, Temperature in
cold and hot legs, Temperature difference between
hot and cold legs, Temperature in Prz. Neutron
flux could be monitored from reactor building
central hall (Shelter room - reserve emergency
cooldown panels IC is qualified as
safety-related equipment), from the shelter room,
which is located in the reactor building. These
parameters are displayed in MCR during normal
operation (same sensors used for MCR and reserve
emergency cooldown panel) - Implementation of adequate air filtering,
supplied to MCR is foreseen in 2009 as well as
flying objects protection installation - Implementation of reserve control panel is
foreseen in 2009
14Task B Detailed analysis safety issues list
related of IC
- Control Room Habitability/Shutdown Panel
- Modernisation
- By design following measures were implemented to
address this issue - Separation of scram buttons - MCR, SUZ-2 panel
and Central control panel. - Measures are taken for rooms and buildings
seismic stability increase. - Replacement of single-wing doors in cable tunnels
and in turbine hall on the door with 90 min.
fire-resistance is performed. - Gas masks, air bottles, and communication are
existing at MCR. - Emergency personnel protection procedures are
developed related - Effectiveness of modernization
- The original design of MCR at ANPP provides
sufficient base to maintain control room
habitability in case of main control room
inhabitability or unavailability.
Implementation of reserve control panel will
allows performing safe shutdown in case of
unavailability of MCR.
15Conclusion
- Performed modernizations for IC improvement for
ANPP were based on recommendations coming from
IAEA-TECDOC-640 - Most of recommendations for III and IV category
issues were addressed - Implementation of the rest recommendations is
included in modernization program for 2006-2016 - Further modernizations on IC will be developed
based on safety assessments (SAR and PSA results)