Title: Dec 2006
1Schedule toward the SC-ECAL Beam Test _at_ DESY
Dec 2006
Jan 2007
Feb 2007
1
2
3
4
1
2
3
4
1
2
3
4
ACFA
KEK
Japan -Korea
Beam Test _at_ DESY Feb 25 Mar 29
Shipping Feb-14
Delivery of 400 MPPCs
Delivery of 360 MPPCs
Settle MPPC Operation voltage
Prepare MPPC mass check system
MPPC numbering Mass check
MPPC mass check.
MPPC baking and soldering
MPPC soldering
Direct-readout megastrip source scan
Test assembly Install LED/Temp. monitor
system Prepare shipping
megastrip Assembly source scan
Megastrip bench test
Fabrication of megastrip layer components
Finalize module design
Fabrication of Frame / light shielding structure
Establish LED / Temperature monitoring system
Prepare Trigger / Veto counters
MPPC study (response curve)
Analysis code / Event display
Contact DESY (DC gas, safety issue, etc)