SAFETY and COMMISSIONING - PowerPoint PPT Presentation

1 / 19
About This Presentation
Title:

SAFETY and COMMISSIONING

Description:

Agreed with TS on a new sharing of responsibilities at P2 in 2004 ... tapis volant. Hans Taureg. Safety and Commissioning. 11. LHCC Installation Review 3 ... – PowerPoint PPT presentation

Number of Views:3248
Avg rating:3.0/5.0
Slides: 20
Provided by: htau
Category:

less

Transcript and Presenter's Notes

Title: SAFETY and COMMISSIONING


1
SAFETY and COMMISSIONING
2
Introductory remarks
  • Remarks on safety issues
  • Of general nature
  • Concerning several systems and their interference
  • No detector specific issues
  • Commissioning treated from the safety point of
    view

3
OUTLINE
  • Safety organization
  • Safety
  • Access
  • Communications
  • Gas
  • Commissioning
  • Co-activities of commissioning and installation
  • Operating conditions

4
Safety organization
  • Agreed with TS on a new sharing of
    responsibilities at P2 in 2004
  • Adjusted the organization and working habits
    accordingly
  • The installation work is defined as a series of
    Work packages
  • The organization of the execution of the work
    packages is shared between PH and TS
  • All installation activities are described in task
    procedures and checked by a special safety
    coordinator
  • Task procedures and inspection reports are
    documented on EDMS, see link in EDMS 530025
  • This organization is now established and works
    well

5
Safety Organisation
6
Safety organization
  • Access and safety procedures for ALICE
  • Documented in EDMS 452686
  • Explained at several collaboration meetings
  • Wearing of personal protection
  • Reinforced compliance
  • Supervision of work and safety
  • Missing personnel for permanent supervision of
    all work sites at P2

7
Access
  • Access to sub-detectors
  • Inside L3 solenoid
  • µ chambers
  • Restricted areas
  • L3 case
  • µ arm

8
Access inside L3
  • RB24 side
  • Passage along side of space frame
  • Access below space frame

9
Access inside L3
  • Platforms on RB26 doors
  • Access to TOF and TRD being improved

10
Access µ chambers
tapis volant
11
Restricted areas
  • Inside L3 solenoid
  • RB26 side during installation
  • Access essentially from RB24 side
  • Escape route through FASS
  • Follow two person rule (Safety Code A6)
  • Limit number of persons in the area
  • 4 persons with TPC in nominal position
  • 8 persons during ITS etc installation

12
Restricted areas
Access to TPC, ITS on RB26 side and FASS
Back frame
Space frame
TPC
FASS
Front absorber
13
Restricted areas
  • µ arm
  • FASS
  • Access from µ arm side, escape route through L3
  • Dipole
  • Access between L3 and dipole
  • Access between ST3 and ST4
  • Below µ arm
  • Follow two person rule (Safety Code A6)
  • Limit number of persons in each area
  • 2 persons between tracking stations 1 to 4
  • 6 persons below µ arm

14
Restricted areas
Access ST1 / ST2
Access ST3 / ST4
Access ST2 / ST3
15
Communications
  • Communications between spaces inside the
    detector and the outside world
  • Below µ arm
  • Inside µ arm (FASS, Dipole)
  • Inside L3 solenoid
  • Have to verify functionality

16
Gas
  • During installation / commissioning only
    non-flammable gas mixtures will be used
  • HMPID will fill CH4 shortly before first beam
  • Gas detection and ODM available
  • ODM inside L3 and below µ arm
  • Reinforced ventilation inside L3 during
    installation

17
Commissioning
  • Separate installation and commissioning
  • Installation during day time
  • Commissioning during night time
  • Avoid co-activities in each area
  • Minimize co-activities by scheduling and
    coordination
  • Limit on number of persons
  • Limit from access means

18
Commissioning
  • Detector operating conditions during installation
  • Definition of conditions under way
  • Examples
  • Restrictions on HV and LV
  • No TPC drift HV during installation in solenoid
  • Power down nearby detectors / modules
  • Permit TOF / TRD commissioning during ITS
    installation

19
Conclusions
  • Safety organization in place and working
  • Concerns about permanent supervision
  • No intrinsically dangerous operations
  • Strict scheduling, coordination and procedures
    have to limit risks from
  • Access difficulties
  • Concurrent activities
Write a Comment
User Comments (0)
About PowerShow.com