Title: This chapter provides an outline of the definitions, standards, and procedures you need to know when
1GuardrailTerminals
- This chapter provides an outline of the
definitions, standards, and procedures you need
to know when selecting the necessary type
terminals. - The chapters topics are
- Weak Post Terminals
- Strong Post Terminals
- Gaps Between Guardrail Runs
2CHAPTER 9 OBJECTIVES
- You will be able to perform the following tasks
after finishing this chapter - list the methods for terminating a guardrail
system - describe the standards for these methods
- list the reasons for selecting a given type of
terminal
3GUARDRAIL TERMINALS
- The main purposes of a terminal are to help
- reduce serious injuries to a vehicle's occupant
- and minimize vehicle damage.
- You will ensure a terminal will achieve this by
- installing it as tested and approved under NCHRP
350 test criteria - developing the necessary tension at the end of
the system to redirect a vehicle or absorb energy
4CURRENT WEBSITES
- All currently approved guardrail terminals can be
found on these websites which cover NCHRP 350
requirements - http//Virginiadot.org/business/locdes/nchrp350-in
dex.asp - http//safety.fhwa.dot.gov/programs/roadside_hardw
are.htm - Manufacturers specific products with detailed
descriptions and specifications are linked
through the FHWA site.
5WEAK POST CABLE SYSTEM(STD. GR-3 TERMINAL)
PLAN VIEW
ELEVATION
- The cables are tapered down to the ground at both
ends and anchored in a concrete deadman under the
current standard. The cables are preferably
anchored in a back slope. - The location of the terminal should be determined
by the LON procedure. - If the anchor is to be buried in the back slope,
the full height of the barrier should be carried
75 feet upstream of the hazard before flaring
beyond the ditch line and tying into the concrete
deadman.
CABLE GUARDRAIL TERMINAL 501.06
6WEAK POST CABLE SYSTEM(STD. GR-3 TERMINAL)
- Constant tension is maintained in the cable
system with springs as part of one anchor, and
with turnbuckles to adjust the tension based on
the ambient temperature at installation as
required by VDOT specifications.
7WEAK POST W-BEAM SYSTEM(STD. GR-8, TYPE II
TERMINAL)
- There is no NCHRP 350 approved run-on terminal
for the weak post W-beam system (Std. GR-8) at
this time. - This turned-down anchorage which develops the
necessary tension may be used on run-off
locations for one-way traffic. - Run-on conditions must include a strong post
terminal and 50 feet of Std. GR-2 to transition
to the weak post W-beam system.
TYPE II TERMINAL TREATMENT (RUN-OFF ANCHORAGE)
501.15
8WEAK POST W-BEAM SYSTEM(STD. GR-8, TYPE II
TERMINAL)
This is the old GR-8 No picture was available for
the new installation
9STRONG POST W-BEAM SYSTEM(STD. GR-6 BURIED IN
BACK SLOPE TERMINAL)
- Use this standard when the front slope is 41
Max. or flatter. - Burying the guardrail end in a back slope is the
most desirable method for terminating the
guardrail system. The end cannot be hit directly
if it is buried.
TERMINAL TREAMENT FOR W-BEAM GUARDRAIL 501.09
10New GR-6 with Double Rail
11STRONG POST W-BEAM SYSTEM(STD. GR-6 BURIED IN
BACK SLOPE TERMINAL)
- When burying a terminal, you must
- provide the necessary anchorage to develop the
required tension forces - place it deep enough ( minimum) so that the end
of the rail will not become exposed
The next two slides show anchorage methods.
TERMINAL TREAMENT FOR W-BEAM GUARDRAIL 501.09
12STRONG POST W-BEAM SYSTEM(STD. GR-6 BURIED IN
BACK SLOPE TERMINAL)
- This anchoring method uses three 6 foot steel
posts, spaced at 3' 1½" intervals, as the end
anchor. Each post is attached to the guardrail
by four bolts. Additionally, each post has bolted
or welded steel plates attached.
END ANCHORAGE (POST) 501.10
13STRONG POST W-BEAM SYSTEM(STD. GR-6 BURIED IN
BACK SLOPE TERMINAL)
- This anchoring method uses concrete deadman,
measuring 3' 2' 2', as the end anchor. The
guardrail is attached to the deadman through a
terminal connector by bolt anchors, which are
either cast in-place or drilled. - The end anchor must have a minimum of 1 foot of
cover. The cover must be compacted on the same
plane as the normal ground slope. No mounds or
bubbles can be present after the ground has
been tamped.
END ANCHORAGE (CONCRETE) 501.10
14STRONG POST W-BEAM SYSTEM(STD. GR-6 BURIED IN
BACK SLOPE TERMINAL)
- The height of the rail should be measured from
the graded shoulder extended, when there is a
ditch at the bottom of the front slope. - The maximum distance from the ground line to the
bottom of the W-beam rail is 18 inches.
TERMINAL TREATMENT FOR W-BEAM GUARDRAIL 501.09
15STRONG POST W-BEAM SYSTEM(STD. GR-6 BURIED IN
BACK SLOPE TERMINAL)
REMEMBER
The GR-6 can be installed using the TOP RAIL only
if the slopes and ditch dimensions warrant this.
- A bottom rail shall be added to the system when
the height between the ground line and the bottom
of the top rail exceeds 18 inches.
- Taper both W-beam rails down to maintain the 18
inch height if the clearance under the bottom
rail exceeds 18".
TERMINAL TREATMENT FOR W-BEAM GUARDRAIL 501.09
16STRONG POST W-BEAM SYSTEM(STD. GR-6 BURIED IN
BACK SLOPE TERMINAL)
- The posts must be 8 feet long when a bottom rail
is used.
- The maximum exposure between the bottom rail and
the groundline is 18 inches.
TERMINAL TREATMENT FOR W-BEAM GUARDRAIL 501.09
17STRONG POST W-BEAM SYSTEM(STD. GR-6 BURIED IN
BACK SLOPE TERMINAL)
- Regardless of whether one or two rails are used,
the flare must not cross the ditch bottom until
it has extended a minimum of 75 feet upstream
from the beginning of the hazard being shielded,
or the cut to fill slope transition.
18IMPROPERLY INSTALLED EXAMPLE(STD. GR-6)
- This system has an improperly installed single
rail GR-6 cut slope terminal. The end of the
rail is exposed a vehicle would be speared if
the end were hit directly. The standard calls
for the rail to be anchored in the slope by
having at least two posts buried a minimum
of one foot in the ground.
19See the results of a build up and a rain storm
soon there after. This terminal should have been
extended and buried deeper as the standards
indicate. NO MOUNDS keep the slopes the same.
20(No Transcript)
21Not a good example of the GR-6 installation. The
slope does not exist.
22This location is not a good candidate for a GR-6.
Embankment not adequate, To me the GR should have
been extended to get the proper LON then install
a GR-9. They are trying to create an area that
does not exist.
23IMPROPERLY INSTALLED EXAMPLE (STD. GR-6)
- The end of this terminal is buried under a
bubble of soil. This mound of soil was piled on
the terminal in order to meet the specification
that the terminal be buried under a minimum of
1 foot of soil. Bubbles or mounds are not
acceptable. The soil can sluff down the slope
or erode over time, thus exposing the terminal.
24STRONG POST W-BEAM SYSTEMSITE PREPARATION
A key component to proper installation of
guardrail terminals is proper site preparation
25STRONG POST W-BEAM SYSTEM(STD. GR-7 FLARED
TERMINAL)
- This terminal configuration is one which flares
the end of the terminal away from the normal
line of the barrier. - Only a flare of 4 feet is acceptable under
current standards.
BREAKAWAY CABLE TERMINAL 4' FLARE 501.11
26This is a GR-7 Slotted Rail Terminal.
27STRONG POST W-BEAM SYSTEM(STD. GR-7 FLARED
TERMINAL)
FLEAT
SRT-350
- A vehicle hitting the end of a flared terminal,
either head-on or at an angle, will break away
the end and pass through the guardrail with
little absorption of energy.
- The FLEAT, however, absorbs the energy of a
head-on impact.
- It is, therefore, imperative that a large run out
area free of hazards be available downstream from
the beginning of the terminal.
28STRONG POST W-BEAM SYSTEM(STD. GR-7 FLARED
TERMINAL)
Proper Delineation
- This run out area would desirably be as long as
250 feet and as wide as 40 feet, but at least the
width of the design clear zone.
- There should be no obstacle within 75 feet of the
beginning of the terminal.
29IMPROPERLY INSTALLED EXAMPLE(STD. GR-7)
- The guardrail's stand up trailing terminal on the
other side of the median ends 12' 6" from the
beginning of the flared terminal. This placement
could result in a vehicle that crashes through
the flared terminal possibly being speared by
the stand up trailing terminal.
12' 6"
30STRONG POST W-BEAM SYSTEM(STD. GR-7 FLARED
TERMINAL)
- These terminal systems are proprietary
(patented). The manufacturers installation
instructions must be followed precisely, as
tested and approved.
- Each system uses a breakaway cable anchoring
system to develop the terminal tension. - Specific product details are available on the
manufacturer's web site.
31IMPROPERLY INSTALLED EXAMPLE(STD. GR-7)
- This GR-7 terminal had been damaged and repaired.
However, the replacement terminal does not have
the proper 4 foot parabolic flare.
32STRONG POST W-BEAM SYSTEM(STD. GR-7 FLARED
TERMINAL)
- The offsets are measured from a tangential line
extended from the end of the guardrails standard
section if the terminal is on the inside of the
curve.
BREAKAWAY CABLE TERMINAL 4' FLARE 501.13
33STRONG POST W-BEAM SYSTEM(STD. GR-7 FLARED
TERMINAL)
- The offset will be held at the standard section
offset if the resulting curve is so sharp as to
make the offset less than the standard section
offset.
BREAKAWAY CABLE TERMINAL 4' FLARE 501.13
34GR-9 terminal used without having to add site
preparation for GR-7
35GR-9 with good runout area, but the approach area
with curb should be clearer.
curb
36STRONG POST W-BEAM SYSTEM(STD. GR-9 PARALLEL
TERMINAL)
Cable Assembly
Length of Need
Offset Strut
Bearing Plate
Cable Anchor
Guardrail Exit Slot (Away from Traffic)
Begin Typ. Guardrail
Guardrail Extruder
6'- 3"
6'- 3"
6'- 3"
50'
Pay Limits GR-9 Terminal
Traffic
- These terminals are straight systems that may be
placed parallel with the roadway.
ALTERNATE BREAKAWAY CABLE TERMINAL NO FLARE
501.18
37(No Transcript)
38STRONG POST W-BEAM SYSTEM(STD. GR-9 PARALLEL
TERMINAL)
- For small angle impacts, these systems are
designed to allow a vehicle striking the
terminal at a small angle to be brought to a
controlled stop through absorption of the
impacts energy.
- The vehicle will pass through this system with
little absorption of energy and little speed
reduction in higher angle end impacts.
39STRONG POST W-BEAM SYSTEM(STD. GR-9 PARALLEL
TERMINAL)
- Some parallel systems use a large impact head at
the terminals beginning which protrudes in front
of the guardrail. The head may be offset from 1
to 2 feet. This offset, however, must be
installed over a 50 foot straight line flare.
40STRONG POST W-BEAM SYSTEM(STD. GR-9 PARALLEL
TERMINAL)
- GR-9 parallel terminals can be offset up to two
feet over the entire 50 foot length of the
terminal. This flare is only on the first 25
feet, which may cause the terminal to kink since
the impact head will have to change direction
midway at the break point of the offset.
25'
41STRONG POST W-BEAM SYSTEM(STD. GR-9 PARALLEL
TERMINAL)
- These terminal systems are proprietary
(patented). The manufacturers installation
instructions must be followed precisely, as
tested and approved.
- There should be no hazard within the first 75
feet of this system as measured from the
terminals beginning. - Specific product details are available on the
manufacturer's web site.
42STRONG POST W-BEAM SYSTEM(TERMINALS FOR CURBED
SECTIONS)
- There are currently no terminals approved for use
in conjunction with curbs. - Two recommended methods for installing
terminals on high speed roadways with curbs
are - to lower the curb
- to taper back from the curb
43STRONG POST W-BEAM SYSTEM(TERMINALS FOR CURBED
SECTIONS)
- Method 1
- Lower the curb to 2 inches of height or less
for approximately 50 feet in advance of the
terminalsend so that the vehicle is at the
appropriate height when contact is made.
- For parallel terminals the 2 inch height should
be carried an additional 12 feet beyond the
terminals upstream end and the terminals end
should be offset 1 foot to keep the impact head
behind the curbs face. - The 2 inch height should be carried 37 feet
beyond the terminals upstream end in flared
terminals.
44STRONG POST W-BEAM SYSTEM(TERMINALS FOR CURBED
SECTIONS)
- Method 2
- Taper the guardrail back from the curbs face on
a 251 taper for 50 feet. Raise the rails
height an amount equal to the curbs height. Use
a crashworthy terminal based on this line of 251
extended.
45Mountable Curb Transition from 4 inches to 2
inches Height at Terminal End
46STRONG POST W-BEAM SYSTEM(TRAILING END)
- The trailing, or downstream, end of a guardrail
system is not likely to be hit by traffic if it
is outside the clear zone.
- The necessary tension of the system needs to be
developed at the trailing end by using
rectangular washers only on the last 50' of
guardrail.
47STRONG POST W-BEAM SYSTEM(BREAKAWAY CABLE
ANCHORAGE)
- Terminal systems with exposed ends, such as the
Std. GR-7 and GR-9, use an anchored cable to
develop the tension required to handle
downstream impacts.
- The terminals vertical end is broken away upon
end-on impacts, thus allowing the vehicle to
continue downstream.
48WEAK POST W-BEAM SYSTEM (TRAILING END TERMINALS)
- Turned-down terminals that develop the necessary
tension may be used. - The full capability of the guardrail system must
be available at the end of the hazard. - This system may be used to terminate a guardrail
which is outside the clear zone for opposing
traffic where there is still some likelihood of
an opposing traffic hit.
Old GR-8 installation
New design
TYPE II TERMINAL TREATMENT (RUN-OFF ANCHORAGE)
501.15
49WEAK POST W-BEAM SYSTEM (TRAILING END TERMINALS)
- The weak post turned-down terminal Std.GR-8, Type
II with full anchorage is acceptable as the
trailing end on a weak post guardrail system.
TYPE II TERMINAL TREATMENT (RUN-OFF ANCHORAGE)
501.15
50GAPS BETWEEN GUARDRAIL RUNS
Eliminate Terminals
ConnectGuardrail
- Eliminate the terminals and connect the two runs
when the end of one guardrail run terminates
within 200 feet of the beginning of the next
downstream run of the same type of guardrail and
there is no obvious reason for the gap.
51SUMMARYAPPROACH TERMINALS
- Gaps of less than 200 feet between successive
runs of guardrail should be closed
- Terminals must provide two functions
- Develop the required tension
- Minimize injury severity for end impacts
- New installations of turndowns are acceptable for
weak post systems only under low speed run-off
conditions (45 mph or less)
52SUMMARYAPPROACH TERMINALS(cont.)
- Buried in back slope (Std. GR-6) is most
desirable since
- It cannot spear
- It is farther from the travel way
- Generally will not be gotten behind (no LON
calculation) - The maximum exposure between the bottom rail and
the ground is 18 inches - Provide tension anchor
53SUMMARYAPPROACH TERMINALS(cont.)
- Proprietary flared terminal (Std. GR-7)
- Allows a vehicle to pass on through for end
impacts - Must have adequate runout area behind
54SUMMARYAPPROACH TERMINALS(cont.)
- Proprietary parallel terminal (Std. GR-9)
- Bring low angle impacting vehicles to a
controlled stop - Higher angled impacts pass on through
- If terminal includes an impact head, its
desirable to have straight flare of 2 feet (at
least 1 foot minimum)
55SUMMARYAPPROACH TERMINALS(cont.)
- All remaining hardware after posts break away
must not exceed 4 inches projection in a 5 feet
chord
56SUMMARYTRAILING END TERMINALS
- Tension in standard section must be carried
beyond the point of need
- The end of the hazard for one direction travel
- The LON for two direction roadway
- Weak post W-beam (Std. GR-8) may use a turndown
577 SELF-CHECK QUESTIONS
- 1. Define terminal.
- 2. One function or purpose of a terminal is to
- a. mark the end of the clear zone
- b. hold a delineator
- c. minimize personal injuries and damage to a
vehicle
58ANSWERS
- 1. Define terminal.
- The end of the guardrail system.
- 2. One function or purpose of a terminal is to
- c. minimize personal injuries and damage to a
vehicle
597 SELF-CHECK QUESTIONS(cont.)
- 3. The currently approved method for terminating
a cable system is to - a. anchor the cables in a concrete deadman
- b. weld the cables together and bolt to the
ground - c. taper the cables into a final post
60ANSWER
- 3. The currently approved method for terminating
a cable system is to - a. anchor the cables in a concrete deadman
617 SELF-CHECK QUESTIONS(cont.)
- 4. The best way to terminate a strong post system
is to - a. cap the rail
- b. wrap the rail around the post
- c. bury the end in a cut slope
- 5. Why is this method the best method?
62ANSWERS
- 4. The best way to terminate a strong post system
is to - c. bury the end in a cut slope
- 5. Why is this method the best method?
- Because nothing is exposed nothing can be hit.
637 SELF-CHECK QUESTIONS(cont.)
- 6. You must provide a minimum of _____ of cover
when burying a beam. You cant _____ or ____ the
dirt over the rail. - 7. Why must you anchor and bury the rail deep?
Why cant you just cover it with dirt?
64ANSWERS
- 6. You must provide a minimum of 1 foot of cover
when burying a beam. You cant bubble or mound
the dirt over the rail. - 7. Why must you anchor and bury the rail
deep?Why cant you just cover it with dirt? - You must anchor and bury the rail in order to
get the necessary tension. Mounded dirt could
erode or sluff off over time the end could
become exposedand become a hazard.