Title: OGA Technical Seminar Distribution Integrity Management and the Integrity Management Audit Process
1OGA Technical SeminarDistribution Integrity
Management and the Integrity Management Audit
Process
2Progress towards Distribution Integrity
Management Regulations
3Inspector Generals Report
- July 20, 2004 report to US House of Rep.
- Gas Distribution Lines make up 85 of the 2.1
million miles of natural gas pipelines in the
United States. - Natural gas distribution pipelines over the last
10 years have experienced over 4 times the number
of fatalities and 3.5 times the number of
injuries when compared to hazardous liquid and
transmission pipelines.
4Inspector Generals Report
- Distribution
- 174 fatalities
- 662 injuries
- Transmission and Hazardous Liquids
- 43 fatalities
- 178 injuries
5Transmission/Hazardous Liquid
- 20,000 integrity threats have been identified and
remediated in less than 16 of the lines
requiring inspections. - Mileage still needing baseline integrity
inspections - 135,000 Miles Hazardous Liquid
- 326,000 Miles of Transmission
6Inspector Generals Strategy
- Three Elements of DOTs IG Plan
- Understanding the infrastructure
- Identifying and characterizing the threats
- Determining how best to manage the known risks
(prevention and mitigation issues)
7Inspector Generals Report
- Noted AGF study to be presented in December 2004
- By March 31, 2005, OPS will finalize its approach
for requiring operators of gas distribution
pipelines to implement some form of integrity
management elements
8American Gas Foundation Report
- Looked at three major areas
- Natural Gas Distribution Industry Safety
Performance - Current Regulations and Industry Practices that
address threats to the natural gas distribution
infrastructure - Differences between Gas Transmission and Gas
Distribution Infrastructure
9American Gas Foundation Report- Findings
- Key differences noted between distribution and
transmission infrastructure - Type of infrastructure
- System operating pressures
- Materials of construction
- Typical failure mechanisms
- Inspection methods
- Class locations
- Connection to customers
10American Gas Foundation Report- Findings
- Visual inspection of piping is more prevalent in
distribution than transmission systems. - Many operators actively participate in damage
prevention organizations. - Some one call programs allow exemptions from one
call membership and not all include
fines/penalties for offenders.
11American Gas Foundation Report- Findings
- Current pipeline regulations address threats to
distribution infrastructure. - Operators employ prevention and mitigation
practices in excess of those required by law. - Downward trend in incident fatalities and
injuries (1990-2002) - Major cause of incidents is outside force damage
third party damage
12Allegro Report
- Completed in 2004 for OPS
- Evaluated five years of incident data (1999-2003)
- Attempted to reclassify them into the new cause
categories listed in the current incident
reporting forms - 67 incidents were outside force damage
- 38 excavation and mechanical damage
- 11 vehicle damage-(contributed to 25 of fatal
incidents)
13DOT Action Plan General Approach
- Building on AGF Report, DIGIT Committee, State
and Industry Initiatives - Involve all stakeholders
- Assure flexibility to the maximum extent
practicable - Identify strategies to implement selected
integrity management options (Details Forthcoming)
14Action Plan Team Structure
- Executive Steering Team
- Coordinating Team
- Task Teams
15Team Structure
- Executive Steering Team
- State Commissioners (4),
- Industry/Trade Association (4),
- Public (1),
- Fire Marshall (1),
- OPS (Stacey Gerard)
16Team Structure
- Coordinating Team
- NAPSR (2)
- NARUC (1)
- AGA/APGA (2)
- Public (1)
- OPS (Tom Fortner, Mike Israni)
- Observers (4-Industry, 4-State)
17Team Structure
- Task Teams
- (federal/ state/ industry subject matter experts)
- Strategic Options
- Risk Control
- Data
- Outside Force
18Strategic Options
- Identify options to implement for distribution
system safety
19Risk Control
- Evaluate the effectiveness and applicability of
the current regulations as well a reviewing
current risk control practices in government and
industry
20Data
- Assemble existing information to identify the
type, significance, and trends for threats
affecting distribution pipelines
21Outside Force
- Review Common Ground Alliance database and
related information to identify practices being
used to prevent outside force damage and the
extent of the applications
22Implementation Options to be considered
- Structured Nation-Wide Education Program
- National/local advertising campaign similar
to call-before you-dig - Model State Legislation
- Prepare draft language that could be
incorporated by States into legislation
addressing distribution pipeline safety issues.
23Implementation Options to be considered
- National Consensus Standard or Guidelines
- National Consensus Standard or other guidance
document detailing specific practices for
improving distribution pipeline safety under
different circumstances. - Guidance Document for Adoption by States
- Similar to above except made mandatory. States
could adopt in whole or in part based on local
needs.
24Implementation Options to be considered
- Simple Flexible Federal Regulation
- Regulation requiring that each operator have an
integrity plan that reflects (a) knowledge of
infrastructure, (b) consideration of applicable
threats, (c) activities to reduce risk, and (d)
process for monitoring performance. - Prescriptive Federal Regulation
- Regulation similar to the integrity management
rule for gas transmission pipelines
25Implementation Options to be considered
- Development of Innovative Safety Technology
- Support research and development of techniques
to assess the integrity of small-diameter,
networked pipeline systems of varying materials.
26Action Plan -- Schedule
- Initial Meeting of Executive Steering Team (with
Coordinating Team) March 16-17 - Task Teams Meeting March 29-31
- Public meeting September
- Recommendations to Executive Steering Team
December - Interim products/progress available on OPS
web/Docket
27Excess Flow Valves
- Older OPEN NTSB recommendation to OPS
- Allegro Report identified 101 incidents where
excess flow valves possibly might have mitigated
consequences - Statewide survey sent out this week- responses
due by April 15, 2005 - Will be looked at by the Risk Control and Data
groups - Mandates forthcoming???
- Part of the Distribution IMP rules???
- OPS is anticipating a public meeting possibly as
early as June 2005
28OPS Web Site
29Transmission Integrity Management Inspections
for Ohio
30Specific Deadlines
- Past Deadlines
- By June 17, 2004 operators were to have started
their baseline integrity assessments as outlined
in November 17, 2003 Advisory Bulletin - By August 31, 2004 begin semi-annual reporting
of the four performance measures - By December 17, 2004- All operators must have a
written integrity management plan - Future Deadlines
- 50 Baseline Assessments of covered segments to
be completed by 12/17/2007 - Finish Baseline Assessments on covered segments
12/17/12 - Reassess Covered Pipeline Every 7 Years
31Ohio Integrity Management
- Operators without HCAs
- Documentation must be maintained to demonstrate
that the operator evaluated the system for HCAs - Will need to have a procedure that would identify
HCAs if conditions change around the pipeline
facilities- An operator must be able to
demonstrate that it has periodically evaluated
its pipeline for HCAs - For transmission pipelines operating below 30
percent of SMYS in class 3 or 4 locations but not
in an HCA, enhanced protection against
third-party damage must be implemented in
accordance with 192.935(d). - Operators will not have to have an integrity
management plan until they identify HCAs in
their pipeline system
32Incorporates by Reference
- If there is a conflict between the regulations
and the standards then the regulations prevail - Must/Shall Statements mandatory
- Should Statements are recommended
33Operators Plans/Framework
- Aspects an operator should have completed
- Identify HCAs
- Identify Threats
- Baseline assessment plan
- Remediation??
34Operators Plans/Framework
- Framework allowance
- Rule has allowances for framework aspects of the
parts of an operators integrity management plan-
i.e. prevention and mitigation, - Outlines will NOT be acceptable- must have
minimal process detail - Certain aspects such as HCA Identification,
Baseline Assessments, Remediation, etc. should be
more detailed
35Gas Integrity Management Plan
- Describe how relevant decisions will be made, by
whom, and timeline - Remember that you will need to document
procedures and processes- this is a new concept
to operators
36Inspection Forms
- Will utilize the federally developed protocol
inspection form - Questions currently available on the OPS
integrity management website
37Protocol Questions
- 14 sets of questions (A-N)
- Most emphasis on these areas
- A- Identify HCAs
- B- Baseline Assessment Plan
- C- Identify Threats, Data Integration, and Risk
Assessment - D- DA Plan (If Applicable)
- E- Remediation
- I- Performance Measures
- J- Recordkeeping
38Ohio Inspections
- Regional Training- End of May for Central Region-
Seamus Mulligan and Jill Henry - Ohio will begin inspection in late June early
July - Initial round of inspections to be completed in
2005
39Initial Screening Questions
- List of screening questions has been
developed-(Hopefully send the first week of
April) - Will be sent out to the transmission operators
for completion by the end of April 2005. - These questions will help us prioritize the
inspection schedule and determine if a pre-audit
meeting is necessary. - Will help us determine which protocol questions
will be applicable.
40Ohio IMP Audits
- Pre-audit meeting will only be scheduled as
necessary - Will probably ask for a copy of the plan prior to
the audit for review - Anticipate most audits being under a week (larger
operators will be scheduled for two weeks)-
screening questions will help estimate audit time
41Special Issues/Concerns
- Dont wait until the audit to bring up questions-
please ask now! - We are trying to address everyones concerns
equally and apply the rules consistently - Anticipate issues for LDCs operating small
amounts of Transmission - Regulations are complicated-dont expect to be an
expert
42OPS Web Site
43Further Information
- Jill Henry
- at
- 614-728-2137
- or
- jill.henry_at_puc.state.oh.us