OGA Technical Seminar Distribution Integrity Management and the Integrity Management Audit Process - PowerPoint PPT Presentation

1 / 43
About This Presentation
Title:

OGA Technical Seminar Distribution Integrity Management and the Integrity Management Audit Process

Description:

Identify strategies to implement selected integrity management options (Details Forthcoming) ... or other guidance document detailing specific practices for improving ... – PowerPoint PPT presentation

Number of Views:70
Avg rating:3.0/5.0
Slides: 44
Provided by: jilla3
Category:

less

Transcript and Presenter's Notes

Title: OGA Technical Seminar Distribution Integrity Management and the Integrity Management Audit Process


1
OGA Technical SeminarDistribution Integrity
Management and the Integrity Management Audit
Process
  • April 1, 2005

2
Progress towards Distribution Integrity
Management Regulations
3
Inspector Generals Report
  • July 20, 2004 report to US House of Rep.
  • Gas Distribution Lines make up 85 of the 2.1
    million miles of natural gas pipelines in the
    United States.
  • Natural gas distribution pipelines over the last
    10 years have experienced over 4 times the number
    of fatalities and 3.5 times the number of
    injuries when compared to hazardous liquid and
    transmission pipelines.

4
Inspector Generals Report
  • Distribution
  • 174 fatalities
  • 662 injuries
  • Transmission and Hazardous Liquids
  • 43 fatalities
  • 178 injuries

5
Transmission/Hazardous Liquid
  • 20,000 integrity threats have been identified and
    remediated in less than 16 of the lines
    requiring inspections.
  • Mileage still needing baseline integrity
    inspections
  • 135,000 Miles Hazardous Liquid
  • 326,000 Miles of Transmission

6
Inspector Generals Strategy
  • Three Elements of DOTs IG Plan
  • Understanding the infrastructure
  • Identifying and characterizing the threats
  • Determining how best to manage the known risks
    (prevention and mitigation issues)

7
Inspector Generals Report
  • Noted AGF study to be presented in December 2004
  • By March 31, 2005, OPS will finalize its approach
    for requiring operators of gas distribution
    pipelines to implement some form of integrity
    management elements

8
American Gas Foundation Report
  • Looked at three major areas
  • Natural Gas Distribution Industry Safety
    Performance
  • Current Regulations and Industry Practices that
    address threats to the natural gas distribution
    infrastructure
  • Differences between Gas Transmission and Gas
    Distribution Infrastructure

9
American Gas Foundation Report- Findings
  • Key differences noted between distribution and
    transmission infrastructure
  • Type of infrastructure
  • System operating pressures
  • Materials of construction
  • Typical failure mechanisms
  • Inspection methods
  • Class locations
  • Connection to customers

10
American Gas Foundation Report- Findings
  • Visual inspection of piping is more prevalent in
    distribution than transmission systems.
  • Many operators actively participate in damage
    prevention organizations.
  • Some one call programs allow exemptions from one
    call membership and not all include
    fines/penalties for offenders.

11
American Gas Foundation Report- Findings
  • Current pipeline regulations address threats to
    distribution infrastructure.
  • Operators employ prevention and mitigation
    practices in excess of those required by law.
  • Downward trend in incident fatalities and
    injuries (1990-2002)
  • Major cause of incidents is outside force damage
    third party damage

12
Allegro Report
  • Completed in 2004 for OPS
  • Evaluated five years of incident data (1999-2003)
  • Attempted to reclassify them into the new cause
    categories listed in the current incident
    reporting forms
  • 67 incidents were outside force damage
  • 38 excavation and mechanical damage
  • 11 vehicle damage-(contributed to 25 of fatal
    incidents)

13
DOT Action Plan General Approach
  • Building on AGF Report, DIGIT Committee, State
    and Industry Initiatives
  • Involve all stakeholders
  • Assure flexibility to the maximum extent
    practicable
  • Identify strategies to implement selected
    integrity management options (Details Forthcoming)

14
Action Plan Team Structure
  • Executive Steering Team
  • Coordinating Team
  • Task Teams

15
Team Structure
  • Executive Steering Team
  • State Commissioners (4),
  • Industry/Trade Association (4),
  • Public (1),
  • Fire Marshall (1),
  • OPS (Stacey Gerard)

16
Team Structure
  • Coordinating Team
  • NAPSR (2)
  • NARUC (1)
  • AGA/APGA (2)
  • Public (1)
  • OPS (Tom Fortner, Mike Israni)
  • Observers (4-Industry, 4-State)

17
Team Structure
  • Task Teams
  • (federal/ state/ industry subject matter experts)
  • Strategic Options
  • Risk Control
  • Data
  • Outside Force

18
Strategic Options
  • Identify options to implement for distribution
    system safety

19
Risk Control
  • Evaluate the effectiveness and applicability of
    the current regulations as well a reviewing
    current risk control practices in government and
    industry

20
Data
  • Assemble existing information to identify the
    type, significance, and trends for threats
    affecting distribution pipelines

21
Outside Force
  • Review Common Ground Alliance database and
    related information to identify practices being
    used to prevent outside force damage and the
    extent of the applications

22
Implementation Options to be considered
  • Structured Nation-Wide Education Program
  • National/local advertising campaign similar
    to call-before you-dig
  • Model State Legislation
  • Prepare draft language that could be
    incorporated by States into legislation
    addressing distribution pipeline safety issues.

23
Implementation Options to be considered
  • National Consensus Standard or Guidelines
  • National Consensus Standard or other guidance
    document detailing specific practices for
    improving distribution pipeline safety under
    different circumstances.
  • Guidance Document for Adoption by States
  • Similar to above except made mandatory. States
    could adopt in whole or in part based on local
    needs.

24
Implementation Options to be considered
  • Simple Flexible Federal Regulation
  • Regulation requiring that each operator have an
    integrity plan that reflects (a) knowledge of
    infrastructure, (b) consideration of applicable
    threats, (c) activities to reduce risk, and (d)
    process for monitoring performance.
  • Prescriptive Federal Regulation
  • Regulation similar to the integrity management
    rule for gas transmission pipelines

25
Implementation Options to be considered
  • Development of Innovative Safety Technology
  • Support research and development of techniques
    to assess the integrity of small-diameter,
    networked pipeline systems of varying materials.

26
Action Plan -- Schedule
  • Initial Meeting of Executive Steering Team (with
    Coordinating Team) March 16-17
  • Task Teams Meeting March 29-31
  • Public meeting September
  • Recommendations to Executive Steering Team
    December
  • Interim products/progress available on OPS
    web/Docket

27
Excess Flow Valves
  • Older OPEN NTSB recommendation to OPS
  • Allegro Report identified 101 incidents where
    excess flow valves possibly might have mitigated
    consequences
  • Statewide survey sent out this week- responses
    due by April 15, 2005
  • Will be looked at by the Risk Control and Data
    groups
  • Mandates forthcoming???
  • Part of the Distribution IMP rules???
  • OPS is anticipating a public meeting possibly as
    early as June 2005

28
OPS Web Site
  • http//ops.dot.gov

29
Transmission Integrity Management Inspections
for Ohio
30
Specific Deadlines
  • Past Deadlines
  • By June 17, 2004 operators were to have started
    their baseline integrity assessments as outlined
    in November 17, 2003 Advisory Bulletin
  • By August 31, 2004 begin semi-annual reporting
    of the four performance measures
  • By December 17, 2004- All operators must have a
    written integrity management plan
  • Future Deadlines
  • 50 Baseline Assessments of covered segments to
    be completed by 12/17/2007
  • Finish Baseline Assessments on covered segments
    12/17/12
  • Reassess Covered Pipeline Every 7 Years

31
Ohio Integrity Management
  • Operators without HCAs
  • Documentation must be maintained to demonstrate
    that the operator evaluated the system for HCAs
  • Will need to have a procedure that would identify
    HCAs if conditions change around the pipeline
    facilities- An operator must be able to
    demonstrate that it has periodically evaluated
    its pipeline for HCAs
  • For transmission pipelines operating below 30
    percent of SMYS in class 3 or 4 locations but not
    in an HCA, enhanced protection against
    third-party damage must be implemented in
    accordance with 192.935(d).
  • Operators will not have to have an integrity
    management plan until they identify HCAs in
    their pipeline system

32
Incorporates by Reference
  • If there is a conflict between the regulations
    and the standards then the regulations prevail
  • Must/Shall Statements mandatory
  • Should Statements are recommended

33
Operators Plans/Framework
  • Aspects an operator should have completed
  • Identify HCAs
  • Identify Threats
  • Baseline assessment plan
  • Remediation??

34
Operators Plans/Framework
  • Framework allowance
  • Rule has allowances for framework aspects of the
    parts of an operators integrity management plan-
    i.e. prevention and mitigation,
  • Outlines will NOT be acceptable- must have
    minimal process detail
  • Certain aspects such as HCA Identification,
    Baseline Assessments, Remediation, etc. should be
    more detailed

35
Gas Integrity Management Plan
  • Describe how relevant decisions will be made, by
    whom, and timeline
  • Remember that you will need to document
    procedures and processes- this is a new concept
    to operators

36
Inspection Forms
  • Will utilize the federally developed protocol
    inspection form
  • Questions currently available on the OPS
    integrity management website

37
Protocol Questions
  • 14 sets of questions (A-N)
  • Most emphasis on these areas
  • A- Identify HCAs
  • B- Baseline Assessment Plan
  • C- Identify Threats, Data Integration, and Risk
    Assessment
  • D- DA Plan (If Applicable)
  • E- Remediation
  • I- Performance Measures
  • J- Recordkeeping

38
Ohio Inspections
  • Regional Training- End of May for Central Region-
    Seamus Mulligan and Jill Henry
  • Ohio will begin inspection in late June early
    July
  • Initial round of inspections to be completed in
    2005

39
Initial Screening Questions
  • List of screening questions has been
    developed-(Hopefully send the first week of
    April)
  • Will be sent out to the transmission operators
    for completion by the end of April 2005.
  • These questions will help us prioritize the
    inspection schedule and determine if a pre-audit
    meeting is necessary.
  • Will help us determine which protocol questions
    will be applicable.

40
Ohio IMP Audits
  • Pre-audit meeting will only be scheduled as
    necessary
  • Will probably ask for a copy of the plan prior to
    the audit for review
  • Anticipate most audits being under a week (larger
    operators will be scheduled for two weeks)-
    screening questions will help estimate audit time

41
Special Issues/Concerns
  • Dont wait until the audit to bring up questions-
    please ask now!
  • We are trying to address everyones concerns
    equally and apply the rules consistently
  • Anticipate issues for LDCs operating small
    amounts of Transmission
  • Regulations are complicated-dont expect to be an
    expert

42
OPS Web Site
  • http//ops.dot.gov

43
Further Information
  • Jill Henry
  • at
  • 614-728-2137
  • or
  • jill.henry_at_puc.state.oh.us
Write a Comment
User Comments (0)
About PowerShow.com