Seismic Isolation Retrofit Plan for the LIGO Livingston Observatory - PowerPoint PPT Presentation

1 / 9
About This Presentation
Title:

Seismic Isolation Retrofit Plan for the LIGO Livingston Observatory

Description:

Seismic Isolation Retrofit Plan for the LIGO Livingston Observatory. Dennis ... Improved isolation for the Mode Cleaner optics may be necessary HAM chambers ... – PowerPoint PPT presentation

Number of Views:63
Avg rating:3.0/5.0
Slides: 10
Provided by: sand56
Category:

less

Transcript and Presenter's Notes

Title: Seismic Isolation Retrofit Plan for the LIGO Livingston Observatory


1
Seismic Isolation Retrofit Plan for the LIGO
Livingston Observatory
  • Dennis Coyne
  • 29 Nov 2001

2
Issues
  • Spiky seismic noise 1 - 3 Hz band
  • related to human activity, especially cutting
    lumber
  • worst at y end, appears as wide band noise
    through narrow band filter
  • coincident with transmission peak in test mass
    isolation stack and seismic amplification in the
    soil under the Y-end station
  • precludes interferometer lock during work day
  • Rayleigh surface waves vertical/ horizontal
    1.5/ 1, 200 - 300 meters/ sec
  • Most likely growing with epoch, tracking
    population
  • 1988 LSU survey not evident
  • 1995 Rohay study about 1/ 2 as large and 1/ 2
    rate of today
  • need to include margin in fix
  • Strategy to deal with the noise
  • higher peak current controller short term, adds
    noise
  • active external isolation short study, feedback,
    feed forward.
  • need to be installed before reaching design
    sensitivity - 1 year

3
Improved Seismic Isolation
  • Improved isolation is essential for Test Masses
    BSC Chambers
  • Need factor of 20 reduction in the rms motion
    between 1 and 5 Hz (Firm requirements are being
    developed)
  • Improved isolation for the Mode Cleaner optics
    may be necessary HAM chambers
  • Simulation is being developed to study the effect
    of the resulting frequency noise modest means
    of reducing the rms

4
Improved Seismic Isolation
  • Industry
  • No current commercial off-the-shelf system is
    directly applicable
  • Have contacted some isolation specialty firms
    not promising
  • Reluctant to place the responsibility
    out-of-house as the problem is clearly unique
    challenging for industry
  • Will continue to study adaptation of TMCs STACIS
    system others possibly
  • Fine Actuators
  • Existing single degree of freedom actuation
    system (piezoelectric) used for tidal correction
    and microseismic feedforward compensation could
    be employed for isolation (feedback or
    feedforward)
  • Considerable cross-coupling in the stack modes
    makes this approach unlikely to succeed
  • Experiments at Livingston are planned

5
Improved Seismic Isolation
  • Tuned Mass Damping
  • Passive method to increase modal damping
    requires (perhaps brief) entry into the vacuum
    system
  • Unlikely to get more than a reduction of a factor
    of 8
  • May suffice for the HAM stacks, or may help an
    active system on the BSC
  • Analysis is underway
  • Active 6-dof pre-isolator
  • Preferred approach
  • retrofit fine/coarse actuation with an active
    pre-isolation system under the existing passive
    isolation stacks hope to preserve alignment
  • Leading candidate is the hydraulic actuator that
    the LSC (Stanford) is developing for advanced
    LIGO
  • Alternate actuators (e.g. piezo, EM) are under
    study in parallel

6
Hydraulic system
7
Hydraulic prototype test results
  • 2-DOF system
  • Feedforward andfeedback
  • Potential to reduceambient seismicnoise also
    forinitial LIGO if indicated

8
Implementation
  • Actuator prototypes component test stands are
    underway at Stanford for the actuator and
    sensors at MIT for the hydraulic distribution
    system
  • Full scale prototype system test including
    retrofit installation is planned on the LASTI BSC
  • BSC stack has been installed
  • Long lead items procured in parallel with
    prototype testing
  • Team
  • Accelerated development by the existing LSC adv.
    LIGO team, augmented by LIGO Lab staff
  • Effort transitions out of LSC RD into Lab
    implementation through the LASTI prototype
    development

9
Schedule Cost
  • Preliminary Design Review in Jan
  • System modeling results
  • Sensors selected characterized
  • Hydraulic actuator prototype tested (bolted
    version)
  • Distribution system designed modeled
  • Prototype installation test _at_ LASTI May Sep
  • Installation at Livingston starts Oct
  • Rough estimate is 750K
  • for 4 BSCs, 2 HAMs
  • beyond the RD costs associated with the
    prototype development (which is mostly part of
    the existing RD plan)
Write a Comment
User Comments (0)
About PowerShow.com