Beam Transport - PowerPoint PPT Presentation

About This Presentation
Title:

Beam Transport

Description:

(iii) Vacuum System (beam line BTS)- being assembled ... BTS/COBRA Polarity ( / ), (-/ radial de-focussing/focussing. Max. B ve. Max. B-ve ... – PowerPoint PPT presentation

Number of Views:47
Avg rating:3.0/5.0
Slides: 26
Provided by: ket6
Category:

less

Transcript and Presenter's Notes

Title: Beam Transport


1
Beam Transport Target Systems
BTS Success Novosibirsk 24/5/2005 1815 300 A
2
Beam Line Target Status
  • Topics to be Addressed
  • Beam Transport System
  • (i) Degrader / BTS optimization
  • (ii) Layout - fixed
  • Beam Line Components Status
  • (i) Separator- undergoing
    HV-conditioning
  • (ii) Beam Transport Solenoid BTS
    being commissioned ?E5
  • (iii) Vacuum System (beam line BTS)- being
    assembled
  • (iii) Cryogenic Transfer Lines LN2 LHe
    installed
  • He-Bag Target Systems
  • Schedule 2005
  • Summary Critical Points

3
Beam Transport System Status
4
Beam Transport System
As previously reported Beam Line
Commissioning 2004 concluded with phase space
measurements In vacuum up to the INJECTION into
the BTS (without BTS !!!)
Using real data ? SIMULATE Phase Space
Back-Track to Triplet II
? Forward-Track with Fringe Field of BTS
COBRA up to Target in COBRA

using GEANT
waist
Input Data to GEANT to study Degrader/Target
BTS/COBRA layout
5
Degrader BTS/COBRA Optimization
  • Studied
  • BTS/COBRA Distance vs. Degrader segmentation
    Bfield
  • (Cryo.-Cryo. Gap) minimum (200 mm),
    intermediate(300 mm), maximum(400 mm)
  • BTS/COBRA Polarity (/), (-/) radial
    de-focussing/focussing

Max. Bve
Gap ?
Max. B-ve
  • Weak Gap dependence (4)
  • strong polarity dependence
  • (15)
  • Gap 400 mm
  • -/ Polarity
  • Degrader BTS
  • strong degrader segmentation
  • dependence (25)

6
Beam Transport System Layout
Distances Fixed Platform COBRA surveyed into
Zone
7
Beam Line Component Status
8
Component Status Separator
  • MEG Vertical Separator
  • Delayed by 8 weeks
  • due to HV feed-through problems now solved
  • HV (ve) supply changed to (ve) one - technical
  • HV-electrode on top, want e deflected
    down
  • !!! HV Conditioning Tests in front of ?E5
    !!!
  • expected ready for beam time

Beam Upstream Side
Properties Vmax 200kV Dplates 19cm Leff
70cm
2371 mm
April 2005
May 2005
June 2005
9
Component Status BTS
  • Beam Transport Solenoid BTS
  • Schedule delayed by 7 weeks
  • 5 weeks delay during manufacture
  • 2 weeks transportation (papers stolen at
    Russian border)
  • nevertheless
  • !!! Novosibirsk Crew did a Very Good Job
    !!!
  • BTS arrived PSI 8th July

Coil Manufacture - epoxying
Performance Tests Novosibirsk
End March 2005
End May 2005
10
BTS Performance Tests - Novosibirsk
  • Performance Tests
  • BINP Novosibirsk 21-29th May 2005
  • Tested
  • maximum Design Current (300 A)
  • Quench Detection / Protection Systems
  • (fast switch 30 ms 0.7? Shunt Resistor 90
    power load)
  • Linearity Response (max. dev. 0.4)
  • LHe Consumption Rate (3.6 l/hr)
  • Magnetic Field Measurements
  • Flexible Cryogenic Design via
  • dedicated transfer lines (PSI)
  • dewar operation (BINP)
  • both (emergency)

All measurements tests successful
except Bfield measurements which were
influenced by steel support
structure
0.7? Shunt Resistor
11
Results BTS Performance Tests - Novosibirsk
Main Specifications LCryo 2810 mm DBore
380 mm DCoil 469.5 /
466.2 mm LCoil 2630 mm BMax
lt0.55 T Imax 300 amps LMax
0.98 H EStored 44 kJ
  • Coils
  • double layer
  • cable dia. 1.23 mm
  • 1865 / 1980 windings
  • 40 NiTi
  • RRR 100

BTOT deviates from expected due to Steel support
structure !!! Needs to be re-measured at PSI
!!! Acceptance Tests
Linearity (B vs. I) better 0.4 up to 300 A
12
BTS Preparations PSI
  • Preparations for BTS Installation in
    ?E5
  • cryogenic lines for LHe LN2 ready for
    connection
  • valve chamber ready for mounting on BTS
  • power supply tested ready

Valve Chamber Couples BTS to LHe transfer Line
contains Joule-Thompson Valves for control
LHe Transfer Line
Refrigerator unit Above ?E5
LHe line
13
BTS arrival PSI
8th July 2005
14th July 2005 ?E5
  • BTS arrival PSI
  • 8th July
  • Acceptance Tests
  • assembly / survey ?
  • vacuum / leak tests ? ?
  • cryogenic installation ?
  • electrical installation ?
  • cool-down
  • quench detection /
  • protection tests
  • Bfield measurements

On route PSI 6500 km Novosibirsk - PSI
  • !!! Problems !!!
  • welding joint tower / cryostat
  • damaged in transport
  • ? Re-welded OK
  • cryogenic connection valve-
  • chamber / LHe transfer line
  • not compatible
  • ? To workshops
  • Use dewar system LHe

Dmitry Reports 18th July 1100 coil
superconducting 2000 283A reached
(nominal 200A)
On route ?E5
14
He-Bag Target System Status
15
He-Bag / Target System - General
  • (I) Desired Beam
    Characteristics
  • transport maximum number µ to the target
    (vacuum / He, large ?P)
  • maximize µ stopping-rate in the target
    (small ?P, vacuum /He)
  • minimize beam spot size multiple
    scattering (vacuum / He, degrader close to
    target)
  • minimize background from decays or
    Bremsstrahlung (degrader far from away, vacuum /
    He)
  • (II) Desired
    Target Requirements
  • depolarizing target (isotropic e, non-metal)
  • minimum target size (low-Z)
  • minimize material traversed by decay e ?
    (slanted target)
  • minimize generation of annihilation photons
    (large X0, low-Z e.g. CH2)

?
?
  • Consequences
  • vacuum window interface to COBRA
  • He-atmosphere inside COBRA
  • slanted, non-metallic, low-Z, large X0 target

16
COBRA-Environment
  • (III) COBRA Environment
    Requirements
  • thin vacuum window at entrance COBRA (190µ
    Mylar)
  • safety measures against vacuum window rupture
    (safety seals !!!)
  • must maintain DC TC dimensions insertion
    concepts
  • stringent constant differential He-pressure
    between DCs COBRA (few µb)
  • no He-leakage to TC PMs (N2-Bag)
  • frequent / less frequent access to Downstream
    side for calibration
  • monitoring purposes (
    e.g. Cockroft-Walton, ?- CEX)
  • possibility to exchange targets ( LiF, LH2, CH2
    etc.)
  • Consequences
  • Thin beam line Vacuum Window
  • COBRA End-Cap Flanges HE-seals (US,DS)
  • Target Insertion Tube support
  • system (separate He-environment) (TISS)
  • Target System (TS)
  • ?
  • PSI staged Engineering Design Project
  • started design construction
  • (i)US-flange, (ii) DS-flange, (iii) TISS, (iv)
    TS
  • design Construction ready Feb. 2006

17
End-Cap Flanges He-Bag seals
Engineering Design Concept Upstream End-Cap
  • Design
  • Allows open
  • access to TCs
  • withdrawal
  • without affecting
  • He-environment
  • Mounting
  • N2-Bag
  • TC-rails
  • End-Cap
  • He-Bag
  • TCs
  • Beam pipe
  • with BTS
  • Couple He-
  • Bag rings to
  • vac. window

He-Bag composition Sandwich CH2/EVAL/CH2
He-Bag inner sealing rings
18
Target Optics - momentum
Momentum-Spectrum Data whole Beam Line
optimized for each data point 2-D Scan for
each point !!! Theory ?-Kinematic Edge (29.79
MeV/c) Theoretical func. P3.5 folded with
Gaussian ?P/P Const. Cloud µ contribution ?
Fitted to data
Goal maximize stop-density (min. target
size) Question optimum beam momentum? Answer
28.2 MeV/c
  • ? range vs. P
  • (fixed ?P/P 7.7 FWHM)
  • straggling 11
  • characteristic P3.5

P3.5
straggling 11
Rel. ? stops
  • ? Stopping Rate vs. P
  • (fixed ?P/P 7.7 FWHM
  • fixed 400? CH2 target)
  • as p gt relative stop rate lt
  • as p gt beam rate gt
  • Optimal Stop Rate
  • at P28.2 MeV/c

Norm. ?-stops
?2/dof 0.94 Pcent (28.16 ? 0.02) MeV/c ?P/P
(7.7 ? 0.3) FWHM Pbeam (28.2 ? 0.9)
MeV/c
P3.5
19
Target Optics - degrader
Many solutions studied 2 main categories
BTS
DMN
  • (1) DNM Solution
  • (190? Mylar Window)
  • BTS / COBRA unlike
  • polarities
  • BBTS -3.55 kG
  • degrader 480? CH2 at
  • centre BTS
  • beam ? 12.5 mm

COBRA
BTS
?P 4.2 MeV/c
? Beam envelope (cm)
?P 2 MeV/c
?P 4.5 MeV/c
  • Transmission
  • Efficiency
  • TBTSDeg 98
  • TBTSdegCOBRA 88
  • TSepTIIClli 86.5
  • Expected Stopping Rate
  • R? 9.6107 ?/s
  • at 1.8mA 4cm Tg
  • (1.7108 ?/s at 1.8mA 6cm Tg)

Momentum Profile (MeV/c)
BTS
COBRA
? Beam divergence (mrad)
20
Target Optics degrader cont.
  • (2) SNM Solutions ( no
    degrader in BTS)

  • (125? Mylar Window)
  • either combine Degrader Target (asymmetric
    stop distribution)
  • or move degrader slightly upstream of target
    (e.g. use as end-wall of target insertion tube)
  • Conclusions SNM (no BTS degrader)
  • Combined Soln gives ? 10 mm for 125? Mylar
    Window
  • with 190 ? Mylar ? 11.5 mm
  • no straggling loss only 3 decay loss
  • Expected Rate R? 1.06108 ?/s at
    1.8mA 4 cm Tg.
  • BUT annihilation radiation potential worse -
    needs to be simulated
  • Upstream Soln gives similar results to DNM ?
    12.5 mm
  • annihilation radiation potential worse - needs
    to be simulated

upstream Deg. 15 cm
Combined Tg Deg
21
Target Insertion Tube
  • Target Geometry ( for beam ? 10mm)
  • LPROJ 150.4 mm, ? 21.8, a 60.3 mm, LTRUE
    161.9 mm
  • material CH2 Rohacell / Mylar
  • Slanted Target must be thicker multiple
    scattering loss
  • on downstream-side !!!
  • Target Simulation underway
  • check of optimum angle ?
  • dependence on target thickness (multiple
    scattering,
  • background, acceptance, timing, resolution)
  • material considerations
  • decay particle hit distributions on end-cap
    materials
  • associated background acceptance

22
Target Insertion Tube survey
  • Target Insertion Tube Support System (TISS)
  • Material
  • Rohacell (PMI) closed cell foam, maybe EVAL
    foil?
  • wall thickness probably 2 mm Rohacell 31
  • length 1500 mm
  • dia. 150 mm
  • ? Weight 51 g
  • simulations concerning background from
  • e interactions in TISS underway

Target Insertion Tube
  • Survey aspects
  • target plane determined outside wrt. survey
    markers
  • on rohacell support rings (laser tracker)
  • possible temporary thin cross-wires on support
    rings
  • for axial radial alignment (break
    afterwards)
  • radial adjustment made with TISS end-flange
  • axial position set by TISS (self-positioning)

?-target system
Flange lateral vertical move- ment
23
Schedule 2005
  • Critical Path
  • Commissioning Part 1 too short for BTS/COBRA
  • phase space measurements ? Dec. Part 2
  • final Target measurements ? first beam 2006
  • Changes 2005 (compared to previous schedule)
  • Separator schedule 8 weeks
  • BTS Schedule 7 weeks
  • COBRA end-cap target design manufacture
    extended

24
Summary Critical Path
  • Summary
  • beam transport system up to COBRA defined
  • COBRA Platform surveyed into position
  • All beam transport elements now manufactured
  • MEG Separator being conditioned
  • BTS successfully tested in Novosibirsk
    delivered PSI (8th July)
  • BTS reached current of 283A during commissioning
    at PSI (18th July)
  • All cryogenic lines installed to zone
  • all vacuum system available
  • engineering project for COBRA end-caps target
    Insertion support system underway
  • manufacture to be completed Feb. 2006
  • Critical Points
  • COBRA phase space measurement delayed until Dec.
    2005 (delays Separator BTS)
  • Final measurements with target delayed until
    first beam 2006

25
?-Beam Results (re-cap)
Provisional Results ?- Integral Spot
Rates MHz for 1,8mA Proton Current 4cm Target
E Normalized to Momentum Slit Settings
FS41L/R 250/280 FS43L/R 240/220
  • First ?- Beam Studies with MEG Beam
  • for calibration purposes in the experiment
  • ?-p??0n, ?-p??n
  • 55 ? 83 MeV ?s and 129 MeV ?s
  • Data taken from
  • P-spectrum measurements 25-33 MeV/c
  • ?s detected above 30 MeV/c (pulse-ht. RF tof)
  • dedicated ?- runs at 56 MeV/c 103 MeV/c
  • 56 MeV/c interesting since max. momentum
  • that can be transported to COBRA with
  • good optics SNM in BTS
  • dedicated CEX run at 112 MeV/c

e-
µ-
56 MeV/c R? 7.6 106 ?-/s slits open
R? 7.2 105 ?-/s slits70/70
?-
Write a Comment
User Comments (0)
About PowerShow.com