Title: Chapter 5 - Present Worth Analysis Click here for Streaming Audio To Accompany Presentation (optional)
1Chapter 5 - Present Worth Analysis Click here
for Streaming Audio To Accompany Presentation
(optional)
- EGR 403 Capital Allocation Theory
- Dr. Phillip R. Rosenkrantz
- Industrial Manufacturing Engineering Department
- Cal Poly Pomona
2EGR 403 - The Big Picture
- Framework Accounting Breakeven Analysis
- Time-value of money concepts - Ch. 3, 4
- Analysis methods
- Ch. 5 - Present Worth
- Ch. 6 - Annual Worth
- Ch. 7, 8 - Rate of Return (incremental analysis)
- Ch. 9 - Benefit Cost Ratio other techniques
- Refining the analysis
- Ch. 10, 11 - Depreciation Taxes
- Ch. 12 - Replacement Analysis
3- Where we have been
- Equivalence concept
- Cash flows
- Compound interest factors
- Where we are going in this chapter
- Understanding economic criteria.
- Applying present worth techniques.
- Assumptions in solving economic analysis
problems.
4Economic Decision Making Problems Fall Into Three
Categories
- Three criteria that apply to all of our analysis
techniques - For fixed input situations, maximize the benefits
or other outputs. - For fixed output situations, minimize the costs
or other inputs. - Where inputs and outputs vary, maximize
benefits costs. - First step is to decide which category applies.
- See the back inside cover of the text.
5Economic Criteria Restated Present Worth
Techniques
6Economic Criteria - Examples
7Applying Present Worth Techniques
- With PW analysis the analysis period used is a
major consideration. Several cases - Useful life of the alternative(s) equals the
analysis period. - Alternatives have useful lives different from the
analysis period. - The analysis period is infinite or long enough to
be treated as infinite, n .
8Useful Lives Equal the Analysis Period
- Example 5-1 Require a project to last five
years. - The equipment and tooling will last five years.
- Calculate the PW or NPW over a five year span
and junk the equipment at the end of the five
years (salvage value 0). - Two alternatives with cost of 1000 and useful
live of 5 years. Assume i 7.
9Example 5-1 Fixed input, therefore maximize PW
of Benefits.
- Alternative A
- Find the PW of all cash flows related to benefits
of Alternative A. Also include additional costs
that come later. - PW of Benefits 300 (P/A, 7, 5) 300 (4.100)
1230
10Example 5-1 Fixed input, therefore maximize PW
of Benefits (contd)
- Alternative B - Here we have a combination of a
uniform series (A 400) and a negative gradient
(G 50). Decompose to use the factors available. - PW of Benefits 400 (P/A, 7, 5) - 50 (P/G, 7,
5) - 400 (4.100) - 50 (7.647) 1257.65
11Example 5-1 Contd
- PWB Alternative A 1230.00
- PWB Alternative B 1257.65
- Since our criteria was to maximize PW of
Benefits, Alternative B is preferred. - Notice that each alternative provided the same
total cash flow, but alternative B provided it
sooner so that it was available sooner to the
company to use. -
- MONEY NOW IS BETTER THAN MONEY LATER
12More Examples
- Example 5-2 Two stage construction.
- Fixed output so Minimize PW of Cost
- Use PW factors to find PW of second stage costs
and benefits at time 0. - Example 5-3 Salvage value included
- Fixed output, so Minimize PW of Cost
- Use PW factors to find PW of salvage value.
- Operating maintenance costs were assumed equal.
- Example 5-4 Neither input nor output fixed
- Maximize (PWB - PWC) or Maximize NPW
- Salvage value treated as a negative cost ( a
benefit)
13Useful Lives Different From the Analysis Period
- Consider (based on Example 5-3)
- Speedy Useful life 5 years. P 1500, S
200, PWC 1357 - Allied Suppose useful life 10 years instead
of 5 years. P 1600, Salvage value 325. PWC
1435. - If we have two alternatives with different useful
lives, is it proper to compare PWB and/or PWC
directly? - Answer No, because we have 5 additional years of
benefits for Allied that would be ignored - Solution Require the project to last 10 years.
- For Speedy assume that you will purchase new
equipment and tooling twice At the beginning of
year one and six. - Junk the equipment and tooling at the end of each
five year period and replace with the same
equipment.
14Useful Lives Different From the Analysis Period
- Calculate the PW or NPW over a 10 year span.
- Speedy PWC 2325
- Now Allied is the preferred choice since PWC is
less than for Speedy
15Techniques for Dealing with Unequal Useful Lives
- Repeated Project Policy - We will assume the
same costs and benefits and repeat a project all
the way to the end of the analysis period. This
is a major part of PW analysis. - Least Common Multiple - Find useful life that
coincides with multiple lives of each alternative
under consideration e.g. If useful lives are 3
years and 4 years, then the least common multiple
is 12 years.
16Techniques for Dealing with Unequal Useful Lives
- Terminal year
- Sometimes the least common multiple method (LCM)
creates an unrealistic useful life (e.g., 13
years and 7 years LCM of 91 years). - Instead, pick a terminal year and repeat all
projects up until the terminal year. - Truncate all costs and benefits after the
terminal year - (See Figure 5-1 on page 175 for an illustration)
17Infinite Analysis Period
- For n infinity, A i P
- Therefore
- P A / i
- i A / P
- When you have a very long analysis period, use
the infinity assumption to simplify problems. - Example 5-6 If we can resolve our desired task
or service into an equivalent A, then we can use
P A / i to simplify the process of finding P.
18Assumptions in Solving Economic Analysis Problems
- End-of-year (or period) convention (simplifies
calculations) - Viewpoint (generally the firm)
- Sunk costs (past has no bearing)
- Borrowed money (consider investing only)
- Effect of inflation (prices are not stable)
- Income taxes (must be considered for realism)