Title: Productivity Improvement 
 1Productivity Improvement  SPX APV (formerly 
Invensys APV) 
 2Case Study  Productivity WorkshopAPV Rosista, 
Germany
- Introduction 
 - Asked by customer to increase production 
efficiency within their Housing Production Cell 
and by doing so, coach personnel in Lean 
Manufacturing principles. The project included 
running numerous workshops, which would 
facilitate the actual shopfloor implementation of 
improvements during the estimated timescale (4-6 
months).  - Project Plan 
 - The plan was based on a 4 month program and 
focused on the use of the following lean tools  -  SMED (Single Minute Exchange of Die) 
 -  Kanban scheduling 
 -  Process Flow 
 -  Visual Management 
 - Implementation 
 - All 22 operators included in at least 1 workshop 
 - SMED workshops conducted on 8 key work centres 
using video analysis  - Plan adherence reviewed weekly by 
cross-functional steering group  - Full involvement and support of Labour Works 
Council  
  3- Storyboard 
 -  The attached slide shows images of some of the 
improvements carried out and provides details of 
the key metrics, before  after. The planned 
timescale was extended to 5 months (due to local 
factory legislation) and a capex spend of  
43.5k on various items including racks, bins, 
roller table  duplicate tooling.  - N.B.This is the summary status signed off by all 
team members. 
  4Storyboard  This slide shows the actual 
storyboard detailing the SMED exercise carried 
out on a 250T Hydraulic Press. This was used to 
provide a visual step by step guide of what a 
SMED exercise involves. This then allows all 
personnel to easily understand the goal of set-up 
reduction and provides the stimulus for 
generating ideas within their own areas.
SMED Storyboard 
 5- Savings Analysis 
 -  After allowing a six week bedding in period, we 
completed a productivity study on the cell 
involved in the project and the site as a whole. 
We wanted to demonstrate the uplift in 
efficiency within the Housing Cell but also what 
the knock-on effect had been on site-wide 
efficiency now that the bottleneck process had 
been relieved, and how that had then triggered 
process improvements in other cells. Attached 
below is a summary of productivity using T  A 
figures supplied by finance 
  6Savings Analysis  Here you can see the actual 
costing sheet used on site to calculate 
efficiency and the associated saving / loss 
achieved. The ratio column shows the standard 
efficiency calculation (hrs earned / hrs worked). 
As demonstrated, the efficiency has rose from 
78.4 in Wk 13 to 116.4 in Wk 25. The savings 
generated by the efficiency increase can then be 
easily calculated by taking a 4 wk moving average 
and then multiplying out to provide an annual 
saving. Therefore, at the end of this project, 
the annual savings generated by the efficiency 
lift were  1,799k (as shown bottom RH corner).  
 7Case Study  Productivity WorkshopAPV Rosista, 
Germany
- Summary 
 - Productivity Efficiency 
 - As demonstrated, there is now a 49 increase in 
Productivity Efficiency within the cell. This is 
equivalent to  9.2k per wk, over  450k 
annually!  - The lift in the Housing cell is clearly well in 
advance of the other 4 areas (increases ranging 
from 12 - 23).  - As demonstrated, there is now a 38 increase in 
Productivity Efficiency within the site. This is 
equivalent to  35.9k per wk, over  1,799k 
annually!  - Set-up Time 
 - Reduced by 34 
 - Inventory 
 - Reduced by  86k (30) 
 - General 
 - Efficiency savings also achieved by 
 -  Secondary operations being completed 
in-cycle  -  Reduction in manual handling