Quantitative Methods for Flood Risk Management P.H.A.J.M. van Gelder $ $ Faculty of Civil Engineering and Geosciences, Delft University of Technology THE NETHERLANDS - PowerPoint PPT Presentation

1 / 33
About This Presentation
Title:

Quantitative Methods for Flood Risk Management P.H.A.J.M. van Gelder $ $ Faculty of Civil Engineering and Geosciences, Delft University of Technology THE NETHERLANDS

Description:

Events with small probabilities and large consequences ... ML estimate of 1/100 year quantile is below the ... River Meuse discharges (1/1250 years quantile) ... – PowerPoint PPT presentation

Number of Views:162
Avg rating:3.0/5.0
Slides: 34
Provided by: hydraulice
Category:

less

Transcript and Presenter's Notes

Title: Quantitative Methods for Flood Risk Management P.H.A.J.M. van Gelder $ $ Faculty of Civil Engineering and Geosciences, Delft University of Technology THE NETHERLANDS


1
Quantitative Methods for Flood Risk Management
P.H.A.J.M. van Gelder Faculty of Civil
Engineering and Geosciences, Delft University of
Technology THE NETHERLANDS
  • Workshop
  • Statistical Extremes and Environmental Risk
  • Faculty of Sciences
  • University of Lisbon, Portugal
  • February 15-17, 2007

2
Contents
  • Introduction
  • Extreme Value Statistics
  • Types of Uncertainties
  • Effect of Uncertainties on design
  • Case study
  • Conclusions

3
Introduction
  • Events with small probabilities and large
    consequences
  • Estimating the quantiles of the order of 1/100 -
    1/10,000 years of
  • water levels
  • river discharges
  • precipitation levels
  • etc.

4
Staatscommissie voor den Waterweg, 1920
5
Striking observations
  • Design of breakwater
  • ML estimate of 1/100 year quantile is below the
    largest observation during a 10 year period (see
    figure)
  • Optimal decision-making from which viewpoint?

6
(No Transcript)
7
Threshold selection
  • 1/10,000 year quantiles of sea levels at Hook of
    Holland with 2 parameter estimation methods for
    GPA distribution

8
River Meuse discharges (1/1250 years quantile)
9
Homogeneity of datasets (generated by the same
process?)
10
Wave heights at Karwar India
11
Karwar
12
Karwar
13
Extreme Value StatisticsMany available methods
  • Moments
  • Least Squares
  • Maximum Likelihood
  • L-Moments
  • Minimum Entropy
  • Bayesian
  • all refined mathematics

14
Lack of data
  • N 101 102 observations
  • RP 102 103 104 years
  • Homogeneity
  • Stationarity

15
Not only mathematics, but physical insight
  • Discharge water content x orographic x synoptic
    (Klemes, 1993)
  • Storm surge tide wind setup
  • Joint distribution of waves and storm surges
    (Vrijling, 1980)

16
(No Transcript)
17
  • Still extrapolation with huge uncertainty
  • wait for more data
  • postpone the constructions of the port, sea
    defence, or dam
  • the most rational way to decide on the size of
    the structure under uncertainties

18
  • If we see the design as a decision problem under
    uncertainty, there are more uncertainties
  • extrapolation uncertainty
  • model uncertainty
  • uncertainty of the resistance
  • ...

19
Types of Uncertainties
20
  • Z R S U
  • R Resistance
  • S Loads
  • U Uncertainty

21
Probability Distributions of ?
22
Policy Implications
  • Three Possible Reactions
  • 1 Accept the difference and do nothing.
  • 2 Heighten the dikes in order to lower the new
    probability of flooding to the old value.
  • 3 Reduce some uncertainties by research before
    deciding on the heightening of the dikes to the
    optimal probability of flooding.

23
Case study
  • Lake IJssel
  • 1200 km2
  • very shallow
  • steep waves

24
Physical and reliability model
  • Wave run-up z2 (Van der Meer)
  • Wind surge ? (Brettschneider)
  • Reliability function
  • Z K - M - ? - z2
  • Crest Level K
  • Lake Level M

25
Uncertainties
  • Intrinsic
  • Lake Level
  • Wind Speed
  • Statistical
  • Lake Level
  • Wind Speed
  • Model
  • Surge
  • Oscillations
  • Significant wave height
  • Wave steepness
  • Wave run-up

26
FORM Results of Rott. Hoek
27
Contributions of Uncertaintiesat Rotterdamsche
Hoek
28
Rotterdamsche Hoek
29
Reliability-based Optimizationimprove or
postpone
30
CONCLUSIONS
  • Extreme value theory in the most refined form is
    less fruitful
  • The limited amount of data and the various
    sources of uncertainty have to be seen in the
    context of the design decision
  • All uncertainties have to be taken into account
    in the design decision

31
Conclusions
  • A method to get insight in the effect of
    uncertainty in hydraulic engineering problems is
    described.
  • The most influential random variables are
    generally the ones with inherent uncertainty
    (this uncertainty cannot be reduced).

32
Conclusions
  • In case of exponential distribution normal
    uncertainties, a simple expression for the
    economic optimal probability of failure can be
    derived
  • Larger location parameter leads to higher optimal
    design, but has no influence on the optimal
    probability of failure
  • Larger scale parameter leads to smaller optimal
    design and higher probability of failure

33
Conclusions
  • More options than structural
  • reduce uncertainty by data collection or research
  • decrease loads (µ down or s down)
  • increase resistance (µ up or s down)
  • reduce damage in case of failure
  • Economic optimal decisions should be proposed for
    the height as well as the timing of the
    improvement
Write a Comment
User Comments (0)
About PowerShow.com