Title: Agenda Item 7'6 Direct Reuse as a Water Management Strategy for Multiple WUGs
1Agenda Item 7.6 Direct Reuse as a Water
Management Strategy for Multiple WUGs
2Todays Presentation
- Reuse defined
- How can reuse water be used?
- Who already has reuse projects?
- Water quality considerations
- Brazos G potential supply of reuse water
- Brazos G potential users of reuse water
- Putting supplies and demands together for the
2006 Brazos G Regional Water Plan
3Definitions
- Water Reuse putting treated wastewater plant
effluent to beneficial use - Reuse Water
- Reclaimed Water
- Recycled Water
4Definitions
- Two forms of reuse
- Direct Reuse pipe treated wastewater directly
from wastewater plant to place of use - flange-to-flange
- purple pipe
- Indirect Reuse discharge treated wastewater to
river, stream or lake for subsequent diversion
downstream - bed-and-banks
5Reuse Water Applications
- Irrigation
- Municipal (parks, golf courses, ball fields,
landscape) - Agricultural (avoid direct contact with food
crops) - Construction watering
- Industrial
- Power plant cooling
- Manufacturing process water
- Potable municipal water
- Requires advanced treatment (RO, etc.)
- El Paso Aquifer Storage and Recovery (ASR)
- Direct potable use not done yet in Texas
6Some Existing Reuse Projects
- City of Abilene
- City of Cleburne
- City of Round Rock
- City of Georgetown
- San Antonio Water System (SAWS)
- Lakeway, El Paso
7City of Abilene
- 4 MGD reclaimed water permit
- Excess stored in Lake Daniel
- Sales to customers for landscape irrigation
- Dyess AFB
- Abilene Christian University
- Hardin Simmons University
- Diamond Back Golf Course
- Others
- 0.45/1,000 gallons reclaimed water rate
- 2.75/1,000 gallons potable water rate
8Abilene Reclaimed Water System
9City of El Paso Reclaimed Water Project
- Started in late 1960s
- Over 5 MGD currently supplied
- Golf course irrigation
- Landscape irrigation
- El Paso Utilities
- Implementing plans that could double current
uses - Opportunity for Aquifer Storage and Recovery
(ASR)
10Other Reuse Projects
- Cleburne
- ?1 MGD sales to Ponderosa Pines cogen plant
- Plans for golf course irrigation adjacent to WW
plant - Round Rock
- 1 MGD for irrigation (Forest Creek Golf Course)
- Plans for expansion (Old Settlers Park and
others) - Georgetown
- Berry Creek WWTP to Berry Creek Golf Course
- San Gabriel WWTP to Southwestern University
11Water Quality Considerations
- TCEQ Regulated by 30 TAC 210
- Type I Uses
- Public or food crops generally can come into
contact - Type II Uses
- Public or food crops cannot come into contact
12Quality Criteria 30 Day Average
- Type I Reclaimed Water Quality
- BOD5 or CBOD5 5 mg/l
- Turbidity 3 NTU
- Fecal Coliform 20 CFU/100ml
- Fecal Coliform (not to exceed) 75 CFU/100ml
- Type II Reclaimed Water Quality
- BOD5 20 mg/l
- Or CBOD5 15 mg/l
- Fecal Coliform 200 CFU/100ml
- Fecal Coliform (not to exceed) 800 CFU/100ml
13Brazos G Reuse Supplies/Demands
- 40 Wastewater treatment facilities in the Brazos
G Region that are projected in 2060 to treat gt 1
MGD (1,120 acft/yr) - 26 of these wastewater facilities are proximate
to water needs - 30 Water User Groups (WUGs) with need are
proximate to these wastewater facilities
142060 Wastewater Quantity
- 2000 and 2060 treated wastewater quantity derived
from Brazos WAM - 2060 quantity of wastewater discharged either
- Total treated wastewater
- 25 reuse of Y2000 treated WW quantity
- 50 reuse of later treated WW quantity
- Wastewater discharged in 2060
-
- B) Estimate provided by facility
15Brazos G Potential Reuse Water
162060 Discharge and County Balances
172060 Water User Group (WUG) Balances
18Preliminary Reuse Pairings
19City of Bryan Example
This graphic is too large to place in pdf file,
sorry.
20Future Work
- Further develop reuse water supply options for
interested water user groups (demand and supply) - Confirm developed plan with water user groups
- Develop general costing scenarios for undefined
future reuse water supply plans - Upgrade cost for existing WWTP to Type 1
- Satellite wastewater treatment plant cost
- Planning costs for future use of reuse water for
indirect potable municipal supply
21Discussion