Title: Theres No Shortage of Electrical Events Lessons Learned at BNL and Beyond
1Theres No Shortage of Electrical Events
Lessons Learned at BNL and Beyond!
- Edward A. Sierra
- Quality Management Office
- Presented to
- ALD for ESHQ
- Safety Health Services Division Manager
- Lab Electrical Safety Committee
- August 30, 2006
2AGENDA
- Point to Ponder
- Why this Presentation?
- DOE Electrical Safety Report 2004
- BNL Electrical Occurrences, 2002 2006
- Causes
- BNL Lesson Learned Statements
- Electrical R ORPS Reports in the Complex
- Causes
- DOE Suggested Measures to Prevent Electrical
Occurrences - DOE Special Operations Report, Electrical Safety
2006 - Mandated Response
- BNL World-Class in Electrical Safety?
- Beyond BNL, Electrical Safety Programs
- Path Forward
3Point to Ponder
- Organizations only improve where the truth
is told and the brutal facts confronted. - - Jim Collins
- Good to Great, 2001
4Why this Presentation?
- As directed by the Deputy Director of Operations
- The Laboratory will evaluate the DOEs ORPS and
lessons learned-databases concerning all previous
electrical events to identify lessons learned.
In addition, a search will be made for electrical
safety best practices within the DOE complex.
The results of this evaluation/search will be
presented to the ALD for ESHQ, the Safety and
Health Services Division Manager, and the
Laboratorys Electrical Safety Committee for them
to assess the applicability to BNL.
5DOE Electrical Safety Special Report
2004-02Four Types of Electrical Safety
Occurrences
-
- Electrical safety occurrences are the most
frequently reported near miss events across the
DOE complex, and thus pose the greatest risk to
workers.
6DOE Electrical Safety Special Report,
2004-02Four Types of Electrical Safety
Occurrences
- 1. Electrical Work Near Misses - while
performing electrical maintenance, repair, or
installation functions. - 2. Electrical Intrusion Near Misses -
during excavation and decommissioning and
decontamination work. - 3. Vehicle Near Misses - striking overhead
electrical power lines, etc. -
- 4. Other Electrical Near Misses -
non-electrical workers who suffer shocks, etc.,
during routine work performance.ROOT CAUSES
largely stemmed from basic conduct of operations
deficiencies -
- Work Planning
- Lockout/Tagout
- Configuration Management
7Complex Workers Involved in 2002-2003Electrical
Safety Occurrences
817 BNL Electrical Safety Occurrences2002-2006
- 2002
- Minor Utility Strike During Horizontal Boring
Operations - Sub Personnel Drilled Anchor Bolts in Concrete
Encased Electrical Duct Bank - U4A Beam Line User Received Electrical Shock _at_
NSLS - 2003
- Forklift Load Strikes Overhead Lines
- Employee Received an Electric Shock to Hand
During Magnet Operations _at_ Physics - Communication Cable Struck During Excavation
- 2004
- Electrical Utility (Encased in Concrete Floor)
Conduit Strike - Potential Fire Hazard (electrical arc) in AGS
Cable Tray - Worker Experiences Electric Shock During Beam
Line Water Hose Replacement _at_ NSLS - 2005
- Unexpected Discovery of Electrical Hazardous
Energy Source _at_ Magnet Division - Energized Wire Discovered During RF Power Amp
Repair _at_ C-AD - Unauthorized Modification to Power Cord Prongs
- 2006
- 400 Amp Electrical Switch Failure (arc flash) _at_
C-AD - Exposed Electrical Terminals in Legacy Installed
Light Timer _at_ Medical
97 BNL Electrical Workers Near Misses 2002-2006
- 2002
- U4A Beam Line User Received Electrical Shock _at_
NSLS - 2003
- Employee Received an Electric Shock to Hand
During Magnet Operations _at_ Physics - 2004
- Worker Experiences Electric Shock During Beam
Line Water Hose Replacement _at_ NSLS - 2005
- Unexpected Discovery of Electrical Hazardous
Energy Source _at_ Magnet Division - Energized Wire Discovered During RF Power Amp
Repair _at_ C-AD - 2006
- 400 Amp Electrical Switch Failure (arc flash) _at_
C-AD - Unexpected Energized Cord Cut _at_ NSLS
104 BNL Electrical Intrusion Near Misses 2002-2006
- 2002
- Minor Utility Strike During Horizontal Boring
Operations - Sub Personnel Drilled Anchor Bolts in Concrete
Encased Electrical Duct Bank -
- 2003
- Communication Cable Struck During Excavation
- 2004
- Electrical Utility (Encased in Concrete Floor)
Conduit Strike -
-
111 BNL Vehicle Near Misses 2002-2006
- 2003
- Forklift Load Strikes Overhead Lines
-
125 BNL Non-Electrical Workers
Near Misses 2002-2006
- 2004
- Potential Fire Hazard (electrical arc) in AGS
Cable Tray - 2005
- Unauthorized Modification to Power Cord Prongs
- 2006
- Exposed Electrical Terminals in Legacy Installed
Light Timer _at_ Medical - Energized Conductor Discovered in Cut Conduit _at_
Chemistry - Painter's spackling knife contacts abandoned live
electrical wiring
1317 BNL Electrical Safety Occurrences2002-2006
(Activity Category)
1417 BNL Electrical Safety Occurrences2002-2006
(Cause Codes)
- TOP 6 CAUSES
- Defective or Failed Part
- Individual justified action by focusing on biased
evidence - Inadequate work package preparation
- Incomplete / situation not covered
- Lack of written communication
- Comm. between work groups LTA
15BNL Electrical Safety Occurrences
(2002-2006)Lessons Learned Statements
- A routine task can easily become a hazard if the
required procedure is not followed or if
attention to detail is not applied. -
- Do not assume that the hazards in your work area
are always at your eye/foot level. Be aware of
ALL your surroundings. - Reliance on word of mouth should not have removed
the requirements to initiate adequate hazard
reviews. - Construction activities should require written
communication and/or verification of work
completion. - A complete review of all systems should be
conducted prior to any operations, even if the
manufacturer's representative has carried out
installation. - All electrical equipment connected to line
voltage must be bonded to ground. It cannot be
assumed that even very heavy equipment sitting on
stone is adequately connected to ground. -
16BNL Electrical Safety Occurrences
(2002-2006)Lessons Learned Statements
- Heat tapes used in cryogenic applications in
order to prevent icing must be capable of
functioning in wet environments even when it is
not anticipated that ice will build up. - A safety review prior to start of work is needed
whenever significant changes to approved
electrical configurations are made. - In a user facility, communication of key ESH
messages should be carefully and consistently
expressed to ensure that key requirements have
been understood and accepted by visiting
scientists. - Ensure that all beamline and facility equipment
with significant hazards has clear ownership and
a responsible person. - Do not assign work as "skill of the worker" on
equipment with electrical or other energy sources
that you are unfamiliar with. - Do not alter the configuration of equipment or
components unless you are authorized to make
changes and are knowledgeable of the hazards
associated with the equipment. -
17BNL Electrical Safety Occurrences
(2002-2006)Lessons Learned Statements
- Project managers are responsible to ensure that
they comply with all applicable procedures for
the work that they perform or execute. It is
imperative that the Project Manager review all
project requirements with the contractor to
ensure thorough job knowledge and operating
conditions are known. - The process of identifying concealed utilities
embedded in concrete is an inherently challenging
and imprecise process that, even when carried out
in accordance with established procedures and
utilizing the latest detection equipment, does
not guarantee the utility can be precisely
located. Personnel must recognize the uncertainty
involved and assure that all relevant information
about the area in question has been communicated
and that all reasonable measures have been taken
to protect the safety of workers and facilities
prior to authorizing the start of work in the
area. Due to this uncertainty, embedded utilities
should be avoided in all new designs and
de-energized whenever possible if penetrations
are required during construction.
18Electrical R ORPS Reports
- 10 Electrical R Reports issued across complex
- Hanford Site (3)
- Yucca Mountain
- Idaho National Lab (2)
- Sandia National Lab
- Los Alamos National Lab
- Savannah River Site
- Rocky Flats Env. Technology Site
- Note On 2/28/05 BNL ORPS Categorizers voted
that an R Report concerning utility strikes was
not warranted.
19Electrical ORPS Reports
- 17 BNL Report CAUSES
- Defective or Failed Part
- Individual justified action by focusing on biased
evidence - Incomplete / situation not covered
- Lack of written communication
- Inadequate work package preparation
- Comm. between work groups LTA
- 10 R Report CAUSES
- Check of work was LTA
- Management policy guidance / expectations not
well-defined, understood or enforced - Work planning not coordinated with all
departments involved in task - Inadequate work package preparation
- Comm. between work groups LTA
20DOE Electrical Safety Special Report
2004-02Suggested Measures to Prevent Electrical
Work Occurrences
- Walk down the work site to (1) identify equipment
to be worked on, (2) ensure that equipment to be
isolated is clearly marked, (3) verify or modify
drawings to reflect as-built conditions, and (4)
identify additional hazards or other safety
issues. - For decommissioning work, re-evaluate electrical
hazards as systems and equipment are dismantled
and isolations are removed. - Ensure that lockout/tagout procedures or work
instructions include a zero-energy check to
confirm the effectiveness of the lockout/tagout
installation. Always perform a zero-energy check
on the circuit to be worked, as well as on other
nearby circuits and terminals. Perform these
checks any time new areas or equipment are
accessed. - Upon completion of wiring work, check for proper
voltages, phasing, and grounding. - Use lockout/tagout processes if there is a
possibility that work may be performed in close
proximity to energized electrical conductors. - Ensure that lockout/tagout procedures or work
instructions include independent verification
that the lockout/tagout has been correctly
performed.
21DOE Electrical Safety Special Report
2004-02Suggested Measures to Prevent Electrical
Work Occurrences
- Ensure that purchased electrical components and
equipment are acceptance-tested before they are
put into service. - Work on energized circuits should be performed
only after obtaining special approvals and
developing job-specific safety controls. - Always use electrical-rated PPE (e.g., insulated
gloves and boots, ground-fault circuit
interrupters, double-insulated tools, and rubber
mats) when working on energized electrical
circuits and equipment. - Stop work if an unanticipated electrical hazard
or condition is encountered and seek appropriate
assistance.
22DOE Electrical Safety Special Report
2004-02Suggested Measures to Prevent Electrical
Intrusion Occurrences
- Drill pilot holes and penetrate no deeper than is
required for the job. - Check drill holes frequently for obstructive
material, such as wire fragments or rebar. - Always wear personal PPE.
- Clearly mark components that are to be removed
and establish boundaries and hold points for zero
energy verification when performing demolition
work. - Conduct source checks for energy near the work,
and not just at known energy sources. - Exercise stop work authority if unanticipated
conditions are encountered. - Use appropriate PPE equipment that has proper
electrical ratings. - Standardize methods for identification and
location of concealed or buried electrical
utilities.
23DOE Electrical Safety Special Report
2004-02Suggested Measures to Prevent Electrical
Intrusion Occurrences
- MO contractors should share information such as
locator data, drawings, and permit information
with subcontractors performing the work. - Analyze the specific work activity and do not
just base hazards controls on established
standards and work practices. - Perform excavation and penetration work in a
timely manner following surveys and marking of
locations. Markings can deteriorate over time,
and conditions can change. - Employ utility locator services or use the latest
survey technology available. - Hand-excavate in close proximity to the expected
location of the utility rather than using
excavation equipment. - Re-evaluate hazards analysis processes and
associated controls for excavation and electrical
penetration-type work. - Place marking tape or electronic markers above
newly installed utilities or excavated utilities
to aid in future identification.
24DOE Electrical Safety Special Report
2004-02Suggested Measures to Prevent
Vehicle/Electrical Occurrences
- Job hazard analyses for tasks involving vehicles
need to include all work areas and travel routes
to identify overhead electrical hazards and to
address appropriate requirements for vehicle
clearances and an adequate number of spotters. - Job hazard analyses should also consider the
possibility of changed vehicle profiles and load
configurations, such as raised truck beds, the
shifting of masts and booms, and the increased
heights of vehicles after unloading. - Spotters assigned to transports need to be
dedicated for the whole job, including exiting. - Drivers must be trained to stay in communication
with spotters and to be aware of the effect of
changed vehicle and load configurations on
clearances. - Guy wires, utility poles and overhead lines need
to be marked if not clearly visible to drivers
and spotters. -
25DOE Special Operations ReportElectrical Safety,
August 2006
- 2005 Secretarys Directive
- Demonstrate adequate performance expectations
- Demonstrate accountability for improved
electrical safety - More electrical events in 2005 than 2004
- Significant increase in LOTO events and shocks
- Significant concern regarding the safe
performance of electrical work - 2006 All electrical safety improvement
activities under EFCOG - Electrical Safety Improvement Project Plan
- Actions implemented by end of CY 2006
26DOE Special Operations ReportRecurring Process
Area Issues
- Inadequate Work Planning and Hazards
Identification - Failure to
- Understand the scope of work
- Adequately review drawings and walk down the job
- Consult with SMEs
- Identify adequate barriers
- Prescribe appropriate PPE
- Stop work when unanticipated conditions are
encountered - Hazardous Electrical Energy Control
- Failure to
- Follow LOTO procedures
- Perform independent verification
- Electrical Safety Compliance
- Failure to
- Perform zero-energy verification
- Wear properly rated PPE
- To use electrically rated tools
- Have sufficient justification for working hot
27DOE Mandated Response
- DOE provided Lines of Inquiry to assess
electrical safety program - Electrical Work Planning Process
- LOTO Process
- Zero-Energy Check and Energized Work Process
- Specifically looking at
- Procedures
- Training
- Implementation
- Verification
28Defining a World-Class Electrical Safety
Program
- Adapted from Breakthrough Safety Management -
by S. Smith - 06/08/2004 - http//www.occupationalhazards.com/safety_zones/47
/article.php?id11919 - Electrical events have been eliminated.
- Electrical safety is perceived by management as a
competitive advantage. - Consistent electrical safety processes are
encouraged and supported by management. - Electrical safety processes are externally
verified through outside audits. - Benchmarking against other organizations is
promoted. - Electrical safety accomplishments are
acknowledged by outside organizations. - Electrical safety achievement is sustainable.
- Other organizations seek out BNL to mentor them
in electrical safety.
29BNLs World-Class Electrical Safety Program
30Beyond BNL Electrical Safety Programs
- Hanford
- U.S. Navy
- Strategic Petroleum Reserve
- Bayer Pharmaceutical
- Savannah River Site
- Princeton Plasma Physics Laboratory
31Beyond BNL Hanford
- Contact Victor Edens, (509) 371-2077
- Establish a centralized work control and planning
center to control work on, or adjacent to,
operating systems and hazardous energy sources.
(Construction Utilities Group, CUG) - Life Critical Safety Procedures approved by CUG
- Incorporate comprehension tests and practical
evaluations into training for LO/TO, Confined
Space, Hazardous Work Permit, Zero Energy Checks,
and Excavations. - The frequency in which an individual implements a
given work control program should also be a
factor in determining how often refresher
training is required. - Need to Test/verify Supervisor's ability to
identify hazards on a regular basis. (i.e.
Evaluate a supervisor's ability to identify
hazards by observation during periodic
participation in an area safety walk exercises
involving photo review to identify hazards and
other training means). - Implement STARRT Card, addresses ISM 5 core
functions -
32 Beyond BNL U.S. Navy
- Contact Chief Mackey, (757) 444-3520
- USS Wyoming (Gold) was recognized as the best
Electrical Safety Program - http//www.safetycenter.navy.mil/default.htm
33 Beyond BNL Strategic Petroleum Reserve
- Contact Will Woods (DOE), (504) 734-4329
- Close Call Program
- Human Factors Program
- Hired contractor to complete arc flash
calculations
34 Beyond BNL Bayer Pharmaceutical
- Contact Frank Caslaina, (203) 812-2790
- Electrical workers wear FR clothing at all times
- After deeneergizes gt 480 v load side is grounded
prior to work
35 Beyond BNL - Savannah River Site
- Contact Jackie Mcalhaney, (803) 208-3389
- Electrical Site-wide stand down Summer of 05
- LOTO, DD, Equip. Abandonment, Drilling, and
Excavation - Electrical Safety Awareness Week (Raised
Awareness) - Tailored presentations to Admin., Field, and
Electrical Workers - Facility walk downs (1200 findings, most minor)
- Exposed conductors
- Electrical Safety Express Publication written
by SMEs - Referenced during tool box meetings
- Vacuum type Technology, Location of buried
utilities (No hand digging) - Mounted on trailer uses air/water/vacuum
- Contact Jack Goldenburg, (803) 557-9386
- Proximity Voltage Detector
- Tech DVA 30 (detects voltage and current)
36 Beyond BNL - Savannah River Site
- Signed Work Expectation Form, 100 voltage checks
- All LOTOs reviewed by Engineer prior to start of
work - Formal Analysis Program Software Program
- Outputs hazard analysis tree based on site
requirements - Stop Work out, Time Out in
- Now workers to stop
- Encouraged to take time out
- Reinforced
- Annual Training on Energized Work Procedure
- 1st time Live Instructor
37 Beyond BNL - Princeton Plasma Physics
Laboratory
- Contact John Lacernere, (609) 243-3308
- 4 Tier Safety Program (Initially provided by
Live Instructor) - 3 Year Re-training Cycle or as Needed
- Introductory training
- Basic electrical training
- Electrical utility training (EUT)
- High voltage maint. training (Admin by PSEG)
- Bus work is deenergized when racking breakers or
done remotely - Bus work is deenergized when racking MCC buckets
- Nothing requires working hot except
troubleshooting - CONVENIENCE IS NEVER TO OVERRIDE SAFETY
- Contractor Work
- Qualified to work electrically by PPPL beyond EUT
- Heavily supervised by PPPL, at least initially
38 Beyond BNL - Princeton Plasma Physics
Laboratory
- Raised awareness of arc flash issue across site
- Folks did not fully appreciate potential danger
- Resulted in fewer people operating
switches/breakers
39The Path Forward
- As directed by the Deputy Director of Operations
- The results of this evaluation/search will be
presented to the ALD for ESHQ, the Safety and
Health Services Manager, and the Laboratorys
Electrical Safety Committee for them to assess
the applicability to BNL.