Verification and Testing of a Differential Flow Meter Using the API MPMS Chapter 22.2 Protocol - PowerPoint PPT Presentation

1 / 25
About This Presentation
Title:

Verification and Testing of a Differential Flow Meter Using the API MPMS Chapter 22.2 Protocol

Description:

key com.apple.print.ticket.creator /key string com.apple.printingmanager /string ... key com.apple.print.ticket.creator /key string com.apple.print.pm. ... – PowerPoint PPT presentation

Number of Views:712
Avg rating:3.0/5.0
Slides: 26
Provided by: edbo1
Category:

less

Transcript and Presenter's Notes

Title: Verification and Testing of a Differential Flow Meter Using the API MPMS Chapter 22.2 Protocol


1
Verification and Testing of a Differential Flow
Meter Using the API MPMS Chapter 22.2 Protocol
  • Eric Kelner, P.E., Southwest Research Institute,
    San Antonio, TX
  • Russell Burkey, Southwest Research Institute, San
    Antonio, TX
  • Eric Reid, Rosemount-Dieterich Standard, Boulder,
    CO

2
Presentation Outline
  • Metering Research Facility
  • Background of API MPMS, Chapter 22.2
  • General requirements of the standard
  • Testing procedure and test results
  • Conclusions

3
Metering Research Facility
Built in 1991, the MRF is a high-accuracy natural
gas flow test and calibration facility capable of
simulating field operating conditions.
4
API MPMS Chapter 22.2 Background
  • In 2003, a standard defining a testing and
    reporting protocol for flow meters that produce a
    change in velocity by creating a differential
    pressure was developed by the American Petroleum
    Institute (API) Manual of Petroleum Measurement
    Standards (MPMS), Chapter 5.7 Working Group,
    entitled Differential Pressure Flow Measurement
    Devices. It was subsequently moved to MPMS,
    Chapter 22, Section 2.
  • Objectives of the standard
  • Establish performance characteristics of the
    meter.
  • Facilitate understanding and introduction of new
    metering technologies.
  • Provide a method for validating manufacturers
    performance specifications.
  • Provide a means to compare different types of
    differential pressure flow meters.
  • Quantify the measurement uncertainty of the
    device.

5
API MPMS, Chapter 22.2 General Requirements
  • Test Facility Verification
  • Traceable to NIST.
  • Must measure Cd within the 95 confidence
    interval of the R-G equation over the Reynolds
    number range of testing.
  • Baseline Tests
  • Intended to establish meter performance under
    good flowing conditions.
  • Meter located at least 30D downstream of a
    perforated plate flow conditioner.
  • Disturbance Tests
  • Intended to establish meter performance under
    worst-case velocity profile distortions.
  • Two close-coupled elbows oriented out-of-plane.
  • Half-moon plate or half-open gate valve (upstream
    and downstream).
  • Swirl Generator producing minimum of 24 degrees
    of swirl.
  • Combined upstream and downstream disturbances,
    based on previous test results.
  • Special installation tests for specific
    installations.
  • Meter location, relative to disturbances, is
    specified by the manufacturer.

6
API MPMS, Chapter 22.2 General Requirements
  • Uncertainty
  • Facility and test result uncertainty and
    uncertainty calculation methods, must be
    reported.
  • Acceptance Criteria
  • Defines whether additional testing must be done
    to eliminate (statistically) an installation
    effect.
  • Alternatively, can provide a statement of bias or
    a new Cd curve for cases with significant
    installation effects.
  • The standard allows flexibility in determining
    the acceptance criteria.
  • Reporting
  • Standardized format to facilitate comparison of
    different meters.

7
Test of Rosemount Dieterich-Standard Conditioning
Orifice Plate Flow Meters
  • In 2005, several Rosemount Dietrich-Standard
    Model 405 C and Model 1595 conditioning orifice
    plate flow meters were tested in accordance with
    API MPMS, Chapter 22.2 under BLM oversight.
  • The testing was performed in the Low Pressure
    Loop (LPL) at the Metering Research Facility
    (MRF) at Southwest Research Institute (SwRI).
    The gas flow tests performed at the MRF included
    baseline and disturbance tests.
  • The testing included five 2-inch diameter meters,
    with various beta ratios (i.e., ß 0.20, 0.40,
    0.60), two 3-inch diameter meters with a 0.65
    beta ratio, and five 4-inch diameter meters with
    various beta ratios (i.e., ß 0.20, 0.40, 0.65).
  • Results from the tests of the Rosemount Model 405
    C conditioning orifice plate flow meter are
    presented.

8
Facility Verification - MRF Low Pressure Loop
  • MRF measured Cd is within the 95 confidence
    interval of the Reader-Harris-Gallagher equation.

9
Reference Flow Meters
  • The MRF uses a bank of critical flow Venturi
    nozzles as the working flow rate standard.

10
Test Meter
  • Rosemount Model 405 C
  • Four small orifices.
  • Less sensitive to velocity profile effects than a
    standard orifice meter.

11
Baseline Tests
  • Over 100 diameters of straight pipe upstream of
    test meter.

12
Disturbance Tests Out-of-Plane Elbows
13
Disturbance Tests
  • Half-moon plate and swirl generator.
  • The swirl generator was provided by Rosemount
    Dieterich-Standard.

14
Confirmation of Swirl Angle
15
Swirl Measurement System
16
Contributions to Uncertainty
  • The following variables were accounted for in the
    uncertainty calculation
  • Meter bore diameter
  • Meter tube diameter
  • Gas temperature
  • Gas pressure
  • Meter differential pressure
  • Reference mass flow rate
  • Gas composition
  • Gas density (computed from equations of state)
  • Gas expansion factor (computed from ISO-5167)
  • Facility reproducibility
  • Point-to-point scatter in Cd (from six
    consecutive 90-second runs at each flow rate)
  • Primary element installation effects

17
Acceptance Criteria
  • Discussions between BLM and Rosemount
    Dietrich-Standard produced the following
    acceptance criteria.
  • Acceptance Criterion 1
  • Compare point by point. If the 95 confidence
    intervals for Cd for the baseline and disturbance
    tests overlap, no installation effect exists for
    that configuration.
  • If no overlap, use Acceptance Criterion 2.
  • Acceptance Criterion 2
  • Compare average Cd values over the tested range
    of Reynolds numbers.
  • If no overlap, retest using longer upstream pipe
    lengths.

18
Acceptance Criterion 1
19
Acceptance Criterion 2
20
Reporting Requirements
  • Test facility information.
  • Name, location, test fluid.
  • Pressure and temperature instrumentation
    calibration certificates.
  • Surface roughness of piping used for tests.
  • Meter information.
  • Name, type, S/N, model, size, schedule.
  • Geometry and critical dimensions.
  • Flow conditioner positioning.
  • Manufacturers Cd and flow equations.
  • Description of full test matrix and presentation
    of results.
  • Test type, meter orientation, upstream/downstream
    piping.
  • Sketch or diagram.
  • Table and plot of measured Cd, including
    uncertainty.

21
Reporting - Test Record Sheets
22
Reporting - Test Record Sheets
23
Test Results
  • For this beta ratio, the meter showed no
    additional error due to the disturbances.
  • In general, the installation effect tended to
    increase as beta ratio increased.

24
Manufacturers Recommendations Based on Test
Results
  • The table summarizes the straight run
    requirements for all models, as determined from
    the test results.

25
Conclusions
  • The testing protocol described in API MPMS,
    Chapter 22.2 can provide a thorough and rigorous
    method for testing the performance of any
    differential pressure flow meter.
  • The tests are severe and quantify meter
    performance under extreme, if not worst-case,
    flowing conditions.
  • The protocol is sufficiently standardized to
    provide apples-to-apples comparisons of various
    differential pressure flow meters, regardless of
    meter geometry.
  • The standard is subject to interpretation with
    respect to the definition of an installation
    effect and the statistical analysis.
  • These issues should be resolved during
    discussions between the manufacturer, user, and
    test laboratory operator during the development
    of the test plan.
Write a Comment
User Comments (0)
About PowerShow.com