EMgt 4110 Engineering Professionalism and Practice - PowerPoint PPT Presentation

1 / 39
About This Presentation
Title:

EMgt 4110 Engineering Professionalism and Practice

Description:

'A temporary endeavor undertaken to create a unique product or ... Cabinets. 15.03.00. Electricity. Plumbing. Trim. Ducts. 15.02.01. Chimney. 15.02.02. Furnace ... – PowerPoint PPT presentation

Number of Views:64
Avg rating:3.0/5.0
Slides: 40
Provided by: hongy7
Category:

less

Transcript and Presenter's Notes

Title: EMgt 4110 Engineering Professionalism and Practice


1
EMgt 4110 Engineering Professionalism and Practice
  • Project Management

2
Project
  • A temporary endeavor undertaken to create a
    unique product or service

PMI (Project Management Institute) Standards
Committee, A Guide to the Project Management
Body of Knowledge (PMBOK) Upper Darby, PA PMI,
1996, p.167
3
Three Dimensions of Project Goals
Cost
Target
Performance
Time
Adapted from Milton Rosenau, Successful Project
Management (Belmont, Ca. Lifetime Learning
Publications, 1981), 16.)
4
Stages
  • Project Definition
  • Project Selection (financial aspects,
    non-financial or intangible aspects)
  • Project Planning
  • Project Execution (control)
  • Project Termination (evaluation)

5
Time Distribution of Project Effort
Peak Effort Level
Level of Effort
Time
Evaluation And Termination
Planning, Scheduling, Monitoring, Control
Conception
Selection
6
Relative Uncertainty of Ultimate Time and Cost by
Life-Cycle Phase
From Russell D. Archibald, Managing
High-Technology Programs and Projects, Wiley, New
York, 1976, p.23
7
Project Planning
8
Project Plan - Contents
  • Objectives
  • Benefits
  • Scope of Work
  • Project Team Organization
  • Schedule (Network, Milestones)
  • Resources (equipment, labor, contractors)
  • Budget (detail, controls)

9
Project Plan - Purpose
  • Baseline for Evaluating and Controlling Progress
  • Highlight Critical Issues
  • Coordinate with External Parties
  • Communicate to Affected Parties

10
Action Plan
Deliverables
Measure(s) of accomplishment
Key constraints and assumptions
Immediate predecessor tasks
Estimated time duration
Estimated resources
Assigned to
Tasks
11
Work Breakdown Structure
  • Hierarchy of Tasks
  • Higher levels contain summary tasks
  • Lowest level tasks represent actual work
  • Divide along Physical or Specialty Boundaries?
  • Use a Coherent Numbering System
  • Tie Numbering into Schedule, Budget

12
Example of WBS for Building a House
13
Responsibility Interface Matrix (RIM)
Persons or Positions Responsible
Project Engineer
Basic Design
A
Project Element or Work Package
Responsibility Code P Primary Responsibility S Sec
ondary Responsibility N Must be Notified A Must
Give Approval
Structure of a Responsibility Matrix
14
Sample of Responsibility Interface Matrix (RIM)
From Kocaoglu, D.F. and Cleland, D.I. RIM
Process, Management Review 1982
15
Reporting Relationship Matrix
16
Remember...
  • Obtaining Permits/Licenses
  • Generating Reports
  • Get a Second Opinion!
  • Identify Key Milestones
  • Identify and Address All Deliverables
  • FOCUS ON THE OBJECTIVES

17
Project Scheduling
18
Project Scheduling
  • Core of project management
  • Time dimension of project plan
  • Shows logical relationships between tasks
  • Determines completion date and milestone dates
  • Identifies critical items

19
Schedule Elements
  • Tasks/activities (have duration)
  • Milestones (no duration, important events)
  • Relationships
  • Time line (hours, days, weeks, months)

20
Network Techniques
  • CPM (Critical Path Method)
  • Designed for construction projects
  • Activity-on-arrow vs. Activity-on-node
  • Converted from action plan
  • PERT (Program Evaluation and Review Technique)
  • Time oriented
  • Use probabilistic activity time estimates
  • PERT/CPM

21
Network Techniques
  • Network The arrangement of all activities (Arcs)
    and events (nodes at the beginning and end of an
    arc), defining the project and the
    predecessor-successor relationships among
    activities.
  • Path Series of connected activities or
    intermediate events between any two events in a
    network.

22
Project Scheduling Definitions
  • Critical Activities/Events Activities/Events
    which, if delayed, will delay the completion of
    the project.
  • Critical Path
  • Sequence of critical activities and
    critical events that connect the projects start
    event and finish event.

23
Gantt Chart
Week
24
A Hierarchy of Bar Charts
Top Level
Intermediate Level
Bottom Level
25
Project Management Software
  • Professional Packages
  • Over 2000 cost
  • Very flexible, multi-project capability
  • Primavera Project Planner (P3)
  • Personal Packages
  • Under 500 cost
  • Canned views, reports, graphics
  • Microsoft Project

26
Resources Allocation and Budget
27
Resource Allocation
  • Standard PERT/CPM methods assume project is time
    constrained
  • Resource constrained projects are common
  • Resources
  • People
  • Equipment
  • Space

28
Project Budget
  • Budget is also a control mechanism
  • Top-Down Budgeting
  • Bottom-Up Budgeting
  • Combined

29
Estimating
  • Total Cost Estimate
  • Target Accuracy (5-15)
  • Follow the WBS and Schedule
  • The Cost of Estimating Time Accuracy

30
Elements of an Estimate
  • Material Cost
  • Get quotes on big-dollar items
  • Estimate other items
  • Remember tax and freight (11)
  • Labor Cost
  • Hours per task
  • Hourly rates
  • Overhead (Overtime, meals, sick pay, holiday pay,
    etc.)

31
The Other Costs
  • Design, engineering
  • Permits, fees
  • Interest expense
  • Equipment rental, leases
  • Secretarial, administration, document
    reproduction, phone calls, fax
  • Overhead
  • Contingency/Escalation

32
Spending Plan
  • Budget Meets Schedule
  • Month-by-Month Spending
  • Budget Tied to Achievement
  • Cumulative Spending Curve
  • Distribute Indirect/Other Costs

33
Project Monitoring and Control
34
Planning vs. Control
  • Planning concentrates on setting goals and
    directions Control guides the work toward those
    goals
  • Planning allocates resources Control ensures
    effective, ongoing utilization of those resources
  • Planning anticipates problems Control corrects
    the problems
  • Planning motivates participants to achieve goals
    Control rewards achievement of goals

35
Controlling
  • Plan
  • Review of the Plans Previously Instituted for
    the Objectives in Question
  • Measuring
  • Determining the Current Level of Accomplishment
    or Progress toward the Given Objectives
  • Comparison
  • Comparing the Measured Actual Performance to
    Planned Performance at the Current Stage of
    Events
  • Evaluating
  • Identifying Significantly Unfavorable Deviations
    from Planned Performance
  • Re-planning
  • Determining What Courses of Action are Needed to
    Bring Performance Up to or Beyond Previously
    Planned Level to What Defined Objectives can be
    Achieved to Exceeded
  • Correcting
  • Implementing the Corrective Actions as
    Determined above

36
Project Control Cycle
Measure
Take Corrective Action
Compare and Evaluate
37
Gantt Chart Showing Work Status as of Week 20
38
Corrective ActionCrashing
  • Compute a cost/time slope for each activity that
    can be expedited (crashed)
  • Focus on the critical path(s)
  • Crash activities one at a time to decrease
    project duration at the minimum additional cost.

39
Trend Projection
Write a Comment
User Comments (0)
About PowerShow.com