Title: CHAPTER 9, MAKING A CHOICE AND PRESENTING THE BUSINESS CASE
1CHAPTER 9, MAKING A CHOICE AND PRESENTING THE
BUSINESS CASE
- A conclusion is sometimes the place where you got
tired of thinking
2Figure 9.1, the problem-solving model
3MAKE A CHOICE
- Other things being equal, the best alternative to
choose will be the one having these
characteristics - an acceptable level of risk,
- the largest benefits (financial and/or
non-financial), - the lowest costs,
- the best benefit/cost ratio.
- The choice of best alternative should be
immediate and unanimous. If not, go back to the
beginning of the model.
4Figure 9.2, Make a choice checklist
Yes/No
5The Evaluation Process
- The evaluation of alternative courses of action
is a three-stage process - 1. Data Collection
- 2. Analysis
- 3. Evaluation
6The Evaluation Process
- 1. DATA COLLECTION
- There are three types of data
- Quantitative data based on observations.
- Qualitative data based on observations.
- Data based on the opinions, intuition and
personal judgment of experts.
7The Evaluation Process
- 2. ANALYSIS
- Before ranking begins, the quality of the
information to be used in the evaluation needs to
be tested. - Good information should be used in the analysis,
bad information should be discarded..
8The Evaluation Process
- 3. Evaluation
- 1. Identify all major assumptions used in the
collection of data. - Time frame
- Physical life (Projected operating life).
- Technological life (equipment obsolescence).
- Product useful life (economic obsolescence).
9The Evaluation Process
- Cost data
- Sum of dollars associated with the total project
cycle, from the business case preparation to post
implementation evaluation. - Benefits/savings data
- Increase in revenues and/or decrease in costs
over the life of the project. - Increase in efficiency/productivity.
10 The Evaluation Process
- 2. Identify operating and non-financial impacts
- employees with appropriate skill sets may be
unavailable when required - availability of technology and support systems
- environmental impact
- compliance with legislated/regulatory
requirements. -
- 3. Risks
- Identify any risks that could affect the
expenditure initiative.
11The Evaluation Process
- The evaluation system used for non-financial
impacts will be different for each situation.
(There is no standard practice for evaluating the
impact of a suggested solution on customer
perception or employee perception for example. ) - In the case of financial evaluation, there is a
standard procedure..
12Financial Evaluation
- Chapter 8 dealt with the mechanics of the
financial evaluation NPV. B/C Ratio, Payback
period and IRR. - Financial analysis is quite narrow.
- There is more to the health of people, the
reduction of crime, and the safety of fish than
can be measured with money.
13Non-Financial Evaluation
- Some business cases need to be advanced even
though they do not have benefits that can be
measured in financial terms. - Their true impact could only be measured using
some other measurement scale.
14Non-Financial Evaluation
- Even when alternatives have no financial benefits
of any form, they all have a financial cost. - One method to help rank non-financial
alternatives in order of preference is to use
financial costs to drive the rankings. This is
called Critical Values analysis.
15Non-Financial Evaluation
- Imagine that park in the neighbourhood has a
present value of financial costs of negative
712,800 which comes from the financial
spreadsheet assuming a 500,000 construction cost
and 25,000 per year in maintenance for an
estimated 20 year life of the project. - As there are no financial benefits, the present
value of the costs of the park must be matched to
the users of the park.
16Figure 9.3, Non-financial analysis input screen
17Figure 9.4, Critical Values
18Figure 9.5, The Value Of A Park Visit
This is to say that we are investing 27.91 in
each park visit per person. The financial value
would then be matched against some qualitative
judgement. Does it make sense to pay that much
per park visit?
19Non-Financial Evaluation
- Sometimes a business case has more than one
social impact. For example, if our project will
also create five new jobs in the region we split
the investment between the two Social accounts.
- The investment made per job is 8,366.20 and the
investment per park visit is 13.95.
20Figure 9.6, Shared benefits
21THE EVALUATION MATRIX SPREADSHEET
- The third tab on the spreadsheet presents a tool
that might be useful in the ranking and selection
of alternative solutions to a problem. - The tool enables the decision-maker to rank
alternatives against the criteria that meet the
requirements of the strategic plan.
22THE EVALUATION MATRIX SPREADSHEET
- Step 1, Establish Decision Criteria
- Step 2, Apply Weighting Factors.
- Step 3, Rank the Alternatives Against Each
Criteria. - Step 4, Calculate the Weighted Scores.
- The result of this analysis is that the
alternative that best meets the most important
criteria will be given the highest numerical
value.
23Figure 9.7, evaluation matrix
24INTEGRATING THE EVALUATION WITH YOUR BUSINESS CASE
- The spreadsheets are only tools to support the
business case. - The case itself will be a combination of
quantitative analysis provided by the
spreadsheets, and qualitative analysis provided
by the text of the case.
25Implementation plan and Control Systems
- Controlling projects and initiatives is an
absolutely critical element of being effective in
a management situation. - There are two focus areas in developing control
systems to manage expenditures.
26Implementation plan and Control Systems
- The first is to control the scope, time and money
spent while a project is being constructed, and - the second is to control the operation of the
project while costs are incurred and benefits are
earned.
27IMPLEMENTATION PLAN
- A project can only be called a success when the
implementation has proceeded, the project has
created the anticipated benefits, and there is a
measure of the benefits received. - The implementation plan deals with two elements
- What has to happen to be successful?
- How will you know if you have achieved the
benefits?
28IMPLEMENTATION PLAN
- Step 1, Build the project
- The construction phase should identify project
management responsibilities - Assign individual(s) to
- be in charge of the overall project
- plan the project schedule
- determine resource requirements
- ensure that the project is completed on
time/within budget
29IMPLEMENTATION PLAN
- Timetable
- Develop a timetable to cover all phases of the
project that includes - project duration
- area of responsibilities
- key project events
- deliverables and due dates
30IMPLEMENTATION PLAN
- Resource impacts
- 1) CAPITAL BUDGETS
- 2) OPERATING BUDGETS
- 3) NON-FINANCIAL BUDGET
31IMPLEMENTATION PLAN
- Step 2, Control the Results
- The difference between a budgeted amount and an
actual amount is called a variance. It is the
variance that causes a management reaction.
Variances are a powerful management tool to use
to control a process.
32VARIANCES AS A MANAGEMENT TOOL
- To be useful as a tool, we must consider the
following - The variance fairly reflects a manager's control
area. - The variance isolates relevant deviations from
the plan. - Management reaction is appropriate to the
magnitude and severity of the variance. - The act of isolating variances and taking
corrective action causes desired changes in
behavior.
33VARIANCE ANALYSES, MANAGEMENT BY EXCEPTION
- When performance is evaluated, two factors are
considered - Has there been a deviation from the plan? If so
how large? - Was the deviation controllable, and by whom?
34VARIANCE THEORY
- A variance analysis will generate observations
like. - Spending on materials and labour is 50,000
higher than expected. - Customer demand is 15 less than expected
- Customer satisfaction is 15 greater than
expected - The emission if solid particulates into the
airborne environment is 5 more than expected - The impact on the economic system in terms of job
creation is 7 more than expected
35Variances
- Variances
- identify the presence of a deviation from the
plan - attach a value to the deviation from the plan
- identify possible cause areas.
- Variances do not
- Fix blame
- Suggest remedies
36Remedial action may involve the following
activities
- Directing the process into an "in control state",
by forcing the process to meet the budget. - Changing the budget if the variance was caused by
a permanent change in operating conditions which
causes the budget to be wrong - Ignoring the variance and taking no corrective
action on the assumption that the variance was a
temporary aberration that will not repeat itself
37WHEN TO INVESTIGATE VARIANCES
- Variances should be investigated when the cost of
investigating and correcting the process is less
than the cost of allowing the process to continue
in its out of control state. - A process appears to be heading for an out of
control state. - The variance is minimal but repeats itself
constantly. - The investigation may have a desired behavioral
side effect.
38Making Effective Presentations
- Effective business communication uses objective
language. We must persuade the reader that the
information we are providing is accurate,
deserving of consideration, relevant and
important. - What we say and how we say it should be driven by
the needs of our reader. - It is important to align your written and oral
submissions with the information needs of the
reader in a convincing manner.
39Effective business presentations
- Planning
- Clearly establish the objectives and style of the
report to meet the reader's needs. - Using a Logic Model
- Overcome resistance to change by presenting a
conclusion that is supported by objective facts
and sound business rationale. - Proving the Conclusions
- Provide evidence as to the source of information
used in the analysis and evidence of the costs
and benefits associated with the solution to a
problem.
40PLANNING YOUR CASE PRESENTATION
- Set your objective.
- What do you wish to accomplish as a result of
your submission? - What must you convince the audience of to achieve
your objective? - What conclusions will you guide your audience to
reach?
41PLANNING YOUR CASE PRESENTATION
- Identify the concerns you have of the audience
and their - Perspective, (Financial? Performance? Image?)
- Prior knowledge
- - What do they know of your submission?
- - What do they not know?
- Attitude
- - Indifference?
- - Acceptance?
- - Objection?
42PLANNING YOUR CASE PRESENTATION
- Identify additional conclusions the audience must
reach based on the audience analysis. - Identify the proof that can be provided to
support each conclusion the audience is required
to reach. - Order your conclusions and proofs in descending
order of importance to your audience. What will
they want to hear first? - Identify the appropriate language to use with the
given audience. - Is your language personal?
- Are you communicating in the active voice?
- Are you using language that is simple and easy to
understand? - A business case presentation must stand alone.
43BUSINESS CASE REPORT FORMAT
- A perfect business case will leave no questions
in a reader's mind, and will allow a logical and
informed decision to be made. - A) PREAMBLE
- Describe the "big" picture.
- B) PROBLEM DEFINITION
- Clearly identify the problem being solved.
- C) RECOMMENDED SOLUTION
- Identify the alternative chosen early in the
report. - D) SELECTION CRITERIA
- Offer a description of the criteria used to make
the choice
44BUSINESS CASE REPORT FORMAT
- E) ALTERNATIVES
- Demonstrate to the reader that a sufficient
number of good quality alternatives were
considered. - F) ANALYSIS OF ALTERNATIVES
- Non-financial issues and Financial Issues
- G) IMPLEMENTATION PLAN FOLLOW UP
- Offer a detailed implementation plan including
project timelines and management
responsibilities, as well as a description of the
measurement tools that will be used to track
progress and identify project benefits and costs. - H) RISK ASSESSMENT
- A detailed description of all risk elements,
including project specific risk and environmental
risks should be included.
45PROVING YOUR CONCLUSIONS
- It is not sufficient evidence to simply say, "I
believe this to be true" or "It is common
knowledge that..." - Credible evidence will be presented as
- Example
- Expert testimony
- Analogies
- Statistics
- Personal experiences
- The emphasis should be on quality over quantity.
Too much evidence can be as confusing as too
little.
46CONCLUSIONS REGARDING PRESENTATIONS
- Business communications are concise, factual and
to the point. - An illogical or unsupported approach to
communicating solutions to problems may result in
deferred action, even though the chosen action
best solves the problem. - The most efficient communicators will tailor the
presentation to the needs and perceptions of the
audience.
47CONCLUSIONS REGARDING PRESENTATIONS
- Good communications will actually improve the
decision making process. - It may be advisable to have your document
reviewed by a colleague prior to final
submission. The author is often too close to the
document to notice deficiencies in presentation
style. - Make a point of learning from every proposal you
submit, the good ones and the bad ones. - Make a point of using the financial analyst for
your business unit or department. This person
can make your job easier.
48Chapter summary
- Making a choice is easy if the analysis is
complete and logical, - controlling the project is easy if expectations
re reasonable and variances are reviewed
frequently, and - making a presentation is easy if a model is used
that satisfies the logic of the listener. - Its all easy if you follow a model. It becomes
difficult, confusing and frustrating when you
depart from logic and start being random or
relying on gut feel or personal opinion.
49Closing Remarks
- There is one last aspect of business casing that
needs to be covered. It deals with performance
measurement, or showing evidence that the results
we are looking for are actually occurring. - The concept of performance measurement and
performance management are cover in section 3,
chapters 10-12.