PUBLIC PRIVATE PARTNERSHIPS PPP The Advantages - PowerPoint PPT Presentation

1 / 40
About This Presentation
Title:

PUBLIC PRIVATE PARTNERSHIPS PPP The Advantages

Description:

Note: PPP's can create contingent liabilities for purchaser of services ... 6 : Raw Materials Supply Contract. 7 : Sales Purchase Contract ... – PowerPoint PPT presentation

Number of Views:350
Avg rating:3.0/5.0
Slides: 41
Provided by: tmblai
Category:

less

Transcript and Presenter's Notes

Title: PUBLIC PRIVATE PARTNERSHIPS PPP The Advantages


1
PUBLIC - PRIVATE PARTNERSHIPS PPPThe
Advantages Limitations
January 2005 UPU, Berne
T.M.Blaiklock Tel 44208-255-3851 e-mail
tmblaiklock_at_aol.com
TMB
2
Investment Projects in Public Services
  • OPTIONS for Government
  • Implement a project conventionally, funded
    ex-budget or with loans against Govt. guarantee
  • OR
  • Implement project as a PPP (or PFI).
  • Note
  • PPP provision of a public service by the
    private sector
  • PFI capital investment by private sector for
    public service provision

TMB
3
What is a PPP?
  • The Public Sector (i.e. Government)
  • - identifies the demand for a public service
  • - defines the service outputs
  • - agrees long-term concession (franchise) for
    the service
  • - payment made against performance measures
  • - imposes regulatory regime
  • The Private Sector
  • - provides service
  • - design, builds, finances, operates and
    maintains the service and
    the
    assets
  • - operates within regulated environment
  • i.e. public interest requirements

TMB
4
PPP in Public Services
Benefits
Constraints
  • off-balance sheet (?)
  • introduces private sector capital
  • introduces private sector practices
    efficiencies
  • promotes competitive markets
  • facilitates innovation

TMB
5
On or Off Balance Sheet?
PPP is Off Balance Sheet if (a)
construction/completion risk carried by PPP
concessionaire AND (b) either demand or
availability risk carried by PPP
concessionaire. ref. EU Decision for Balance
Sheet Treatment of PPPs Feb 2004 Note
PPPs can create contingent liabilities for
purchaser of services
TMB
6
ELEMENTS OF PROJECT FUNDING
At Risk
Equity Debt
Typical Debt/Equity Ratios
Hotels property 50/50 Industrial projects
70/30 Infrastructure power 80/20 PPPs
90/10
No Risk
  • Grants and subventions

TMB
7
SOURCES OF FUNDS PPPs
TMB
8
PPP INVESTMENT CRITERIA
  • IRR / Equity IRR
  • Investment Period

At Risk
Equity Debt
No Risk
  • Grants and subventions

TMB
9
SOURCES OF FUNDS PPPs
TMB
10
Question against what security are loans
provided?Answer
SECURITY FOR LENDERS
  • sovereign or government risk
  • corporate risk
  • cash-flows
  • limited / non-recourse
  • Project Financing
  • PPP Concessions

TMB
11
History of PPPs
UK, Europe Rest of World excl. USA
Cash-Flow / Bank, ECA IFI Loans - - - - - - -
- Bond Issues
Govt. Corp. Gtees
Private Co.s - - - - - - - - - Privatisations - -
- - - - -Services - - - - - - - -
North Sea Oil
Minerals Nat. Resources
Power Telecoms Infrastructure Public
Services

PFI
PPP
U.S.A.
- - - - - - - - - - - - - - - - - - Industrial
Revenue Bonds - - - -- - - - - Comm. Bk. Loans--
Municipalities Govt. Agencies
Private Corporations, PICs - - - - - - - - - - -
- - - - - - - - - - - - - - - - -
Turnpikes Power Oil/gas Pipelines Airports,
Water- - - - - - - - - - -
PPP
2000
1990
1980
1970
1960
TMB
12
FUNDING STRUCTURE PPP
Regulatory Regime.

Contractor
Operator Maintenance
Purchasers
Sales Contract.
Revenues
Construction Contract
O M Contract
O M Payments(1).
Supply Contract
Escrow Acct.
Supplier raw materials fuel
PROJECT COMPANY Concessionaire
Surplus(3)
Debt Service Payments (2)
Share Subscription Agreement
Loan Aggts.
Dividends
Concession Aggt. e.g. PPP
Lenders ECAs IFIs banks (Inter-credit
. Aggt.)
3rd Party Gtees.
Investors
The Engineer
GOVERNMENT Purchaser of Public Service
TMB
13
PPP AGREEMENTS
  • 1 Implementation Agreement.
  • 2 Concession Agreement
  • 3 Construction Contract
  • 4 Operations Contract
  • 5 Maintenance Contract
  • 6 Raw Materials Supply Contract
  • 7 Sales Purchase Contract
  • 8 Special-Purpose Company Documents
  • 9 Share Subscription Contracts
  • 10 Loan Agreements
  • 11 Inter-creditor Agreement
  • 12 Escrow Account / Trustee Arrangements
  • 13 Insurance
  • 14 Licences Permits Bills Decrees

TMB
14
PPP INVESTMENT CRITERIA
  • IRR / Equity IRR
  • Investment Period

At Risk
Equity Debt

No Risk
  • Cover Ratios
  • Risk Analysis
  • Grants and subventions

TMB
15
Project Finance House of Risk
Construction Contract
Permits Licences Bills Decrees
Insurance
Concession Implementation Aggt.
Mortar Risk
Sales Contract
O M Contract
Inter- creditor Escrow Aggts.
Supply Contract
Share- holders Aggt.
SPCo Docs
Loan Aggts.
TMB
16
PPP RISK MATRIX
TMB
17
PPP LENDERS CRITERIA
Debt Service Cover Ratio periodic Free
Cash Flow
Fixed Charges
Free Cash Flow Net Operating
Profit plus depreciation less
increase in working capital less
incremental cap. expenditure less
tax Fixed Charges loan principal
interest payts. plus mandatory dividends,
lease payts.
TMB
18
PPP v. Conventional Project Funding?
TMB
19
CONVENTIONAL FUNDING STRUCTURE (1)PAID FROM
GOVERNMENT BUDGET
Contractor or Supplier

EPC Contract
PURCHASER Govt. Agency
BUDGET FUNDS
Govt.
TMB
20
CONVENTIONAL FUNDING STRUCTURE (2)GOVERNMENT
GUARANTEE
Contractor or Supplier

EPC Contract
PURCHASER Govt. Agency
Equity Grant / Subvention
Loan Aggts.
Lenders ECAs IFIs banks (Inter-credit.
Aggt.)
The Engineer
Govt.
Govt. Gtee
TMB
21
Cost of Conventional Project Purchase
  • METHODOLOGY
  • 1 Prepare a Public Sector Comparator PSC
  • 2 Undertake a Value for Money VFM
    assessment

TMB
22
Cost of Conventional Project Purchase
  • Methodology for PSC
  • 1 Base Cost estimates (NB. full life cycle)
  • 2 Concept of Optimism Bias
  • 3 Risk assessment allocation
  • NB. subjectivity of risk
  • 4 Value Retained Risks
  • 5 Value Transferable Risks

TMB
23
Project Cash-Flows
Revenues less Opcosts
240
205
Value
180
200
110
100
2004 today
2006
2005
0
Time
2004 Today
2005
2007
2008
2009
2010
- 100
Capital Costs
(120)
(90)
- 200
(180)
TMB
24
PSC v. PPP
139.05
125.10
Optimism Bias 39.82
NPV Cost of Service Payments 120.00
Cost NPV _at_ 3.5
Option A is better than PSC
NPV Base Costs 94.13
Retained Risk 5.10
Retained Risk 5.10
PSC
PPP Option A
TMB
25
PSC v. PPPValue for Money
1 evaluate PPP bids versus PSC 2 identify
material factors not included in PSC
e.g.- - wider cost savings
efficiencies - innovation - technology
transfer - quality of service delivery -
wider economic social benefits dis-benefits
(e.g. pension
transfer issues)
TMB
26
The PPP Bid Process
TMB
27
THE PPP PROJECT PROCESS
TMB
28
THE PROJECT PROCESS

Time
Phases
PPP
Govt.
Pre-Qualification
2-3mth (2 mth)
3-6 mth (3 mth)
Tendering
3 mth (3 mth)
Negotiations
Formation of SPC Complete Financial
Aggts.
3-9 mth (3 mth)
Financial Close
3-6 mth (2 mth)
Total 14-27mth (13 mth)
TMB
29
PPPsIssues Arising
  • employment issues transfer of staff to the
    PPP option
  • basis of Public Sector Comparator (PSC) and
    Value for Money (VFM)
  • e.g. discount rate to be use the assessment and
    allocation of risk
  • common contractual terms and documents
  • windfall gains from re-financing the nature
    of the Partnership
  • short-term perspective of investors secondary
    equity
  • contingent liability of Govt. contractual
    payments
  • EU procurement rules conflicts with realistic
    negotiation process

TMB
30
PPPsIssues Arising
  • lack of skills in utility operations original
    investors sell-off
  • high up-front bidding costs for PPP
    concessions.
  • Impact of financial strength of bidders
  • skills shortage in sponsor Govt. departments
    and agencies.
  • independence of financial advisors and
    conflicts of interest
  • public interest companies safety v.
    profits (transport)
  • complexity of PPP are the costs justifiable?
  • Govt. life cycle shorter than project maturity
    of PPPs

TMB
31
PPP in Public Services
Benefits
Constraints
  • off-balance sheet
  • introduces private sector capital
  • introduces private sector practices
    efficiencies
  • promotes competitive markets
  • facilitates innovation
  • complex structure documents
  • time-consuming to arrange
  • high up-front costs
  • demands significant senior staff attention
  • project choice important
  • PSC methods need refining
  • difficult to resolve when in default
  • needs legal framework
  • corporate governance (?)

TMB
32
USEFUL SOURCES OF INFORMATION
  • www.hm-treasury.gov.uk
  • www.dft.gov.uk
  • www.nao.gov.uk
  • www.scotland.gov.uk
  • www.parliament.uk
  • www.partnershipsuk.org.uk
  • www.europa.eu.int
  • www.worldbank.org
  • www.ebrd.org
  • www.ipfa.org
  • www.partnerships.vic.gov.au
  • _________
  • PFI Report IFR Project Finance Intl.
  • Euromoney Project Finance Infrastructure Journal

TMB
33
Some PPP Applications
TMB
34
TYPES OF PUBLIC SERVICE PROJECT
  • Power Stations thermal nuclear hydro CHP
    wind.
  • Mass Transit metros LRTs bus-ways.
  • Road, Rail Bridges toll-roads.
  • Water Industry irrigation desalination
    clean/dirty water.
  • Public Services offices school buildings
    hospitals prisons law courts
  • ___________________
  • Air Transport airports ATC IT systems.
  • Ports container ports bulk handling.
  • Oil Gas pipelines refineries facilities.
  • Petrochemicals agro-industries.

Regulated PPPs
Unregulated non-PPP
TMB
35
UK PPPs Sectors
  • Health 11
  • Transport 6
  • Defence 4
  • Water Waste Water 6
  • Accommodation Police 4 )
  • Accommodation Education 21 )
  • Accommodation Health 17 )
  • Accommodation Other 11 )
  • IT Education 1
  • IT health 3
  • IT - Other 12
  • Prisons 4
  • 100
  • Total Value Euro 50 billion

53
TMB
Source Infrastructure Journal Aug 2002
36
Typical PPP Contractual Structure

e.g prisons hospitals schools office
buildings warehouses
Govt. Agency or Trust
Concession Aggt.
Payts. For Availability
Shareholders
SPCo
Financiers
Building Contractor Facilities Manager
TMB
37
Min. of Defence Facilities Management PPP
  • Project to provide warehousing services for
    the Navy
  • Client Royal Navy
  • Value Euro 40 million
  • Benefits innovation flexibility
  • efficient use of property
  • cuts transport costs
  • Note post 2003, min. PPP value Euro 30
    million

TMB
38
Inland Revenue HM Customs ExciseOffice
Building PPP
  • Project to sell and lease back 600 office
    buildings in UK
  • Value Euro 600 million
  • PPP Concessionaire Mapeley UK Ltd.
  • Benefits flexibility
  • efficient property management for Govt.
  • Issues Mapeley not financially strong,
    although shareholders strong.
  • Mapeley UK Ltd based offshore in tax haven
  • NB there are many successful UK office
    building PPPs

TMB
39
Magistrates Courts IT System PPPLibra
Project
  • Project to provide IT system for the Crown
    Prosecution Service and for Courts management
  • Client Lord Chancellors Office (i.e.
    Government)
  • PPP Concessionaire ICL / Fujitsu
  • Value Euro 400 million
  • Issues changes in specifications
  • underestimate of R D costs
  • lack of understanding of PPP for both parties
  • difficulties when problems arose
  • Result No more IT PPPs in the UK

TMB
40
Navcanada Air Traffic Control PPP
  • Project to provide air traffic services in
    Canada
  • PPP Concessionaire Navcanada (Crown / trust
    corp.)
  • Value Euro 600 million
  • Issues strong predictable cash-flows
  • hard currency revenues
  • non-Government interference
  • private sector management regime
  • off balance sheet
  • Result survived commercial impacts of 9/11,
  • cf. NATS in UK.

TMB
Write a Comment
User Comments (0)
About PowerShow.com