Title: Tees Valley Resource Efficiency Club Half Day Workshop Energy Management Renewable Energy
1Tees Valley Resource Efficiency Club Half Day
WorkshopEnergy ManagementRenewable Energy
Paul McQuillan EIA Consultant Atkins
2Why consider renewable energy?
- Prices of fossil fuels and electricity are likely
to rise in the future - Carbon targets for buildings (the Merton Rule)
- Government incentives and grant funding may be
available - Green credentials status
3Renewable energy options
- Wind
- Solar PV
- Solar Thermal
- Bioenergy (biofuels)
- Ground source heat pumps (geothermal)
- Not discussing hydroelectricity, tidal, wave or
offshore wind
4Renewable energy options
- Electricity
- Wind
- Solar PV
- Space heating
- Biomass
- Ground source heat pumps
- Hot water
- Solar thermal
5Wind
- Wind used to create electricity
- Energy output determined by wind speed
- Turbine changes direction to face wind
direction - Energy output increases with rotor diameter
6Solar PV
- Uses solar energy to create electricity
- Best location is south facing and 50 angle
- Duration and strength of sunlight hours in a
year - Energy output is determined by area of PV cells
7Bioenergy
- Uses biological materials to derive heat
energy - Energy derived from wood, straw, crops, animal
waste - Energy output determined by the material and
the boiler - Environmental impacts of combustion of wastes
- Availability of biomass fuels
- Carbon neutrality?
8Ground source heat pumps
- Uses geothermal energy to create heat energy
- Open loop, closed vertical loop or closed
horizontal loop - Sub surface temperature stable at 10 C to
12C - Available land
9Solar Thermal
- Use solar energy to create hot water
- Best location is south facing
- Flat plate or evacuated tube
- Energy output is determined by surface area
10How do you know which is suitable
- Solar roof space
- Geothermal land available
- Bioenergy boiler
- Wind height above ground
11(No Transcript)
12How do you know which is suitable
DTI wind speed database
Power 0.5 x density of air x area x velocity3
13Grant funding available
- Low Carbon Buildings Programme
- Applications for 2007 are closed
- Further funding may available to commercial
organisations from March 2007. - Large commercial organisations including
developers could apply for up to 40 of the total
installation costs. - Small to medium sized enterprises (SMEs) were
entitled to an extra 10 uplift and could apply
for up to 50 of the total installation costs. - Stream 2A - was allocated over five funding
rounds with maximum grants of 100k or 40-50 of
total costs (excl. VAT). Stream 2A closed on 28
September 2007. - Stream 2B - was allocated over four funding
rounds with a maximum grant of 1m or 40-50 of
total costs (excl. VAT). Stream 2B closed on 14
September 2007 - See the website at www.lowcarbonbuildings.org.uk
14Grant funding available
- Enhanced Capital Allowance Scheme
- Enhanced Capital Allowances (ECAs) enable a
business to claim 100 first-year capital
allowances on their spending on qualifying plant
and machinery. There are three schemes for ECAs - Energy-saving plant and machinery
- Low carbon dioxide emission cars and natural gas
and hydrogen refuelling infrastructure - Water conservation plant and machinery
- Businesses can write off the whole of the capital
cost of their investment in these technologies
against their taxable profits of the period
during which they make the investment. - This can deliver a helpful cash flow boost and a
shortened payback period.
15Grant funding available
- Carbon Trust Interest Free Loans
- Energy-Efficiency Loans from the Carbon Trust are
a cost effective way to replace or upgrade your
existing equipment with a more energy efficient
version. - Small or medium-sized enterprises (SMEs) in
England could borrow from 5,000 to 100,000. It
is unsecured, interest free and repayable over a
period of up to 4 years. - See www.carbontrust.co.uk/energy/takingaction/loan
s.htm
16Grid connection or not?
- Unit cost to sell to grid is 3p per kWh
(approximately) - Unit cost to buy from grid is 6-10p per kWh
(approximately)
17Planning issues - wind energy
18Key planning constraints
- Residential Amenity
- Noise
- Shadow Flicker
- Aeronautical Impacts
- Civil
- Military
- Radio-Communication Link Impacts
- Ecology
- Visual Impact
19Noise
- Two distinct types of noise source
- Mechanical Noise - produced by the gearbox,
generator and other parts of the drive train - Aerodynamic Noise - produced by the passage of
the blades through the air - Recommended Good Practice on Controlling Noise
from Wind Turbines - The Assessment and Rating of Noise from Wind
Farms (ETSU for DTI 1997) - describes a framework for the measurement of
wind farm noise and gives indicative - noise levels calculated to offer a reasonable
degree of protection to wind farm neighbours - ..should be used by planning authorities
when assessing and rating noise from - wind energy developments
- Planning Policy Statement 22 Renewable Energy,
Companion Guide
20Noise
Without background noise data - requirement to
demonstrate turbine noise at the nearest
residential property is lt35dB. - Turbines gt
225kW typically a separation distance of 400m
- Micro-generation (i.e Turbines lt 20kW)
typically a separation distance 170m With
background noise data requirement to
demonstrate turbine noise at nearest residential
property is lt 5 dB(A) above background
levels Noise from the wind farm should be
limited to 5 dB(A) above background for both
day- and night-time. (ETSU, 1997) - Turbines
gt 225kW typically a separation distance of
350m
21Noise Constraints - Solutions
Ensure a satisfactory separation distance can be
achieved Commission an appropriate level of
background noise assessment work
22Shadow Flicker
Under certain combinations of geographical
position and time of day, the sun may pass
behind the rotors of a wind turbine and cast a
shadow over neighbouring properties. When the
blades rotate, the shadow flicks on and off the
effect is known as shadow flicker. It only
occurs inside buildings where the flicker appears
through a narrow window opening. PPS22 Companion
Guide Only properties within 130 degrees either
side of north, relative to the turbines can be
affected at these latitudes in the UK Flicker
effects have been proven to occur only within ten
rotor diameters of a turbine i.e. 80m diameter
turbine blades potential shadow flicker up to
800m
23Shadow Flicker - Solutions
Avoid sites with large populations of residential
properties close to the turbine and immediately
to the north Commission a shadow flicker
assessment to assess nos. of affected
properties Fit a photosensitive cell to the wind
turbine
24Aeronautical - Civil
Key Consultees gt Civil Aviation Authority
(CAA) gt National Air Traffic Services (NATs) gt
Aerodromes within 30km of proposed wind turbine
(Newcastle Airport Durham Tees Valley
Airport) Other Interests gt Unlicensed
Aerodromes gt Parachuting Activities gt
Hang-gliding, other aviation/leisure activities
25Aeronautical - Civil
Two main impacts 1. Physical Safeguarding 2.
Technical Safeguarding Airports consulted on
wind turbine applications will usually object
where i) a turbine is visible to airport
radar ii) the turbine breaches airport protected
surfaces Often objections are reconsidered
if/when the developer provides information to
demonstrate that the safe operation of the
Airport will not be compromised.
26Aeronautical - Civil
Solutions Liase with statutory consultees at an
early stage Appropriate Layout and Design to
mitigate against possible impacts Commission any
necessary aeronautical assessment
work Investigate impact upon other
aeronautical interests
27(No Transcript)
28Aeronautical - Military
The Ministry of Defence (MOD) frequently objects
to wind energy proposals where there is
potential conflict with military aviation and
radar systems, particularly air defence radar
systems. Early consultation required (responses
typically take 12 weeks). RAF Leeming (Tornado
Main Operating Base and contains a UK Air
Defence Radar and Rapid Response Unit)
29Radio-Communication Link Impact
Invisible and often ignored as an issue
Often viewed as a soft constraint, however,
where turbine location options are limited
this can significantly impact upon a
scheme Comprehensive consultation is
crucial
30Radio-Communication Link Impact
Solutions Avoid locations close to
Telecommunication Masts Consult with Ofcom at an
early stage Commission any necessary link impact
assessment work
31Ecology
Brownfield sites less constrained in terms of
Ecological interests than rural wind farm
sites. Major issues can still be raised
particularly on those industrial sites situated
in riverside or coastal locations. Common
issues gt Birds gt Bats gt Great Crested
Newts gt Water Voles
32Ecology
Solutions Avoid locations immediately adjacent
to Ecological designations (i.e. Sites of
Special Scientific Interest, Ramsar sites
etc.) Consult with Natural England (formerly
English Nature), the RSPB and the Local Wildlife
Trust at an early stage Be prepared to undertake
some on-site bird/bat monitoring and factor this
into the project timetable
33Ecology
34(No Transcript)
35Visual Impact
A subjective and emotive issue Major issue on
Greenfield sites, not normally given as much
weight on industrial sites Solutions Avoid
visually sensitive locations Undertake a Visual
Assessment of the proposal in liaison with the
Local Planning Authority
36Other Planning Issues
- Archaeology
- TV Reception
- Red Herrings
- Ice throw
- Distraction to Drivers
- Low frequency noise - dB(C)
- Affect on property value
- Economics of wind energy
37Space available for development
Is there enough space on-site for a wind turbine?
- Things to consider
- Rotor Swept Area
- Topple Distance
- (from roads, railways, powerlines etc.)
- Sheltering/Turbulence
- Health and Safety
- Indicative dimensions
- gt 225kW turbine - 47m max tip height
- 13.5m rotor
radius - gt 2-3MW turbine - 125m max tip
height - 45m rotor
radius
38On-Site/Installation Constraints
- gt Access
- gt Ground Conditions
- gt Underground Services
- gt Grid Connection
- gt Health and Safety/Risk Assessment
- Solution
- Undertake the necessary assessments at the
earliest opportunity.
39Unpredictable factors
- Objections
- gt Residents
- gt Other Third Parties
- Local Planning Authority
- The Development Control Committee
Solution A comprehensive consultation and PR
process which involves the local community and
other relevant third parties and involve the
local planning authority in pre-application
discussions
40Micro-Generation
- Typically turbines lt 20kW
- 15kW 20kW Turbines up to 20m tip height
- Estimated 4 month lead in time
- Economics not particularly attractive
difficult to see how they can pay for themselves
without grant assistance
41225kW - sub 850kW Wind Turbines
- A good option on difficult sites
- Can be difficult to find a manufacturer
- Best option could be reconditioned machines
from re-powered sites in Europe - Turbine availability ( type of turbine
available) is extremely dynamic
42850kW - 3MW Wind Turbines
- An excellent investment on the right site
- Pay back period approximately 5 years
- Lengthy lead in times (worse case scenario 18
months)