Title: Everglades Agricultural Area Storage Reservoir A1 Basis of Design Report BODR
1Everglades Agricultural AreaStorage Reservoir
A-1Basis of Design Report (BODR)
- November 2005
- Shawn Waldeck, P.E.
- Acceler8 Project Manager
2Agenda
- CERP/Acceler8 overview
- Project purpose
- SFWMM (2 x 2 model)
- Project overview
- Test cell program
- Seepage
- Recreational opportunities
- Outreach/Stakeholder feedback
- Project assurances
3Comprehensive Everglades Restoration Plan (CERP)
Restoring the Everglades Flow Pattern
4Getting the Water Right
5Acceler8 Overview
EAA Reservoir A-1 (BODR stage)
6Project Purpose
- EAA Reservoir A-1 is an important part of the
Comprehensive Everglades Restoration Plan (CERP).
As part of CERP it will
- Allow SFWMD to better manage water to the
environment - Allow SFWMD to manage water deliveries to
agricultural community
7(No Transcript)
8Project Purpose
- Capture, store, and make use of EAA Basin runoff
and releases from Lake Okeechobee - Reduce Lake Okeechobee regulatory releases to the
estuaries - Restoration of Everglades hydropatterns
- Balancing inflow into STA-3/4
- Preserve existing agricultural water uses
- Incidental improvement in flood protection in EAA
A-1
9SFWMM (2 x 2 Model)
- SFWMM is a regional hydrologic simulation model
covering Lake Okeechobee, LOSA, EAA, Everglades,
LEC - SFWMM has been used by SFWMD to assess the
benefits of CERP - SFWMM establishes boundary flow for the detailed
water balance model - ECP 2006, 2010 and 2015
10(No Transcript)
11Overall Plan
Connector Canal
- 190,000 ac-ft of storage
- Seepage canals
- New pump station from North New River Canal
- Gated discharge structures
- STA-3/4 Supply Canal
Northeast Pump Station
North New River Canal
Gate Structure
Seepage Canal
EAA Reservoir A-1
Embankment
Internal Borrow Canal
From G-372 Pump Station
Gate Structures
G-370 Pump Station
G-383
STA-3/4 Supply Canal
12Reservoir Site Today
STA-3/4
13Reservoir Site Construction Completed 2009
EAA Reservoir A-1
STA-3/4
14Typical Embankment Cross-Section
EAA Reservoir A-1
Embankment
Seepage Canal
Caprock
Cutoff Wall
Internal Borrow Canal
Ft. Thompson Formation
Caloosahatchee Formation
15Operation
- Water Sources
- Agricultural runoff from North New River Canal
(NNRC) and Miami Canal drainage basins - Lake Okeechobee regulatory releases
- Direct precipitation
- Pump into reservoir during excess flow periods
- Release of water at the appropriate time to
- Environment
- Agriculture
16Average Annual Inflows (ac-ft)
17Average Annual Outflows (ac-ft)
18Stage Duration Curves for EAA Reservoir A-1
(Preferred Alternative)
19EAA Reservoir Operation During an Average Water
Year
October 1, 1991 to September 30, 1992
20Water for the Natural System
- Based on the water balance model
- Base year deliveries are based on flood control
- Annual delivery to Water Conservation Areas
ranges from 104,000 to 1,487,000 ac-ft over
36-year period of record - Average annual delivery is 685,000 ac-ft
- Improved wet year performance
- There will be more detailed quantification and
evaluation during the design stage for Project
Assurances - Preliminary modeling shows increased quantity and
availability of water
21Average Annual Environmental Deliveries met by
EAA A-1 during POS(No explicit delivery in base
year)
900
270
227
685
700
210
Mean Annual Volume (Kac-ft/yr)
500
150
Percentage Met
100
300
90
76
100
30
2010
2010
2015
Year
Year
22Water for Other Needs
- Based on the water balance model
- Annual delivery ranges from 18,900 to 160,000
ac-ft over 36-year period of simulation - Average annual delivery of 84,000 ac-ft for
agriculture with EAA reservoir - Dry year delivery is 74,450 ac-ft
- Improved dry year performance over base year
- Preliminary modeling shows improvement by
significant reduction in use restrictions - More detailed quantification and evaluation
during design stage for Project Assurances
23Average Annual Agricultural Deliveries met by EAA
A-1 during POS
2006 (Base Year)
180
138
140
100
90
Mean Annual Volume (Kac-ft/yr)
60
20
MC
NNRC
Met by Lake Okeechobee
24Average Annual Agricultural Deliveries met by EAA
A-1 during POS
2010
2010
180
90
140
70
129
Mean Annual Volume (Kac-ft/yr)
100
50
92
Percentage Met by reservoir
39
85
60
30
20
10
MC
NNRC
Met by Lake Okeechobee
Met by EAA Reservoir A-1
25Water Quality
- Category B not expected to cause or contribute
to WQ degradation - DMSTA2 Phosphorus concentration reduction of
17 - Test cell data to be developed in Acceler8
program - Detailed evaluation included in the PIR
26Embankment Design
27Freeboard Requirements
Design Pool Depth
Wind
Wave Run-up
Storm Surge
Waves Form
28(No Transcript)
29Design Storms
- High Hazard facility therefore stringent design
standards apply - 100-year wind with maximum rainfall
- 100-year adjusted wind 104 mph
- Maximum rainfall 54 inches in 3 days
- 500-year rainfall 20 inches in 3 days
- Category 5 hurricane
- Adjusted wind speed 122 mph
- 100-year rainfall 17 inches in 3 days
- Probable maximum wind
- 200 mph is PMW (gust)
- Adjusted wind speed 158 mph
- These follow design criteria developed jointly
by USACE, SFWMD, FDEP
30Test Cells
31Test Cell Program
- Obtain performance data
- Soil properties used for modeling seepage
- Total seepage from reservoir
- Seepage lost
- Evaluate material suitability for
- Embankment construction
- Rock processing
- Evaluate different construction procedures
- Develop cost effective techniques for handling on
site materials
32Test Cell 1
MAKE-UP
RE-CIRCULATE
33Test Cell 2
34Cap Rock
35Subsurface Conditions - Stratigraphy
36Seepage Model
- Developed using USGSs MODFLOW model
- 8 aquifer layers to 220 feet below ground
- Model covers area 32 miles by 23 miles
- Calibrated aquifer parameters to test cell data
- Model used to evaluate seepage, seepage
collection, and potential flows to surrounding
areas (farmlands, STAs, Holey Land)
37Areas Potentially Affected by Seepage
U.S. 27
Agricultural Area
Agricultural Area
NNRC
EAA Reservoir A1
Compartment B
Holey Land Wildlife Management Area
STA-3/4 Supply Canal
STA-3/4
38Typical Cross-Section
Network of Farm Canals
EAA Reservoir A-1
Caprock
Seepage Canal
Cutoff Wall
Ft. Thompson Formation
Caloosahatchee Formation
39Seepage Control Alternatives Considered
- Cutoff wall (34-feet deep) completely around
reservoir - Cutoff wall (34-feet deep) along farmland and
shorter cutoff wall along Holey Land WCA and
STA-3/4 - Deep pressure-relief wells along farmland
40Seepage Controls
41US 27 no effect
US 27
North New River Canal
Seepage Canal
Cutoff Wall
42Potential Recreational Opportunities
43Schedule for EAA Reservoir A-1
2006
2007
2008
2009
Design
Construction
44Cost Summary
45Outreach
- Job training benefits
- 1.5 billion construction program
- Removal of land from production/tax roles
- Jobs for local residents
- Training provided
- Training
- Heavy equipment
- Construction craft worker
46Outreach
- Business involvement benefits
- Emphasis on partnerships linking resources
- Construction symposiums and exhibitions
- Contract opportunity assistance
- Construction symposiums
- Large events primes, subs, support,
workforce and exhibitors - Smaller-scale events subs, small businesses
and support services
47Stakeholder Presentations
- Agricultural
- Environmental
- 298 Districts
- Belle Glade
- Pahokee
- South Bay
- Palm Beach Co
- Seminole Tribe
- FPL
- FDOT
48Issues Identified at Stakeholder Meetings
- A-1 Project Assurances
- PIR and BODR coordination
- Complete planning before construction
- Expand Schedule
- Base year vs. post reservoir condition
- Water quality
- Consider STAs in lieu of storage
- Health and safety of residents in Tri-Cities area
- Local business opportunities and jobs
- Mosquito control
- Maintain legal right to water supply
49Project Assurance Requirements
- WRDA 2000 and Florida Programmatic requirements
- Identify water for the natural system
- Identify water for other water-related needs
- Address any elimination or transfers of water
- Maintain existing level of flood protection
50Model Scenarios for Comparison
- Existing PIR Baseline - Current system
configuration with current allocated demands - Existing PIR Baseline with Project Current
system configuration plus EAA Reservoir with
current allocated demands - Natural System Targets - Restoration targets as
defined by RECOVER or mutually acceptable by
SFWMD, USACE, and Department of Interior
51Water Made Available By Project
- EAA Reservoir is expected to have system-wide
effects - System-wide quantification performed for three
conditions - Annual (water year from November - October)
- Dry Season (November - May)
- Wet Season (June - October)
52Water Made Available By Project
- Identify water made available by a project
- Water for the natural system
- Water for other water-related needs
- Compare model scenarios to Natural System Targets
- Existing PIR Baseline
- Existing PIR Baseline with Project
- Modeling tool SFWMM
53Elimination or Transfer of Water
- Identify any transfer of source that may occur
- Show that there are no adverse impacts from
project to existing legal users - Compare model scenarios
- Existing PIR Baseline
- Existing PIR Baseline with Project
- Modeling tool - SFWMM
54Maintaining Existing Levels of Flood Protection
- Determine if existing levels of service for flood
protection will be diminished outside geographic
area of the project - Show that there are no adverse impacts from
project - Compare model conditions
- Existing PIR Baseline
- Existing PIR Baseline with Project
- Modeling tool - Local scale modeling
55Elimination or Transfer of Water
- Based on modeled operation of EAA Reservoir A-1
- Increased quantity and timing of water for
protection of fish and wildlife - Improved timing of delivery of water for
agriculture - Water supply from the reservoir supplemented by
Lake Okeechobee - No impact to existing users
56Maintaining Existing Levels of Flood Protection
- Control seepage from EAA Reservoir A-1 away from
adjacent lands - Optimized EAA Reservoir A-1 operations includes
pump station, seepage canal and cutoff walls - Inherent improvements to regional flood protection
57Documentation of Project Assurances
- Documentation of Project Assurances for A8
Reservoir will be included in the Preliminary
Design Documents
58Goals and Objectives Met
- Improved quantity, quality and timingof releases
to environment - Flow equalization to STAs
- Some reduction of back pumping events
- Some reduction of Lake Okeechobee releases to
estuaries
- Regional water supply maintained
- Incidental flood control improvement
- Recreation opportunities