Pull Manufacturing Kanban, Just in Time, Demand Flow http:www'managementsupport'com

Description:

Toyota makes 3 car models - a convertible, hardtop, and an SUV. Assume that customers are buying nine convertibles, nine hardtops, and nine SUVs ... – PowerPoint PPT presentation

Number of Views:781
Avg rating:3.0/5.0
Slides: 7
Provided by: managemen7
Category:

less

Transcript and Presenter's Notes

Title: Pull Manufacturing Kanban, Just in Time, Demand Flow http:www'managementsupport'com


1
Pull ManufacturingKanban, Just in Time, Demand
Flow http//www.managementsupport.com
2
Outline
  • Why Pull Manufacturing?
  • The Problem of Inventory
  • Just In Time
  • Kanban
  • One Piece Flow
  • Demand / Pull
  • Standard Work Takt Time
  • Production Smoothing

3
JIT Tactics
  • Single Minute Exchange of Dies (SMED)
  • Statistical Process Control
  • Use of standard containers
  • Doable stable schedules with adequate visibility
  • TAKT-Time
  • 5-S Program
  • Kaizen Event
  • Visual control
  • Flexible workers
  • Tools at the point of need
  • Product redesign
  • Group Technology
  • Total Productive Maintenance

4
Kanban Production Control Systems
Production Kanban
Withdrawal Kanban
A
Machine Center
Assembly Line
B
Storage
....
5
TAKT Time Example
  • Net Available Operating Time
  • Time per shift 480 (minutes)
  • Breaks (2 _at_ 10) - 20
  • Clean-up - 20
  • Lunch - 30
  • NAOT/shift 410
  • Customer Requirements
  • Monthly 26,000 units/month
  • No. Working Days 20 days/month
  • CR/Day 1,300
    units/day
  • TAKT Time
  • 410 x 60 x 3 shifts (73,800) divided
    by 1,300
  • 57.769 seconds per part or 57"

6
Production Smoothing / Leveling
  • Averaging both the volume and the production
    sequence of different model types on a
    mixed-model production line
  • Example Toyota Manufacturing
  • Toyota makes 3 car models - a convertible,
    hardtop, and an SUV. Assume that customers are
    buying nine convertibles, nine hardtops, and nine
    SUVs each day. What is the most-efficient way to
    make those cars?