Title: Graduation Project 1 Strengthening of an existing reinforced concrete structure
1Graduation Project (1)Strengthening of an
existing reinforced concrete structure
United Arab Emirates University College of
Engineering Civil and Environmental Department
Instructor Dr. Ashraf Biddah
- Student Name ID No.
- Nabil Raweh Qahtan 980410066
- Mohammed Eisa Al-Harrasi 980710101
- Hazem Bakri Al-Naser 199901443
2Introduction
- Exclusive Summary
- The general idea of the project.
- Problems Facing reinforced concrete structures.
3Exclusive Summary
- The main achievements
- Studying the Strengthening Methods.
- Selection of an exiting building.
- Experimental Test.
- Beginning of Structural Analysis.
4The general idea of the project
- The owner of a residential building wanted to
convert his building to a commercial building. - According to change in the use of existing
structure, the structural system of the building
will be modified to fit the new changes. - PROBLEM The old building cannot carry the new
loads that come from the changes. - DESIGN BRIEF Design a strengthening system that
can increase the capacity of the existing
structural system to be able to carry the new
loads that come from the changes.
5Problems Facing Reinforced Concrete Structures
- Load increases.
- Damage to structural parts.
- Improvements in suitability for use.
- Modification of structural system.
- Errors in planning or construction.
-
6STRENGTHENING REINFORCED CONCRETE STRUCTURES BY
BONDING STEEL PLATES
- Strengthening is the process of adding capacity
to a member of structure. - Attachment of steel to concrete
- Adhesive connecting mechanism.
- Bolting connecting mechanism.
7Explanatory Sketch
Fig. 1 Techniques of plating reinforced concrete
beams.
8STRENGTHENING REINFORCED CONCRETE STRUCTURES BY
PRESTRESSING CABLES
- Post-tensioning is a technique used to prestress
reinforced concrete after concrete is placed. - The tensioning provides the member with an
immediate and active load-carrying capability.
9External Post-tensioned picture
10 The advantages of External Prestressing
- Ability to restress, destress and exchange any
external prestressing cable. - Crack free members.
- Reduce deflection.
- High fatigue and impact resistance.
11The Disadvantages of External Prestressing
- Usually requiring a greater section depth.
- More exposed to environmental influences (fire,
vandalism, aggressive chemicals etc.). - Handling of the tensioning devices may be more
difficult. - High cost.
12Concrete Jackets(Section Enlargement)
13Concrete Jackets (Section Enlargement)
- Enlargement is the placement of additional
concrete and reinforcing steel on an existing
structural member. - Beams, slabs, columns, and walls, if necessary,
can be enlarged to add stiffness or load-carrying
capacity.
14Concrete Jackets
- In most cases, the enlargement must be bonded to
the existing concrete to create a monolithic
member for additional shear or flexural capacity.
15Column Compressive strengthening by Section
Enlargement
- Enlarging the cross section of an existing column
will strengthen the column by increasing its load
carrying capacity. - A column can be enlarged in various
configurations. - The drying shrinkage effects in the concrete used
to enlarge the column must be considered.
16Section EnlargementMethod A
- In the illustration, Method A will accomplish
efficient load transfer if the new portion is
cast with a bond breaker between the new and old
concrete. - After most of the drying shrinkage has occurred,
the ties that link the old and new concrete can
be installed.
17Section EnlargementMethod A
- The gap between the new portion of the column and
the existing member (to be partially supported by
this column) can be filled with dry packing
material. - This will allow the new material to share its
portion of the load.
18Section EnlargementMethods B C
- When Methods B and C are used, extreme care
should be exercised to select concrete mix
designs with very low shrinkage rates. - Pre placed aggregate concrete generally offers
the lowest drying shrinkage it is, therefore, an
excellent material for column enlargements.
19Disadvantages of the concrete jackets
- Increasing the size of the element, which make
its usage very limited. - Difficult to construct in some active buildings
such as hospitals, schools because of the noise
of equipments. - Needs shuttering, formworks, reinforced steel,
concrete, concrete pumps, vibrators, etc.
20Fiber Reinforced Polymer
21Fiber Reinforced Polymer (FRP)
- FRP is a new class of composite material for the
development and repair of new and deteriorating
structures in Civil Engineering. - Search for alternatives to Steel and alloys to
combat the high costs of repair and maintenance
of structures damaged by corrosion and heavy use.
22FRP Laminate Structure
- FRPs are organized in a laminate structure.
- each lamina (flat layer) contains an arrangement
of unidirectional fibers fabrics embedded within
a thin layer of light polymer matrix material. - FRP consists of two main components
- Fibers.
- Resin or Matrix.
23FRP Laminate Structure
24Types of FRP
- The three main types of fibers used are
- Carbon.
- Glass.
- Aramid.
25Suitability of FRP for Uses in Structural
Engineering
- FRP properties and advantages makes it ideal for
wide spread applications in construction
worldwide. - FRP has a few disadvantages.
26Advantages of FRP
- Corrosion Resistance.
- Lightweight.
- Ease of installation.
- Less Finishing.
- Less maintenance.
- Ductility of FRP wrapped members improves
dramatically. - They are ideal for external application.
27Advantages of FRP
- They are extremely durable.
- They are available in various forms sheets,
plates, fabric, etc. - They are available in long lengths that
eliminates joints and splices. - They cure within 24 hours.
- Versatility.
- Anti-seismic behavior.
28Disadvantages of FRP
- High cost, susceptibility to deformation under
long-term loads - Temperature and moisture effects, lack of design
codes, and most importantly, lack of awareness.
29Decision
30Introduction
- M.S.Project gantt chart.
- Lab tests on FRP material.
- Cost estimation for G.P.1
31M.S. Project Gantt Chart
32M.S. Project Gantt Chart
33Experimental lab test on FRP material.
- The main objective of this experiment was to
study the effect of different environments on the
behavior of FRP material.
34Beams Details
- This experiment consists of 16 beams and 6 cubes.
- Beams were divided to 4 groups, each group
consists of 4 beams with four different
reinforcements. - Beams dimensions were 10cm x 10cm x 50cm.
- Minimum reinforcement of one bar with 6mm
diameter (1F6) was used.
35Groups Environment
- Each group was exposed to four different
environments as follows - Group 1
- Room temperature with 26oC.
- Group 2
- Hot water tank with 100 humidity at 45oC.
- Group 3
- Oven (0 humidity) at 45oC.
- Group 4
- Outside exposed to sun radiation and the
variation in temperature through the 24 hours.
36Equipments
- Digital balance.
- Molds of beams and cubes.
- Mixer.
- Vibrator.
- Hot water tank.
- Oven.
- Cube test machine.
- Beam test machine.
37Materials
- Concrete mix water, cement, sand, coarse and
small aggregates. - Plastic sheet.
- FRP strips.
- Strain gages.
38Procedures
- Steel reinforcements were prepared.
- Strain gages were fixed on the steel
reinforcement. - Concrete ingredients were calculated, weighted
and mixed using a big mixer. - Concrete was poured in the molds of beams and
cubes. - Concrete was vibrated and covered by plastic
sheet.
39Procedures
- 3 cubes were tested after 7 days.
- Concrete beams and cubes were removed from molds
and cured in potable water for 14 days. - Beams and cubes were exposed to air drying in
laboratory.
40Procedures
- FRP was applied with layer of epoxy.
- Beams were exposed to the different environments
for 1000 hours. - 3 cubes was tested after 28 days.
- All beams was tested after 1000 hours.
41Experimental Result
42Experimental Results
43Experimental Results
44Experimental Observations
- Effect of Fiber Reinforcement Polymer (FRP) on
strengthening the beams - One FRP strip increased the beam's capacity by
about 100 for all environments. - Two strips of FRP increased the beam's capacity
by about 200 for all environments. - All reinforced beams strengthen with FRP failed
on de-bonding of the FRP at the end of strips due
to the shear force at this location.
45Experimental Observations
- Environmental effect on the beams
- The effect of environment on reinforced concrete
beams with steel only is negligible. - Plain concrete with one strip of FRP (shear
force) was affected in hot environments (humid
and dry). Where the effect of outdoor and indoor
environments was negligible.
46Experimental Observations
- The reinforced concrete beams strengthen with
FRP (bond capacity between the FRP and the
concrete) was affected in hot and humid
environment. - Although the FRP in the outdoor environment was
subjected to the Ultra Violet during the 1000 hrs
exposure, no reduction in the beam capacity was
noticed.
47Cost Estimation
Total Cost 1496 Dhs (within the budget)
48Analysis background
- The most important and most difficult task faced
by the structural designer is the accurate
estimation of the loads that may be applied to
the structure during its life. - The next problem is to decide the worst possible
combinations of these loads that might occur at
one time.
49Analysis background
- The loads that will be used in this project are
dead and live loads. - Dead loads are loads of constant magnitude that
remain in one position. - Live loads are loads that can change in magnitude
and position.
50Analysis background
- ACI code (9.2) states that the required ultimate
load carrying ability of the member U provided to
resist the dead load D and the live load L must
at least equal - U 1.4D 1.7L
51Analysis background
- The Loads carried by the structure are
transferred from one structural element to
another until it reaches its final destination to
the supporting ground. - The loads that come from slabs to beams can be
estimated according to the slabs design system
and the geometry of these slabs.
52Analysis background
- In one direction slabs the beam is carrying half
of the slab as a rectangular or square shape. - In two way slabs the each beam around the slab is
carrying triangle or trapezoidal shape of the
slab.
53Prokon Structural Analysis Design
- Prokon structural analysis and design is a useful
tool for analysis and design of structures. - The PROKON suite has two main components
- PROKON Calcpad.
- PROKON analysis and design modules .
54Prokon Structural Analysis Design
55Prokon Structural Analysis Design
56Prokon Structural Analysis Design
57Prokon Structural Analysis Design
58Prokon Structural Analysis Design
59Prokon Structural Analysis Design
- Shear and Moment diagrams.
-
60Structural system of the building
- Area 750 m2.
- It consists of two stories.
- Types of slabs One way Hurdy slabs, two way
hurdy slabs and two way solid slabs. - Types of columns Rectangular and circular.
- There are projected beams and hidden beams.
61Structural system of the building
- The Floor cover 2 KN/m2.
- The Live load 2 KN/m2.
62 Hurdy slab load
- The unfactored loads calculation of the one way
Hurdy slabs.
63Comparison between hand Prokon results
64Comparison between hand results and Prokon results
65Conclusion
- It was learned some modern technologies in
strengthening concrete structures. - It was learned a new computer software program.
- The a knowledge that we gained from structural
analysis and design courses were applied.
66Conclusion
- From the experimental results, it was found that
the FRP was effected by 20 in the hot (0
humidity) environment. - It was decided to use FRP to strength the
building. - It was learned how to analyze one way Hurdy slabs
and beams.
67Thank Youfor Listening