2004 NJ Clean Energy Symposium Rowan University Interconnection with Conectiv Power Delivery - PowerPoint PPT Presentation

1 / 21
About This Presentation
Title:

2004 NJ Clean Energy Symposium Rowan University Interconnection with Conectiv Power Delivery

Description:

2004 NJ Clean Energy Symposium Rowan University Interconnection with Conectiv Power Delivery Russ Ehrlich Welcome Thank you for your attendance today What we want to ... – PowerPoint PPT presentation

Number of Views:21
Avg rating:3.0/5.0
Slides: 22
Provided by: usersRow5
Learn more at: http://users.rowan.edu
Category:

less

Transcript and Presenter's Notes

Title: 2004 NJ Clean Energy Symposium Rowan University Interconnection with Conectiv Power Delivery


1
2004 NJ Clean Energy SymposiumRowan
UniversityInterconnection with Conectiv Power
Delivery
  • Russ Ehrlich

2
Welcome
  • Thank you for your attendance today
  • What we want to achieve in 30 minutes or less.
  • Who we are, what we do, when, where and why?
  • Existing available tariff options
  • Interconnection Process
  • Overview of technical requirements for
    interconnection

3
Why is there a need for DG?
  • If utilities can supply power to customers why
    would customers want the option to run local
    generation?
  • Economics
  • Environment
  • Power Quality
  • Reliability

4
CPD NJ Tariff Options
  • RIDER NEM
  • Net Energy Metering
  • AVAILABILITY
  • This Rider is available to any Customer served
    under Company Rate Schedules RS, MGS-Secondary,
    and MGSPrimary who owns and operates an electric
    generation facility that
  • 1. Has a maximum capacity of 100 kilowatts,
    provided that the generation facility is sized no
    greater than the current peak electric needs of
    the customer's facility and
  • 2. Uses a wind or solar photovoltaic system and
  • 3. Is located on the Customers premises and
  • 4. Is interconnected and operated in parallel
    with the Companys transmission and/or
    distribution facilities
  • 5. Is intended primarily to offset all or part of
    the Customers own electricity requirements.
  • 6. Is not a Qualifying Facility (QF) served under
    Rate Schedule SPP, Small Power Purchase

5
Rider NEM
  • CONNECTION TO THE COMPANYS SYSTEM
  • Any Customer who elects this Rider must notify
    the Company, via submittal of a Conectiv Power
    Delivery New
  • Jersey Interconnection Application Form, at least
    30 days prior to activating the electric
    generation facility. The
  • electric generation facility shall not be
    connected to the Companys system unless it meets
    all applicable safety
  • and performance standards established by the
    National Electric Code, The Institute of
    Electrical and Electronics
  • Engineers (IEEE), Underwriters Laboratories, and
    as currently detailed in the Technical
    Considerations Covering
  • Parallel Operations of Customer Owned Generation
    of Less than One (1) Megawatt and Interconnected
    with the
  • Conectiv Power Delivery System in the State of
    New Jersey, dated July 11, 2001, and the
    applicable codes of the
  • local public authorities. Special attention
    should be given to IEEE Standard 929-2000
    Recommended Practice for
  • Utility Interface of Photovoltaic Systems. The
    Customer must obtain, at the Customers expense,
    all necessary
  • inspections and approvals required by the local
    public authorities before the electric generation
    facility is
  • connected to the Companys electric system.

6
Rider NEM
  • INTERCONNECTION AND PARALLEL OPERATION
  • Interconnection with the Companys system
    requires the installation of protective equipment
    which
  • provides safety for personnel, affords adequate
    protection against damage to the Companys system
    or to
  • the Customers property, and prevents any
    interference with the Companys supply of service
    to other
  • Customers. Such protective equipment shall be
    installed, owned and maintained by the Customer
    at the
  • Customers expense. The Customers equipment must
    be installed and configured so that parallel
  • operation must cease immediately and
    automatically during system outages or loss of
    the Companys
  • primary electric source. The Customer must also
    cease parallel operation upon notification by the
  • Company of a system emergency, abnormal
    condition, or in cases where such operation is
    determined to
  • be unsafe, interferes with the supply of service
    to other Customers, or interferes with the
    Companys
  • system maintenance or operation. Generation
    systems and equipment that comply with the
    standards
  • established in the previous Section of this Rider
    shall be deemed by the Company to have generally
  • complied with the requirements of this Section

7
Rate Schedule SPP
  • Small Power Purchase
  • Availability
  • Available to a "Qualifying Facility" (QF) as
    defined in Section 210 of the Public Utility
    Regulatory Policies Act of 1978 who also receives
    service under regular Company Rate Schedules RS,
    RS TOU-D, RS TOUE, MGS, AGS, or TS. The
    generation capacity of such facility must be less
    than 1000 kW.
  • Qualifying facilities with capacity greater than
    1000 kW must negotiate customer specific
    contracts.
  • These facilities are entitled to a contract at
    full avoided energy costs and, if eligible,
    capacity costs.
  • Customer specific contracts are subject to
    approval by the New Jersey Board of Public
    Utilities.

8
Rate Schedule SPP
  • SPECIAL PROVISIONS
  • 1. The customer must pay all interconnection
    charges before the Company will purchase electric
    power.
  • 2. A customer's installation must conform to
    Company specifications for Qualifying Facility
    interconnection as outlined in the Company's
    Technical Guidelines for Cogeneration and Small
    Power Producers.
  • 3. Qualifying Facilities with 10 kW or less
    generating capacity must sign an Electric
    Interconnection/Small Power Purchase Agreement.
  • 4. Purchases from a QF will receive a capacity
    credit when the capacity exceeds 100 kilowatts
    and that capacity meets certain reliability
    criteria. The Company will make capacity payments
    to the QF to the extent that the capacity of the
    QF reduces any capacity deficiency payments by
    the Company to PJM or increases any capacity
    payments to the Company from PJM. Capacity
    credits, if applicable, will be based on the
    average on-peak capacity in any billing month,
    such capacity to be defined as the on-peak
    kilowatt-hours divided by the on-peak hours in
    that month. The seller may be eligible for an
    additional credit where the presence of the QF
    allows the deferral of local transmission or
    distribution capacity cost.
  • 5. The Service Charge will be waived for QF's
    with 10 kW or less generating capacity.
  • 6. Due to simplified metering, QF's with 10 kW or
    less generating capacity will be credited based
    on the average non-load weighted PJM billing rate
    for the month the energy is received.

9
Technical Interconnection Issues
  • Compliance with Tariff rules and CPD regulations
  • Purpose of the requirements?
  • Technical requirements to promote safe reliable
    parallel operation.
  • Enhance the reliability of electric service
  • Facilitate implementation
  • Enhance economic efficiency
  • Help promote distributed resources
  • Who will use the technical considerations?
  • Below 1 MW
  • 34.5 kV below, non transmission.
  • Non inverter based technologies

10
Where do you start?
  • Contact CPD or other local distribution companies
    early in the process!
  • CPD Contact
  • Conectiv Power Delivery
  • PO Box 9239, Mail stop 79NC82
  • (302) 283 6097 Office
  • (302) 283 6090 Fax
  • Attn Russ Ehrlich
  • Or E-mail to Russ.Ehrlich_at_conectiv.com

11
Application Process
  • Interconnection Applications
  • Short Form 10 kW or Less
  • Available on BPUs Clean Energy Web site
  • Long Form System gt100 kW 1000kW
  • Contact Conectiv Power Delivery
  • 1 MW or Greater PJM/ Conectiv ISA
  • Submit partial application to begin process
  • After system is installed inspected submit
    completed application to CPD
  • Application review CPD departmental notification

12
CPD Internal Review
  • System Protection Review
  • Relaying, settings, technology
  • Pre-interconnection Study
  • Inverter based technologies exempt
  • System Planning
  • Power Delivery systems must be designed to handle
    peak circuit load without generation Grid
    reliability
  • Metering
  • Billing
  • System Operations

13
Technical Interconnection Issues
  • General Interconnection and Protection
    Requirements
  • The Generator Owners generation and
    interconnection installation must meet all
    applicable national, state, and local
    construction and safety codes.
  • The Generator Owners generator shall be equipped
    with protective hardware and software designed to
    prevent the generator from energizing one of the
    Companys de-energized circuits. The Generator
    Owners generator must automatically disconnect
    from the Companys system if the Grid source is
    lost, irrespective of connected loads or other
    generators.
  • The generator shall be equipped with the
    necessary protective hardware and software
    designed to prevent sustained parallel operation
    of the generating equipment with the Companys
    system unless the system service voltage and
    frequency are within acceptable magnitudes as
    defined in Section XIV.B.
  • Pre-approved equipment shall be accepted as part
    of an interconnection proposal without the need
    to re-review the equipment itself. However, the
    application, design and setting of pre-approved
    units and/or equipment must be reviewed and
    coordinated according to the unique needs of the
    specific location of the proposed installation.
    Where a complete unit or system has been
    pre-approved, only location-specific issues will
    typically need to be reviewed.

14
Technical Interconnection Issues
  • The Generator Owner will be responsible for
    protecting its own generating and interconnection
    equipment in such a manner so that Company system
    outages, short circuits, single phasing
    conditions or other disturbances including zero
    sequence currents and ferroresonant over-voltages
    do not damage the Generator Owners generating
    equipment. The protective equipment shall also
    prevent excessive or unnecessary tripping that
    would adversely affect the Companys service
    reliability to other Generator Owners and
    Customers.
  • The Generator and interface protection schemes
    shall be continuously monitored and functioning
    and the generator shall immediately disconnect
    from the Companys system for any condition that
    would make the protection scheme inoperable.
  • The operating power required for the protection
    and control schemes for the generator and the
    control power used to disconnect the generator
    from the Company must not be dependent on local
    Company grid power.
  • Where multiple generators are connected to the
    system through a single point of common coupling,
    the sum of the ratings of the generators will be
    used to determine the applicability of these
    guidelines. Protection scheme performance with
    one or more units off line will have to be
    considered .
  • Applicable circuit breakers or other interrupting
    devices at the Generator Owners facility must be
    capable of interrupting the maximum available
    fault current at the site, including any
    contribution from the Owners generator(s).

15
Technical Interconnection Issues
  • The Generator Owner will furnish and install a
    manual disconnect device which, when opened, will
    have the affect of isolating the generator from
    the Companys system. This disconnect device
    shall have a visual break (a disconnect switch, a
    draw-out breaker, fuse block, etc. as appropriate
    to the voltage level), will, at all times, be
    accessible to Companys personnel, and shall be
    capable of being locked in the open position via
    a Company padlock. The Company shall use
    reasonable efforts to utilize padlocks of a size
    consistent with typical manufacturers
    specifications. The Generator Owner shall follow
    the Companys switching, clearance and tagging
    procedures which the Company shall provide and
    attached the Warning Label noted in Section X.
  • On generation installations of 25kW or less, the
    Generator Owner may elect not to install a manual
    disconnect switch provided that the meter can be
    safely pulled by Conectiv to isolate the
    generation equipment from the Company. If the
    Generator Owner elects not to install a manual
    disconnect device, the Generator Owner assumes
    all risks and consequences when a meter must be
    pulled to disconnect the generator thereby also
    interrupting electric service to the Customer.
  • The design, procurement, installation, and
    maintenance of the equipment at the Generator
    Owners site is the responsibility of the
    Generator Owner and at the Generator Owners
    expense.
  • Any necessary enhancements or improvements needed
    within the Companys system and/or at other
    Customer sites to accommodate the parallel
    interconnection of the Generator Owners
    generation will be at the Generator Owners
    expense.

16
Technical Interconnection Issues
  • The Generator Owner has full responsibility and
    liability for the safe and proper operation and
    control of their equipment and the power
    originating from their generator. The Generator
    Owner is also responsible for synchronizing their
    generator(s) with the Companys system and
    maintaining a synchronous condition.
  • The Generator Owner must immediately cease
    parallel operation upon notification by the
    Company if such operation is determined to be
    unsafe, interferes with the supply of service to
    other customers, or interferes with the Companys
    system maintenance or operation.
  • The Company reserves the right to specify the
    type of transformer connection (e.g.
    delta-delta, wye-delta, wye-wye) that will be
    employed for all multiphase interface
    transformers consistent, where reasonable, with
    the Generator Owners power system.

17
Technical Overview
  • Application processing CPD wants to get your
    system up and running so you can maximize the
    return on your investment!
  • Ensure - IEEE/UL/NEC Requirements
  • Customer Utility system protection
  • Customer Utility safety!

18
Facts Figures
  • CPD has approximately 1.1 Million customers
  • 75 CPD customers have installed Renewable systems
    that are operating in parallel with our system.
  • Largest system 200kW Solar system
  • Smallest system 1.8kW Solar System
  • 10kW wind system _at_ Govt. facility
  • Total Renewable Generation - Approximately 500 kW

19
In Closing.
  • Type of Generation.(renewable fuels)
  • Size of Generation..(residential up to mWs)
  • How is the unit operated..(Connected or isolated
    from the grid/Emergency/Parallel)

20
Last but not least..
  • Conectiv Power Delivery supports alternative
    energy generation projects will help customers
    work through the interconnection process.
  • Contact Conectiv Power Delivery early
  • Fill out necessary interconnection application(s)
  • Build safety reliability into the system

21
Thanks Again!
Write a Comment
User Comments (0)
About PowerShow.com