Is it all necessary? Who benefits? Provision for Multi-tier Dispute Resolution in International Construction Contracts - PowerPoint PPT Presentation

About This Presentation
Title:

Is it all necessary? Who benefits? Provision for Multi-tier Dispute Resolution in International Construction Contracts

Description:

Arbitration. 1996 Supplement to the 4th Edition of the Red Book 1997 Supplement to the 3rd Edition of the Yellow Book introduced similar model for Clause 50. – PowerPoint PPT presentation

Number of Views:121
Avg rating:3.0/5.0

less

Transcript and Presenter's Notes

Title: Is it all necessary? Who benefits? Provision for Multi-tier Dispute Resolution in International Construction Contracts


1
Is it all necessary? Who benefits?Provision for
Multi-tier Dispute Resolution in International
Construction Contracts
  • Society of Construction Law
  • Society of Construction Arbitrators
  • Tuesday 1 July 2008

Ellis Baker MA LL.M (Cantab). Head of
Construction and Engineering Practice Group White
Case LLP, London.
2
A. How it was the early FIDIC Contracts
  • FIDIC Red Book 1st Edition 1957 Clause 66
    Settlement of disputes.
  • 2 elements
  • Engineers decision
  • Aribitration.

3
How it was the early FIDIC contracts
  • FIDIC Red Book 1st Edition 1957 Clause 66
    Settlement of disputes
  • First element
  • Engineers decision
  • If any dispute or difference of any kind
    whatsoever shall arise between the Employer or
    the Engineer and the Contractor in connection
    with or arising out of the Contract or the
    carrying out of the Works it shall be referred
    to and settled by the Engineer
  • Such decision in respect of every matter so
    referred shall be final and binding upon the
    Employer and the Contractor until the completion
    of the work

4
How it was the early FIDIC contracts
  • FIDIC Red Book 1st Edition 1957 Clause 66
    Settlement of disputes
  • Second element
  • Arbitration.
  • either the Employer or the Contractor may
    within 90 days after receiving notice of such
    decision require that the matter shall be
    referred to an arbitrator
  • The award of the arbitrator shall be final and
    binding on the parties.

5
How it was the early FIDIC contracts
  • FIDIC Red Book 2nd edition 1969
  • 3rd edition 1977
  • Clause 67 maintains 2 element approach.

6
How it was the early FIDIC Contracts
  • The arbitration element changes
  • Clause 66 1st edition Red Book
  • such reference shall be deemed to be a
    submission to arbitration within the meaning of
    the Arbitration Laws of the country to the Law
    of which the Contract is subject.
  • Clause 67 2nd and 3rd edition Red Book
  • All disputes or differences in respect of which
    the decision (if any) of the Engineer has not
    become final and binding as aforesaid shall be
    finally settled under the Rules of Conciliation
    and Arbitration of the International Chamber of
    Commerce by one or more arbitrators appointed in
    accordance with the said Rules.

7
How it was the early FIDIC Contracts
  • How the early FIDIC contracts worked Clauses
    66/67
  • Engineers decision (first element)
  • All disputes or differences referred to Engineer
    (condition precedent).
  • Engineers decision due within 90 days.
  • Engineers decision final and binding pro tem,
    subject to arbitration.
  • Arbitration (second element)
  • Reference to arbitration by Employer or
    Contractor to be made within 90 days of decision,
    failing which it became final and binding
    absolutely.
  • If no decision received from Engineer within 90
    days, parties had further 90 days to refer to
    arbitration.
  • References to arbitration finally settled (under
    ICC Rules 2nd and 3rd Edition) by one or more
    arbitrator appointed under the Rules.

8
Changes on the way the late 80s and early 90s
  • FIDIC Red Book 4th edition 1987 (1988 reprint)
  • Clause 67
  • While the stages of engineers decision and
    reference to arbitration were recognisably the
    same, Clause 67 had been significantly revised.
  • The 4th Edition introduces fundamental changes
    to the disputes procedure.
  • (Edward Corbett FIDIC 4th A Practical Legal
    Guide, 1991).

9
Changes on the way the late 80s and early 90s
  • FIDIC Red Book 4th edition 1987 (1988 reprint)
  • Clause 67 amendments.
  • Both reference to Engineer of dispute and
    Engineers decision shall state that it is made
    pursuant to this Clause (to remove doubts as to
    whether other communications were references or
    decisions).
  • Time limits for Engineers decision and reference
    to arbitration reduced from 90 days to 84 days.

10
Changes on the way the late 80s and early 90s
  • FIDIC Red Book 4th edition 1987 (1988 reprint)
  • Clause 67 amendments
  • Major innovation
  • Introduction of Amicable Settlement stage
  • Sub-clause 67.2.

11
Changes on the way the late 80s and early 90s
  • FIDIC Red Book 4th edition 1987 (1988 reprint)
  • Sub-Clause 67.2
  • Amicable Settlement
  • Where notice of intention to commence arbitration
    as to a dispute has been given in accordance with
    Sub-Clause 67.1, the parties shall attempt to
    settle such dispute amicably before the
    commencement of arbitration. Provided that,
    unless the parties otherwise agree, arbitration
    may be commenced on or after the fifty-sixth day
    after the day on which notice of intention to
    commence arbitration of such dispute was given,
    even if no attempt at amicable settlement thereof
    has been made.

12
Changes on the way the late 80s and early 90s
  • FIDIC Red Book 4th edition 1987 (1988 reprint)
  • How the procedure worked
  • Reference to Engineer (84 days).
  • Reference to Arbitration (70 days).
  • Arbitration not to be commenced until Amicable
    Settlement attempted (or 56 days in default).
  • ICC arbitration.

13
Changes on the way the late 1980s and early 90s
  • FIDIC Amicable Settlement
  • Note that an early attempt to introduce amicable
    settlement (and expert determination) in the
    FIDIC Yellow Book 2nd edition was regarded as
    unsuccessful at the time of the 3rd edition
  • The provisions in the Second Edition of the EM
    Conditions enabling the parties to refer
    matters to an expert have been removed as have
    the specific requirements for the parties to
    attempt amicable settlement. It was considered
    that this last provision was of little use since
    it merely enabled a party who had no wish to
    settle matters amicably to delay the
    commencement of arbitration
  • Dan Graham, International Construction Law Review
    1987.

14
Changes on the way - the late 80s and early 90s
  • Not all FIDIC contracts changed at the same time.
  • FIDIC Yellow Book Conditions of Contract for
    Electrical and Mechanical Works 3rd edition 1988.
  • Clause 50.1
  • If either party is dissatisfied with a decision
    or instruction of the Engineer as confirmed,
    reversed or varied in accordance with Clause 2 he
    may refer the matter to arbitration pursuant to
    Sub-Clause 50.2.
  • Unless the dissatisfied party has notified the
    other party and the Engineer within 56 days of
    such decision or instruction of his intention to
    refer the matter to arbitration, he shall be
    deemed to have accepted the decision as final.
  • Reference to arbitration shall not relieve the
    Contractor of his obligation to proceed with the
    Works in accordance with the Engineers decision
    or instruction, nor relieve the Employer of any
    of his obligations under the Contract.
  • The Contractor shall in any such arbitration be
    at liberty to rely on reasons additional to the
    reasons stated in the notice given under
    Sub-Clause 2.7.

15
Changes on the way the late 80s and early 90s
  • FIDIC Yellow Book 3rd edition 1988
  • Clause 50.2
  • If at any time any question, dispute or
    difference shall arise between the Employer and
    the Contractor in connection with or arising out
    of the Contract or the carrying out of the Works
    either party shall be entitled to refer the
    matter to be finally settled by arbitration in
    accordance with the Rules of Conciliation and
    Arbitration of the International Chamber of
    Commerce by one or more arbitrators appointed in
    accordance with those Rules, or by arbitration in
    accordance with such other rules as are specified
    in Part II.
  • The Arbitrator(s) shall have full power to open
    up, review and revise
  • (a) any decision or instruction of the Engineer
    referred to arbitration pursuant to
    Sub-Clause 50.1, and
  • (b) any certificate of the Engineer related to
    the dispute.

16
Changes on the way the late 80s and early 90s
  • FIDIC Yellow Book 3rd edition 1988
  • Clause 50.4
  • Formal notice of arbitration must be given to the
    other party, and where required to the
    appropriate arbitration body, no later than
    84 days after the issue of the Final Certificate
    of Payment.

17
Changes on the way the late 80s and early 90s
  • So in 1988 FIDIC forms offered different dispute
    resolution models.

18
New models of dispute resolution in the 1990s
  • Mega-projects the Channel Tunnel
  • Clause 67 Settlement of disputes.
  • Any dispute or difference should
  • in the first place be referred in writing to and
    be settled by a Panel of three persons (acting as
    independent experts but not as arbitrators).
  • Provided the decision is unanimous Such
    unanimous decision shall be final and binding
    upon the Contractor and the Employer unless the
    dispute or difference has been referred to
    arbitration.
  • All disputes or differences shall be finally
    settled under the Rules of Conciliation and
    Arbitration of the International Chamber of
    Commerce by three arbitrators appointed under
    such Rules.

19
New models of dispute resolution in the 1990s
  • Mega-projects the Channel Tunnel
  • The Channel Tunnel Group v Balfour Beatty 1992
    56 BLR 1 Court of Appeal Neill LJ
  • Evans J held that a stay should be refused
    because the time for arbitration had not arrived
    there has not yet been a decision by, or even a
    reference to, the panel under clause 67(1).
  • Many types of contract provide for some
    preliminary step to be taken before there is an
    arbitration I cannot see that this entitles a
    party to disregard the arbitration procedure
    altogether and start an action at law, merely
    because the preliminary step has not been taken.

20
New models of dispute resoltuion in the 1990s
  • Mega-projects the Channel Tunnel
  • Channel Tunnel Group v Balfour Beatty 1993 BLR
    22 House of Lords
  • Those who make agreements for the resolution of
    disputes must show good reasons for departing
    from them having promised to take their
    complaints to the experts and if necessary to the
    arbitrators, that is where the appellants should
    go. The fact that the appellants now find their
    chosen method too slow to suit their purpose is
    to my way of thinking quite beside the point.
  • (per Lord Mustill).

21
New models of dispute resolution in the 1990s
  • Mega-projects Hong Kong International Airport
    1992
  • Mass Transit Rail Corporation HK Government
  • Airport Core Programme
  • Building Works/Engineering works
  • 3-tier Structure 4-tier Structure
  • Decision of engineer Decision of
    architect/engineer
  • Mediation (condition precedent) Mediation
  • Arbitration Adjudication
  • Arbitration

22
New models of dispute resolution in the 1990s
  • Mega-Projects Hong Kong International Airport
    1992
  • Provisional Airport Authority Contracts
  • 4-tier Structure
  • Decision of engineer
  • Appeal to Project Director
  • Reference to Dispute Review Board (DRB)
  • Arbitration

23
New models of dispute resolution in the 1990s
  • Beyond FIDIC the ENAA Model Form
  • Engineering Advancement Association of Japan
    Model Form
  • International Contract for Power Plant
    Construction 1996
  • Clause 6.1(a) If any dispute or difference of
    any kind whatsoever shall arise between the Owner
    and the Contractor the parties shall seeks to
    resolve any such dispute or difference by mutual
    consultation.

24
New model of dispute resolution in the 1990s
  • Beyond FIDIC the ENAA Model Form 1996
  • Clause 6.1(b)
  • If the parties fail to solve such dispute or
    difference by mutual consultation, then either
    party may give to the other party a notice that a
    dispute or difference exists, specifying its
    nature, the point(s) in issue and its intention
    to refer the dispute to arbitration. If the
    parties fail to resolve such dispute or
    difference by further consultation within a
    period of thirty (30) days from the date upon
    which such notice of dispute has been given, the
    dispute or difference shall be referred to and
    finally settled by arbitration under the Rules of
    Conciliation and Arbitration of the International
    Chamber of Commerce (ICC) or any other rules as
    may be agreed.

25
New models of dispute resolution in the 1990s
  • Beyond FIDIC the ENAA Model Form
  • Clause 6.2 Notwithstanding the provisions of
    Clause 6.1 (Arbitration) above save insofar as
    they relate to mutual consultation, either party
    may give a notice to the other of its desire to
    refer to an Expert any dispute or difference.
  • if either party is not satisfied with a
    decision by the Expert as provided in the
    preceding paragraph such dispute or difference
    may be referred to and finally settled by
    arbitration.

26
Developments in SE Asia
  • Hong Kong SAR Private Edition 2006
  • 41.1 (b) Each party shall designate one of its
    own senior executives as its representative
    and the Designated Representatives shall
    endeavour to settle disputes that arise during
    the carrying out of the Works.
  • (c) The Designated Representatives shall have
    the authority to settle disputes and shall not
    be involved in the day to day administration
    of the Contract.
  • 41.2 If a dispute arises under or in connection
    with the Contract, the Architect shall, at the
    request of either party, immediately refer the
    dispute to the Designated Representatives.

27
Developments in SE Asia
  • Hong Kong SAR Private Edition 2006
  • 41.3 If the dispute is not resolved by the
    Designated Representatives within 28 days
    either party may refer the dispute to
    mediation.
  • 41.4 If the dispute is not settled by mediation
    within 28 days either party may refer the
    dispute to arbitration.

28
Developments in SE Asia
  • Singapore Institute of Architects (S/A)Lump Sum
    Edition 2005
  • (Malaysia PAM Clauses 34 and 35 are in similar
    words).
  • Clause 37.1 Any dispute between the Employer and
    the Contractor shall be referred to the
    arbitration and final decision of a person to be
    agreed by the parties

29
Developments in SE Asia
  • SIA Clause 38
  • Notwithstanding Clause 37(1), of the Conditions,
  • upon the agreement of both the Employer and the
    Contractor, the Parties may refer their dispute
    for mediation under the Mediation Rules of the
    SIA.
  • For the avoidance of doubt, prior reference of
    the dispute to mediation under this clause shall
    not be a condition precedent for its reference
    to arbitration by either the Contractor or the
    Employer.

30
The modern international construction and
engineering forms
  • FIDIC Dispute Boards
  • FIDIC Orange Book 1995. Clause 20.
  • 3 tier structure
  • Dispute between Employer and Contractor referred
    to Dispute Adjudication Board (DAB).
  • DAB decision final and binding unless a party
    dissatisfied.
  • Amicable settlement.
  • Arbitration.
  • 1996 Supplement to the 4th Edition of the Red
    Book
  • 1997 Supplement to the 3rd Edition of the Yellow
    Book introduced similar model for Clause 50.

31
The modern international construction and
engineering forms
  • FIDIC Dispute Boards.
  • The FIDIC Rainbow Suite 1999 developed the model.
  • Clause 20 Red Book, Yellow Book, Silver Book
  • 3 tier structure
  • Dispute Adjudication Board
  • Amicable Settlement
  • Arbitration

32
The modern international construction and
engineering forms
  • FIDIC Rainbow Suite Gold Book
  • Conditions of Contract for Design Build and
    Operate Projects introduces
  • 20.4 Avoidance of disputes.
  • If at any time the Parties so agree, they may
    jointly refer a matter to the DAB in writing with
    a request to provide assistance and/or informally
    discuss and attempt to resolve any disagreement
  • The Parties are not bound to act upon any advice
    given during such informal meetings and the DAB
    shall not be bound in any future Dispute
    Resolution process and decision by any views
    given during the informal assistance process

33
The modern international construction and
engineering forms
  • Institution of Chemical Engineers I Chem E
    International Edition 2007.
  • Red, Green, Burgundy Books.
  • Clause 44 Disputes
  • 44.1 The Purchaser and the Contractor shall
    endeavour to avoid the escalation of problems
    into disputes as defined in sub-clause 44.4 and
    to avoid disputes both between themselves and
    with third parties including sub-contractors.

34
The modern international construction and
engineering forms
  • I Chem E International Editions 2007
  • Clause 44 Disputes.
  • 44.4 No matter shall constitute or give rise to
    a dispute unless it has been referred to the
    Project Manager
  • 44.6 The parties shall attempt in good faith to
    negotiate a settlement of any dispute or
    difference
  • 44.7 If a dispute cannot be resolved by
    negotiation the parties may by agreement refer
    it to mediation
  • 45.1 Any dispute which has not been settled
    shall be referred to and finally resolved by
    arbitration.

35
The modern international construction and
engineering forms
  • I Chem E International Editions 2007
  • Options Dispute Review Board (DRB)
  • Clause 46 Any decision issued by the DRB shall be
    binding but not final and the dispute shall be
    resolved by agreement or by reference to an
    Expert or to arbitration.
  • Clause 47 Reference to an Expert.
  • Once referred to an Expert, dispute ceases to
    be referable to arbitration.
  • Findings are final, conclusive and binding.

36
Comment and analysis
  • So, does multi-tier dispute resolution benefit
    the parties if so what are the respective
    advantages and disadvantages of the respective
    models?

37
How it was the early FIDIC Contracts
  • Key-features of early FIDIC Contract Clause 66/67
  • Simplicity - 2 stage procedure
  • Engineer (a condition precedent)
  • Arbitration.
  • Finality - Engineers decision binding pro tem
  • and after 90 days absolutely.
  • Arbitration tribunals decision final.

38
Comment and analysis
  • Mega-projects Hong Kong Airport Airport
    Authority Contracts.
  • there were few referrals. The DRB made six
    binding decisions, with only one case being taken
    to arbitration. The relatively low number of
    referrals suggests that the existence of the DRB
    deferred the referral of disputes and it may be
    that it encouraged the settlement of matters
    between the parties without further recourse to
    third party intervention.
  • Keith Brandt
  • Chartered Institute of Arbitrators Conference,
  • Hong Kong 2002.

39
Comment and analysis
  • Mega-projects Hong Kong Airport

40
Comment and analysis
  • FIDIC Amicable Dispute Settlement
  • The addition of a new Clause 67.2 requiring an
    attempt at Amicable Settlement could also have
    important consequences for the avoidance of
    lengthy legal disputes A Construction Contract
    can generate large quantities of correspondence,
    numerous minor disputes and strong feelings
    between the people concerned. A further
    opportunity to review and discuss their
    differences, probably at Head Office rather than
    site level, may well encourage the parties to
    settle their mutual claims and avoid the
    considerable costs of an Arbitration.
  • Brian Totterdill, Engineer
  • International Construction Law Review 1987

41
Comment and analysis
  • FIDIC Amicable Settlement
  • Sub-Clause 20.5
  • Despite the criticisms that have been levelled
    at Sub-Clause 20.5 (amicable settlement of
    disputes) it can provide a valuable opportunity
    for the parties to arrive at a negotiated
    resolution of the dispute before proceeding to a
    costly formal determination through arbitration.
  • Dale Bracken
  • International Construction Law Review 2006

42
Comment and analysis
  • FIDIC Amicable Settlement
  • The FIDIC provision for amicable settlement may
    be seen as strong encouragement to get on with
    resolving the dispute, or at least with settling
    some of the issues involved, well in advance of
    any arbitration hearing
  • The FIDIC provision in Sub-Clause 67.2 is however
    very general, and leaves to the parties the need
    to select a procedure and cost sharing basis.
    Unfortunately, the parties may need to spend
    most of the limited time available in discussing
    what they should do, rather than getting on with
    it.
  • David Hollands, Engineer, New Zealand
  • International Construction Law Review 1989

43
Comment and analysis
  • Dispute Boards
  • Dispute Review Boards.
  • A DRB has certain psychological advantages over
    formal adversarial dispute resolution e.g.
    early venting of opinions and emotions before
    impartial experts, thus defusing personal
    antagonisms at an early stage and not allowing
    them to fester a conciliatory atmosphere
    producing Recommendations that are not compulsory
    (but can be ignored only at considerable risk)
    quick resolution of disputes so that the parties
    put the disagreement(s) behind them promptly and
    retain focus on the principal goal of both
    parties the successful completion of the
    project.
  • The Dispute Review Board system does work!
  • Gordon Jaynes
  • International Construction Law Review, 1993

44
Comment and analysis
  • Dispute Boards
  • the DRB procedure is now very popular in
    large-scale infrastructure projects, two very
    high profile examples of its use being on the
    Channel Tunnel and Hong Kong Airport projects
  • The DRB is set up at the beginning of the
    project, and through regular site visits, is
    involved from day one in the project. It
    therefore becomes an inherent part of the
    project, and thus will be in a very good position
    to assist in the speedy resolution of disputes as
    and when they arise.
  • Rohan Shorland, Journal of the CharteredInstitute
    of Arbitrators 1999.

45
Comment and analysis
  • Dispute Boards
  • they are in fact better than arbitration. Not
    only do they work well, but they indeed work
    faster, cheaper and in a much less contentious
    manner than arbitration tribunals.
  • Alexis Mourre, InternationalConstruction Law
    Review 2006.

46
Comment and analysis
  • Dispute Boards
  • DRBs are perceived as comparing favourably with
    both ad hoc mediation and the UK statutory
    adjudication scheme.
  • Keith Brandt, Solicitor, Hong KongChartered
    Institute of ArbitratorsConference, Hong Kong
    2002.

47
Comment and analysis
  • Dispute Boards
  • Examples of use cited by Brandt.
  • Channel Tunnel UKChannel Tunnel Rail Link
    UKVasco da Gama Bridge over Tagus
    PortugalAthens Mass Rapid Transit GreeceLHDA
    Dam and Transfer Gallery LesothoMaeslant Water
    Barrier NetherlandsExtran Hydro Development
    PRCXiaolangdi Multipurpose Project PRCLongtan
    Hydro Development PRC.

48
Comment and analysis
  • Dispute Boards Advantages
  • Legitimacy in choice by parties.
  • Regular visits give in-depth understanding of
    project.
  • DRB involved early, when memories and events
    fresh.
  • No opportunity for ambush as in adjudication.
  • Technical expertise of DRB personnel.
  • No obligation to produce compromise.
  • Non-binding nature of DRB decisions a virtue,
    less impression of winner/loser.
  • DRB inhibits unmeritorious claims.
  • Keith Brandt, Hong Kong 2002.

49
Comment and analysis
  • Dispute Boards Why dispute boards succeed
  • Regular site meetings deal with complaints
    early.
  • Gives all parties a chance to have a say.
  • Parties on site unite against DRB members as
    outsiders.
  • Most DRB members are non-lawyers and more
    user-friendly.
  • Experience shows that dispute boards are
    successful, that is, they deal with and finally
    dispose of virtually all the disputes that come
    before them. Broadly it seems that something in
    the order of 97 of disputes referred to a
    dispute board will not go beyond that procedure
    into arbitration or litigation.
  • Dr Robert Gaitskell QCICC Conference, London 2004

50
Comment and analysis
  • Dispute Boards Disadvantages
  • Cost warranted only on larger projects.
  • Cost disproportionate to benefit on all but
    largest projects.
  • Cost Adjudication and mediation are cheaper.
  • Keith Brandt Hong Kong 2002

51
Comment and analysis
  • Dispute Boards Costs
  • DB will generally cost in the order of 0.2 of
    project costs.
  • Dr R. Gaitskell, ICC Conference 2004.

52
Comment and analysis
  • Dispute Boards
  • 1995 World Bank makes DBs mandatory for all IBRD
    financed projects over US 50 million.
  • 1997 Asian Development Bank
  • European Bank for Reconstruction and Development
    follow suit.

53
Comment and analysis
  • Dispute Boards
  • ICC 3 types of Board 2004
  • DRB Recommendations.
  • DAB Decisions.
  • DB Hybrid issues recommendations unless
    decisions requested.

54
Comment and analysis
  • Dispute Boards compared with Dispute Resolution
    Adviser
  • Unlike most forms of dispute resolution where a
    third party neutral or tribunal is appointed once
    a dispute has arisen, the DRA is appointed at the
    commencement of a project, generally well before
    any disagreements have come to a head, thereby
    promoting dispute avoidance the most
    significant attribute of the DRA system is
    perhaps its ability to prevent disputes from
    arising.
  • Andrzej Cierpicki, Asian Dispute Review 2008

55
Comment and analysis
  • Dispute Resolution Adviser
  • DRA used on 60 projects since 1995
  • HK Govt Architectural Services Department study
  • Average cost savings with DRA 2.2
  • Average cost savings with other provision 1.7
  • Increase in duration of project through EoT
  • with DRA 7.2
  • with other provision 15.7

56
Comment and analysis
  • Med-Arb
  • Glencot Development and Design Co v Ben Barrett
    Son (Contractors) Ltd. 2001 80 ConLR 14
  • A mediator will or may have to listen to
    arguments and hear things which may be completely
    irrelevant to the dispute in the adjudication but
    which might be prejudicial to its determination.
  • Mr Talbot was correct in making it clear to
    parties that what he might be doing was a
    departure from adjudication and in getting their
    agreement to it. Such agreement was essential.
    Of course an agreement in advance, even if a
    formal written agreement, may not be effective in
    depriving a party of its right to question a
    later decision on the grounds of apparent or
    actual bias.
  • (per HH Judge Humphrey Lloyd QC.)

57
Comment and analysis
  • Looking forward LONDON 2012
  • Olympic Delivery Authority
  • Independent Dispute Avoidance Panel (IDAP)
  • Chair Dr Martin Barnes
  • 10 construction professionals
  • Adjudication Panel decides disputes not avoided
    by IDAP
  • Chair Peter Chapman
  • 11 adjudicators

58
Conclusions
  • Is what all necessary?
  • The parties should have an opportunity to achieve
    settlement.
  • Amicable Settlement or Mediation or Non-binding
    DRB.

59
Conclusions
  • Does the additional layer of a DB assist in
    avoidance of disputes?
  • Doubtful periodic visits may not be enough to
    ensure genuine familiarity with parties or
    project.
  • A worthwhile alternative for consideration
  • The DRA offers real engagement with parties and
    project and its capacity for dispute avoidance
    merits further study.

60
Who benefits?
  • Of course, the DR community benefits in one sense
    from multiple tiers of professional involvement.
  • But multi-tier dispute resolution is only
    sustainable if it benefits the stake-holders, the
    parties.

61
Conclusions
  • So, is it all necessary?
  • One large international projects it is necessary
    to provide sophisticated mechanisms to try to
    prevent disputes from going to arbitration.
  • Mechanisms capable of doing this are necessary.
    If the mechanisms and the professionals who
    operate them deliver that, the stake-holders are
    the real beneficiaries.

62
Worldwide. For Our Clients.
www.whitecase.com
White Case, a New York State registered limited
liability partnership, is engaged in the practice
of law directly and through entities compliant
with regulations regarding the practice of law in
the countries and jurisdictions in which we have
offices.
Write a Comment
User Comments (0)
About PowerShow.com