Capacity Planning, Aggregate Scheduling, Master Schedule, and Short-Term Scheduling - PowerPoint PPT Presentation

1 / 46
About This Presentation
Title:

Capacity Planning, Aggregate Scheduling, Master Schedule, and Short-Term Scheduling

Description:

Capacity Planning, Aggregate Scheduling, Master Schedule, and Short-Term Scheduling Capacity Planning 1. Facility size 2. Equipment procurement – PowerPoint PPT presentation

Number of Views:2180
Avg rating:3.0/5.0
Slides: 47
Provided by: mgtclassC
Category:

less

Transcript and Presenter's Notes

Title: Capacity Planning, Aggregate Scheduling, Master Schedule, and Short-Term Scheduling


1
Capacity Planning, Aggregate Scheduling, Master
Schedule, and Short-Term Scheduling
Capacity Planning 1. Facility size 2.
Equipment procurement
Long-term
Aggregate Scheduling 1. Facility utilization
2. Personnel needs 3. Subcontracting
Intermediate-term
Master Schedule 1. MRP 2. Dis-aggregation
of master plan
Intermediate-term
Short-term
Short-term Scheduling 1. Work center loading
2. Job sequencing
2
Scheduling Low-Volume Systems
  • Loading - assignment of jobs to process centers
  • Sequencing - determining the order in which jobs
    will be processed
  • Job-shop scheduling
  • Scheduling for low-volume systems with many
    variations in requirements

3
Loading Jobs in Work Centers
  • Assigning jobs to work centers
  • Considerations
  • Job priority (e.g., due date)
  • Capacity
  • Work center hours available
  • Hours needed for job
  • Approaches
  • Gantt charts (load scheduling) - capacity
  • Assignment method - job to specific work center

4
Loading
  • Two Approaches to loading
  • - Finite Loading limit the amount of work that
    is released to a given work center on the basis
    of capacity consideration.
  • Input/output control is a method for keeping
    track of assigned resource (input) and the work
    completed by a resources (output). This helps
    identify a backlog (input rate in greater that
    output rate). The remove a backlog to slow down
    the input.

5
Loading
  • - Infinite loading assign job to center
    regardless of available capacity. This requires
    that proper planning has been done to make sure
    enough capacity is available to take care of all
    work to be done.

6
Scheduling
  • Definition Determination of when something is to
    be done and the tasks and activities required to
    do it. Establishing the timing of the use of
    equipment, facilities and human activities in an
    organization
  • Scheduling aids in on-time completion
  • Direct link to value perceived by customers
  • Scheduling improves the utilization of the firms
    resources
  • Direct link to productivity

7
Strategic Implications of Short-Term Scheduling
  • By scheduling effectively, companies use assets
    more effectively and create greater capacity per
    dollar invested, which, in turn, lowers cost
  • This added capacity and related flexibility
    provides faster delivery and therefore better
    customer service
  • Good scheduling is a competitive advantage which
    contributes to dependable delivery

8
The Goals of Short-Term Scheduling
  • Minimize completion time
  • Maximize utilization (make effective use of
    personnel and equipment)
  • Minimize WIP inventory (keep inventory levels
    low)
  • Minimize customer wait time

9
Scheduling Services Considerations
  • Scheduling services different from manufacturing
  • Inability to store or inventory services
  • Random nature of customer requests for service
  • Point of customer contact
  • Back-office operations
  • Front-office operations

10
Choosing a Scheduling Method
  • Qualitative factors
  • Number and variety of jobs
  • Complexity of jobs
  • Nature of operations
  • Quantitative criteria
  • Average completion time
  • Utilization ( of time facility is used)
  • WIP inventory (average jobs in system)
  • Customer waiting time (average lateness)

11
Forward and Backward Scheduling
  • Forward scheduling begins the schedule as soon
    as the requirements are known
  • jobs performed to customer order
  • schedule can be accomplished even if due date is
    missed
  • often causes buildup of WIP
  • Backward scheduling begins with the due date of
    the final operation schedules jobs in reverse
    order
  • used in many manufacturing environments,
    catering, scheduling surgery

12
Scheduling Difficulties
  • Variability in
  • Setup times
  • Processing times
  • Interruptions
  • Changes in the set of jobs
  • No method for identifying optimal schedule
  • Scheduling is not an exact science
  • Ongoing task for a manager

13
Minimizing Scheduling Difficulties
  • Set realistic due dates
  • Focus on bottleneck operations
  • Consider lot splitting of large jobs

14
Sequencing
  • Sequencing Determine the order in which jobs at
    a work center will be processed.
  • Priority rules Simple heuristics used to select
    the order in which jobs will be processed.
  • Job time Time needed for setup and processing
    of a job.

15
Priority Rules for Dispatching Jobs
  • First come, first served
  • The first job to arrive at a work center is
    processed first
  • Earliest due date
  • The job with the earliest due date is processed
    first
  • Shortest processing time
  • The job with the shortest processing time is
    processed first
  • Longest processing time
  • The job with the longest processing time is
    processed first
  • Critical ratio
  • The ratio of time remaining to required work time
    remaining is calculated, and jobs are scheduled
    in order of increasing ratio.

16
Assumptions of Priority Rules
  • The setup of jobs is known
  • Setup time is independent of processing sequence
  • Setup time is deterministic
  • There will be no interruptions in processing such
    as
  • Machine breakdowns
  • Accidents
  • Worker illness

17
First Come, First Served Rule
  • Process first job to arrive at a work center
    first
  • Average performance on most scheduling criteria
  • Appears fair reasonable to customers
  • Important for service organizations
  • Example Restaurants

18
SPT and LPT Rule
  • SPT Schedule a job with shortest
    processing time first
  • LPT Schedule a job with longest processing
    time first

19
Earliest Due Date Rule
  • Process job with earliest due date first
  • Widely used by many companies
  • If due dates important
  • If MRP used
  • Due dates updated by each MRP run
  • Performs poorly on many scheduling criteria

20
Advantages of the Critical RatioScheduling Rule
  • Use of the critical ratio can help to
  • determine the status of a specific job
  • establish a relative priority among jobs on a
    common basis
  • relate both stock and make-to-order jobs on a
    common basis
  • adjust priorities and revise schedules
    automatically for changes in both demand and job
    progress
  • dynamically track job progress and location

21
Two Work Center Sequencing
  • Johnsons Rule technique for minimizing
    completion time for a group of jobs to be
    processed on two machines or at two work centers.
  • Minimizes total idle time
  • Several conditions must be satisfied

22
Johnsons Rule Conditions
  • Job time must be known and constant
  • Job times must be independent of sequence
  • Jobs must follow same two-step sequence
  • Job priorities cannot be used
  • All units must be completed at the first work
    center before moving to second

23
Johnson's Rule - Scheduling N Jobs on Two Machines
  • 1. List all jobs and their processing times each
    machine.
  • 2. Select first the job with the shortest
    processing time. If the shortest processing time
    lies with the first machine, the job is scheduled
    first if with the second machine, the job is
    scheduled last.
  • 3. Once a job is scheduled, eliminate it.
  • Apply steps 2-3 to the remaining jobs until all
    jobs are assigned. The process will move toward
    the center of the sequence.

24
Limitations of Rule-Based Dispatching Systems
  • Scheduling is dynamic therefore, rules need to
    be revised to adjust to changes in process,
    equipment, product mix, etc.
  • Rules do not look upstream or downstream idle
    resources and bottleneck resources in other
    departments may not be recognized
  • Rules do not look beyond due dates

25
Number of Servers
Single Server
Multiple Servers
Examples
Multiple Single Servers
Examples
26
Queue Discipline
First come -- first served (FCFS)
Multiple Priorities
Examples
27
Project Management
  • A project is a set of activities aimed at meeting
    a goal, with a defined beginning and end.

28
Project Management with Certain Time Estimates
  • Summary of steps
  • Determine activities that need to be accomplished
  • Determine precedence relationships and completion
    times
  • Construct network diagram
  • Determine the critical path
  • Determine early start and late start schedules

29
Project Scheduling When the Times of Activities
are Uncertain
  • Summary of steps
  • Determine the activities that need to be
    accomplished
  • Determine the precedence relationships and
    completion times
  • Construct the network diagram
  • Determine the critical path
  • Determine the early start and late start
    schedules
  • Calculate the variances for the activity times
  • Calculate the probability of completing by the
    desired due date

30
Project Scheduling with Time Uncertainty
  • The Heuristic approach to dealing with timing
    uncertainty
  • Based on understanding of individual activities
    as conforming to a beta distribution
  • Take three time estimates
  • Optimistic - What is the (realistic) fastest we
    can get an activity done?
  • Pessimistic - What is the (realistic) worst case
    scenario for delay?
  • Most likely - What is our most likely estimate?

31
Earliest Due Date Rule
  • Process job with earliest due date first
  • Widely used by many companies
  • If due dates important
  • If MRP used
  • Due dates updated by each MRP run
  • Performs poorly on many scheduling criteria

32
Best Methods among Priority Rule
  • SPT and EDD are superior in all measure. SPT is
    generally the best for minimizing flow and
    average number of jobs.

33
Critical Ratio (CR)
  • Ratio of time remaining to work time remaining

Time remaining

CR
Work days
remaining
Due date
-
Today'
s date

Work (lead
) time remaining
  • Process job with smallest CR first
  • Performs well on average lateness

34
Advantages of the Critical RatioScheduling Rule
  • Use of the critical ratio can help to
  • determine the status of a specific job
  • establish a relative priority among jobs on a
    common basis
  • relate both stock and make-to-order jobs on a
    common basis
  • adjust priorities and revise schedules
    automatically for changes in both demand and job
    progress
  • dynamically track job progress and location

35
Two Work Center Sequencing
  • Johnsons Rule technique for minimizing
    completion time for a group of jobs to be
    processed on two machines or at two work centers.
  • Minimizes total idle time
  • Several conditions must be satisfied

36
Johnsons Rule Conditions
  • Job time must be known and constant
  • Job times must be independent of sequence
  • Jobs must follow same two-step sequence
  • Job priorities cannot be used
  • All units must be completed at the first work
    center before moving to second

37
Limitations of Rule-Based Dispatching Systems
  • Scheduling is dynamic therefore, rules need to
    be revised to adjust to changes in process,
    equipment, product mix, etc.
  • Rules do not look upstream or downstream idle
    resources and bottleneck resources in other
    departments may not be recognized
  • Rules do not look beyond due dates

38
Queuing Theory
  • Where is waiting?
  • Service facility
  • Fast-food restaurants
  • post office
  • grocery store
  • bank

Manufacturing Equipment awaiting repair Phone
or computer network Product orders
39
Measures of System Performance
  • Average number of customers waiting
  • Average time customers wait
  • System utilization

40
Application of Queuing Theory
  • We can use the results from queuing theory to
    make the following types of decisions
  • How many servers to employ
  • Whether to use a single fast server or a number
    of slower servers
  • Whether to have general purpose or faster
    specific servers

Goal Minimize total cost cost of servers
cost of waiting
41
System Characteristics
  • Number of servers
  • Arrival and service pattern
  • Infinite Population The arrival is not
    affected by waiting line (public places, e.g.
    gas station)
  • Finite Population The arrival is affect by
    waiting line.
  • Queue discipline

42
Number of Servers
Single Server
Multiple Servers Single line
Examples
Multiple Single Servers
Examples
43
Customer Arrival rate variable follow a Poisson
Distribution
A Poisson distribution is usually assumed
This also is referred to as having random
arrivals.
44
Service Time
Either an exponential distribution is assumed
Examples
OR any distribution (only single-server model is
easily solved)
Examples
45
The Queue Arrival Process Determining the
Probability of x arrivals in a time period
  • Queue arrivals follow a Poisson distribution.
  • P(x) the probability of x arrivals in a time
    period
  • x the number of arrivals per unit time
  • ? the average arrival rate in a certain time
    increment
  • e 2.7283 (the base of the natural logarithms)

8-45
46
Managing Queue Arrivals
  • A Call center receives 36 calls per hour, Poisson
    distributed. What is the probability of
    receiving 41 calls?
  • ? 36
  • x 41
  • e 2.7283 (the base of the natural logarithms)

8-46
Write a Comment
User Comments (0)
About PowerShow.com