Title: Application of Radioactivity and the Law to Contaminated Land and Demolition Projects
1Application of Radioactivity and the Law to
Contaminated Land and Demolition Projects
- Gareth Walker, BSc, PhD, MRSC
2Contents
- Introduction to legislation
- Introduction to contamination land assessment,
and demolition decommissioning projects - Three case studies
3Overview of Legislation
- Main legislation for this presentation
- Nuclear Installations Act 1965
- Radioactive Substances Act 1993
- Including Exemption Orders
- Ionising Radiation Regulations 1999
- Environmental Protection Act 1990, Part IIA
- Site Waste Management Plan Regulations 2008
- DEFRA policy on Low Level Waste Management (2007)
4Why Undertake an Assessment?
- Obligation Liability management
- Obligated to comply with legislation
- If they fail to comply, are they liable?
- What is the extent of the liability?
5Types of assessments
- Will be focussing on contaminated land and
demolition/decommissioning assessment - Assessed through
- Contaminated land characterisation
- Risk assessment
- Remediation options and cost assessments
- Waste management
- Materials characterisation
6Case Studies
- Contaminated land assessment
- Sellafield characterisation
- Working in partnership with Serco Assurance
- Radiological risk assessment at Hunterston A
- Demolition and decommissioning assessment
- Waste management during decommissioning and
demolition at Bradwell
7Considerations Prior to Contaminated Land
Assessment
- Aim of the assessment
- Contaminant
- Source
-
- Pathway
- Receptor
- Leads to a potentially significant pollutant
linkage - Does the pollutant linkage represent an
unacceptable risk?
8Sellafield
9Drilling at Sellafield Overview
- Installation of boreholes
- Vertical holes (up to 60 m)
- Understanding ground profile (geology)
- Collection of soil and groundwater samples
- Spatial understanding from soil analysis
- Contaminant transport
- Source identification and understanding
- Pollutant linkages (radiological and chemical)
- Conceptual model building
10Characterisation at Sellafield
- Elements of legislation driving this project
- NIA65
- RSA93
- IRR99
- Drilling boreholes into land with unknown
concentrations, isotopes and forms of radioactive
contamination - Fission products
- Daughter isotopes
- Chemical properties
- Mobility by dissolved phase/colloidal transport
11Drilling at Sellafield
12Summary - Sellafield
- Worker safety paramount drillers, engineers and
general site staff - Must maintain nuclear and environmental safety
- Source terms must be defined
- Pathways and receptors must be defined
- Potential liability relating to contaminated land
must be understood
13Radiological Risk Assessment - Overview
- Hunterston A is in the process of decommissioning
and moving towards de-licensing parts of the site - Driver is to put the site into a care and
maintenance period - Assessment of risk to people and the environment
arising from land quality issues at Hunterston A - Through this assessment, understanding the
liability associated with potentially
contaminated land
14Radiological Risk Assessment - Overview
- Used land quality data gathered between 2000 and
2008 - Review of data and comparison to current
legislation - NIA65
- RSA93
- EPA90, Part IIA
- Guidance (statutory)
- Establish the extent of risk, if any, to people
and the environment - Does the site have a liability it needs to
address?
15Radiological Risk Assessment Part IIA
- Contaminated Land Report (CLR) -11 framework
followed to assess risk - Tiered approach
- Phase 1 completed in early 1990s
- Characterisation completed
- Areas of Potential Concern (APCs) identified
- Potentially significant pollutant linkages
identified - Generic qualitative risk assessment (GQRA)
- Conservative approach
- Screens each APC through risk assessment process
further work required?
16Radiological Risk Assessment Part IIA
- Developed a qualitative risk table
- Based on the MoD Defence Estates methodology, and
input from other consultancies to Defence Estates - In consultation with Magnox North
- Assesses pollutant linkage based on
- Magnitude of potential consequence (i.e.
Severity) - Magnitude of probability (i.e. Likelihood)
- RISK SEVERITY X LIKELIHOOD
17Radiological Risk Assessment Part IIA
DESCRIPTORS FOR SEVERITY OF CONSEQUENCE OF
CONTAMINANT SOURCE-RECEPTOR LINKAGE
18Radiological Risk Assessment Part IIA
DESCRIPTORS FOR PROBABILITY OF CONSEQUENCE
OCCURRING
19Radiological Risk Assessment Part IIA
- DESCRIPTORS OF Risk significance
- RISK SEVERITY X LIKELIHOOD
Likelihood Very likely / certain Likely Unlikely Very unlikely
Potential consequence Severe Very High Very High High Medium
Potential consequence Moderate High High Medium Low
Potential consequence Mild Medium Medium Low Very low
Potential consequence Negligible Low Low Very low Trivial
Likelihood Very likely / certain Likely Unlikely Very unlikely
Potential consequence Severe Very High Very High High Medium
Potential consequence Moderate High High Medium Low
Potential consequence Mild Medium Medium Low Very low
Potential consequence Negligible Low Low Very low Trivial
20Radiological Risk Assessment Part IIA
- Apply to each individual APC
- This will define
- Is more work required?
- What work is required?
- When can you stop?
21Radiological Risk Assessment - Summary
- Using this risk assessment approach allowed
- An assessment that is compatible with current law
and guidance - England Wales human health only
- Scotland also, water and ecological
environments - Significance of pollutant linkages to be assessed
in a consistent manner across the NDA
land-holding - Potential contaminated land liability to be
better understood, more readily prioritised and
therefore managed
22Considerations Prior to Demolition and
Decommissioning Assessment
- Legislation and guidance requires quantification
of waste and materials for site-wide Integrated
Waste Strategy (IWS) or Site Waste Management
Plan (SWMP) - The correct characterisation of items and
materials will form part of an IWS or SWMP - Location and extent of chemical and radioactive
contamination must be identified
23Waste Classification
- Waste classification and fate
- Intermediate Level Waste remains at site
creating the waste - Low Level Waste shipped to the LLWR at Drigg
- Very Low Level Waste hazardous waste landfills
with RSA93 licence - Exempt waste no regulatory control free
release - All waste removed from the site must be, as far
as is reasonably achievable, re-used or recycled,
with minimum final disposal
24Waste Management During Decommissioning
25Waste Management During Decommissioning
26Waste Management During Decommissioning
27Waste Management During Decommissioning
28Waste Management During Decommissioning
29Waste Management During Decommissioning - Summary
- Context for determination of a site strategy for
the management of decommissioning wastes and
items is determined by Site Waste Management Plan
regs - Previously required an IWS (EGG01)
- Waste management plans should be developed with
appropriate regulatory and stakeholder
involvement and should take into account current
best practice - e.g. Nuclear Industry Code of Practice
- Current decommissioning policy for nuclear sites
in under review - SDSPUR / SAFESPUR / SAFEGROUNDS / CoRWM
30Summary
- Obligation and liability management
- Legislation grey areas overlap changes
- On-site as opposed to off-site
- Complex sites
- Long histories many stakeholders
- Pollutant linkages
- Characterise Assess Mitigate
- Waste management
- During characterisation
- During remediation
- During demolition decommissioning
31Acknowledgements
- Sellafield contaminated land team
- Hunterston A (Magnox North Hugh Richards)
- Bradwell (Magnox South)
32Application of Radioactivity and the Law to
Contaminated Land and Demolition Projects
- Gareth Walker, BSc, PhD, MRSC