Title:

Facilities Improvements and Bond Construction Update Facilities Advisory Committee

Description:

Existing building HVAC systems to be upgraded in synch with ... A newly upgraded design reflecting a mechanical engineered system was installed ... – PowerPoint PPT presentation

Number of Views:83
Avg rating:3.0/5.0
Slides: 25
Provided by: BillA91
Category:

less

Write a Comment
User Comments (0)
Transcript and Presenter's Notes

Title: Facilities Improvements and Bond Construction Update Facilities Advisory Committee


1
Facilities Improvements and Bond Construction
UpdateFacilities Advisory Committee
  • Long Beach Community College District
  • December 2, 2008

EDUCATE ? ENGAGE ? EMPOWER
2
Agenda
  • Completed Construction Projects
  • PCC Learning Resource Center
  • LAC Central Plant
  • Current Upcoming Construction Projects
  • LAC South Quad Complex
  • LAC Learning Resource Center
  • LAC Building A, Student Services Retrofit
  • LAC Math Technology Building
  • LAC Parking Structure
  • LAC Infrastructure Improvements Phase 3
  • PCC Central Plant
  • PCC Industrial Tech Phase 1
  • PCC MDAB (Multi-Disciplinary Academic Building)
  • PCC Building C Retrofit
  • District Wide Building Needs Assessment Projects
  • Toilet Improvement Projects
  • Quick-Start Projects
  • ADA Projects
  • Lighting Projects

3
Completed Construction Projects
PCC Learning Resource Center Measure E 2002
  • Construction Complete
  • Modern Facility with Computer Lab and Multimedia
  • Stand alone Data Center. Provides District IT
    redundancy
  • Bridge to building E
  • Design elements move towards energy efficiencies
  • Ribbon cutting held 9/17/08

4
Completed Construction Projects
LAC Central Plant Measure E 2002
  • Central Plant equipment, Public Safety, Field
    House for Athletics
  • Final FFE installation underway
  • Plant ready for operation and awaiting completion
    of LRC SQC
  • Construction Complete
  • Anticipated startup 12/05/08

5
Current and UpcomingConstruction Projects
South Quad Complex Measure E 2002
  • Construction approx. 89 Complete
  • Space includes
  • Approx. 68,000 ASF
  • 32 modern classrooms and labs
  • 38 faculty offices
  • Executive office
  • Multipurpose room
  • State of the art Board Room
  • Substantial completion anticipated 1/09

6
Current and UpcomingConstruction Projects
LAC/Learning Resource Center Measure E 2002
  • Construction 91 Complete
  • Adds 10,000 ASF to existing building
  • Substantial Completion Anticipated January 2009

7
Current and UpcomingConstruction Projects
LAC Building A Student Services
Retrofit Measure E 2008
  • Design Development to be submitted this month
  • Adds 4,000 ASF to existing building
  • Will house AR, Counseling, Health Services,
    Cashier, Transfer Ctr., etc.
  • Estimated start of construction 7/09

8
Current and UpcomingConstruction Projects
LAC Math Technology Building Measure E 2008
  • Completed Schematic Design (June 2008)
  • Currently in Design Development phase
  • Will house Math and Culinary Arts instructional
    program as well as Reprographics
  • Estimated start of construction 2011

9
Current and UpcomingConstruction Projects
LAC Parking Structure Measure E 2008
  • Planning initiated for approximately 900 Vehicles
  • To be procured under Design Build Delivery
    method
  • To be located Southeast corner of Lot J adjacent
    to the Verizon building
  • Photovoltaic Electrical Generation Array on top
    level of structure
  • Anticipated start of construction 2009

Proposed Math Technology Bldg.
Lot J
Proposed Parking Structure Loc.
Verizon Bldg.
10
Current and UpcomingConstruction Projects
  • LAC Infrastructure Improvements Phase 3
  • Measure E 2008
  • Planning underway with engineers
  • Completes chilled water lines to North side of
    campus
  • Includes other major utility upgrades Reclaimed
    Water, Domestic Water, Data, etc.
  • Existing building HVAC systems to be upgraded in
    synch with infrastructure improvements
  • Coordinated with modernization and quick start
    projects

11
Current and UpcomingConstruction Projects
PCC Central Plant Measure E 2002
  • Houses Central Plant equipment and Maintenance
    and Operations facility
  • Construction Approximately 99 Complete
  • Currently provides chilled water to the PCC LRC

12
Current and UpcomingConstruction Projects
PCC Industrial Technology Center Phase 1 Measure
E 2002
  • Modern facility houses Welding Department and
    other trade programs
  • Construction is 45 complete
  • Replaces existing antiquated structures
  • New Northern face of the campus
  • Completion anticipated summer 2009

13
Current and UpcomingConstruction Projects
PCC MDAB (Multi-Disciplinary Academic Building)
Measure E 2002
  • 90 construction documents submitted
  • Swing space planning completed 9/2008,
    construction of swing space starts Spring 2009
  • Anticipated start of MDAB construction Summer
    2009
  • To be completed in two phases

14
Current and UpcomingConstruction Projects
PCC Building C Retrofit - Measure E 2008
  • To be designed by Hill Partnership Architects
  • Houses the Fitness Center, Gymnasium, Weight
    Room, and Faculty and Staff Offices
  • Swing space to be located on PCC Campus (TBD)
  • To be completed concurrently with MDAB project
  • Anticipated start of construction Spring 2010

15
Current and UpcomingConstruction Projects
District Wide Building Needs Assessment
Project Measure E 2008
  • Toilet Improvement Projects
  • Quick-Start Projects
  • ADA Projects

16
Current and UpcomingConstruction Projects
District Wide Building Needs Assessment
Projects Measure E 2008
  • Lighting Projects
  • Classroom Improvement Projects

17
Recently Completed Facilities Improvements
Building B and E Boiler Replacement
  • Replaced existing boilers, pumps, expansion tanks
    and common flue with new equipment via helicopter
    lift.
  • A newly upgraded design reflecting a mechanical
    engineered system was installed improving the
    efficiency of the boilers.
  • Completed 10/2008

18
Recently Completed Facilities Improvements
Additional Facilities Improvements
  • LAC upgrades
  • Veterans Stadium scoreboard and PA system
    upgrade
  • Building K upgrades Exterior door paint, room
    111 floor refinishing
  • PCC upgrades
  • Building AA Built wall for information desk,
    installed carpet, and power upgrades
  • Building BB Carpet and window blind
    installation
  • Building CC Installed fans in gym
  • Building DD Carpet and window blind
    installation
  • Building EE Window blind installation
  • Building MM Exterior paint, replaced doors and
    awnings, re-glazed windows, and replaced fascia
    boards

19
Important Ongoing Initiatives
LBCCD Coming Advancements
  • Master Landscape Project
  • District Wide Energy Efficiency Improvements
  • Electronic Marquee Signage
  • Wayfaring and Building Signage
  • Campus Lighting Improvements

20
Planned Phasing of Future Projects
Currently Planned Schedule
  • 2008-09
  • Parking Structure Design/Build concept
  • Anticipate awarding bid Spring 2009
  • Moving Warehouse from PCC to Alteon Building at
    LAC TBD
  • Moving LAC Building A into Swing Space Spring
    2009
  • Install portables at PCC for Swing Space Spring
    2009
  • LAC/PCC Building Needs Assessment Projects
  • Bathroom Improvement Projects
  • Quick-Start Projects
  • Lighting Projects
  • Classroom Improvement Projects
  • Infrastructure Projects
  • Submit FPP for M/N Project at LAC and MM Project
    at PCC and submit IPP for P Building at LAC
  • Finalize Master Landscaping and Signage plans
  • Marquee signage anticipated to be installed March
    2009

21
Planned Phasing of Future Projects
Currently Planned Schedule
  • 2009-10
  • Begin construction of Building A at LAC
  • Anticipating July 2009 start
  • Begin construction of Buildings CC, DD, and EE at
    PCC
  • Anticipating July/August 2009 start
  • Begin Schematic Design for Buildings C and F at
    LAC
  • Submit plans to DSA no later than March 2010
  • Begin Master Landscaping and Signage Initiatives
  • Continue District Wide Energy Efficiency
    Improvements
  • Phase IIA
  • Lighting Upgrades, HVAC Upgrades, Control
    upgrades, Pool Cover, Roof replacement, etc
  • Phase IIB
  • Upcoming advancements include connecting current
    buildings to Central Plant infrastructure

22
Planned Phasing of Future Projects
Currently Planned Schedule
  • 2010-11
  • Anticipated Construction completion of Building A
    at LAC January 2011
  • Submit plans to DSA for Math/Technology Building
    at LAC
  • Move Buildings C and F programs into Swing Space
    (M/N Building) and begin construction Spring
    2011
  • Construction completion of Buildings CC, DD and
    EE at PCC
  • Begin construction of Buildings AA and BB at PCC
  • Anticipating January/February 2011 start

23
Planned Phasing of Future Projects
Currently Planned Schedule
  • 2011-12
  • Begin construction of Math/Technology Building at
    LAC
  • Submit plans to DSA for M/N Building at LAC
  • 2012-13
  • Anticipated Construction completion of Buildings
    C and F at LAC December 2012
  • Anticipated Construction completion of
    Math/Technology Building at LAC December 2012
  • Begin construction of Buildings M/N at LAC
    January 2013
  • Anticipated Construction completion of Buildings
    AA and BB at PCC June 2013

24
QUESTIONS ANSWERS