Test procedure established at every production site. # of successfully average ... Dubna received material to pick up on 22 L2C1 chambers only very recently. ... – PowerPoint PPT presentation

Number of Views:41
Avg rating:3.0/5.0
Slides: 11
Provided by: wwwali
Category:

less

Transcript and Presenter's Notes

Title: TRD ROC Status Christian J' Schmidt, GSI Detector Lab'


1
TRD ROC StatusLeak Fixing and General Production
  • TRD Status Meeting
  • 12.03.2008
  • Institute for Nuclear Physics, Darmstadt

2
Underpressure Leak Tests
  • Test procedure established at every production
    site.
  • of successfully average
  • fixed and tested chambers leak
    conductance l/h
  • Bucharest 4 3.2
  • Heidelberg 1 ?
  • Frankfurt 9 1.9
  • Dubna 6 0.8
  • GSI 111 (incl. SM5) 2.04
  • Total to date done 131 1.99
  • additionally at CERN 10 (SM4)
    5

SM5 was fixed at GSI, resulting in an overall
added leak conductance of 49.5 l/h
3
What is left to do
  • SM3 (30 ch, CERN) 50 are currently
    traveling to GSI
  • GSI 43 in the queue after SM3
  • Frankfurt 50 still in debate
  • Bucharest 21 in the queue, delivery in May
  • Heidelberg 13 in the queue
  • Münster 3 integration spares, should be fixed
    in Münster
  • Dubna 15 delivery planned in June
  • SM1 SM2 60 located in space frame
  • SM4 20 all have been treated, need testing
  • Sum 225

4
Priorities
  • Highest Fix and reassemble SM3 and SM4,
    assemble SM5 for installation before April
    25th
  • (Kens talk)
  • Second Keep constant supply of fixed and tested
    chambers for further SM assembly (GSI,
    Frankfurt), ch. for SM6 are OK
  • Third Fix remaining chambers at production sites
    before delivery to GSI
  • Fourth Integrate under-pressure leak test into
    final test procedures, replacing previous
    leak test.
  • Do not deliver unfixed/ non-tested chambers!
  • X.5th Fix and reassemble SM1 and SM2 as soon as
    they may be un-mounted

5
Parts and Materials to Finalize Ch. Production
  • Padplanes
  • Last fill-in orders and claims for reclamation
    have been sent out to Optiprint
  • Backpanels
  • Last fill-in orders to complete production have
    been initiated
  • Radiators
  • Need to collect all superfluous and damaged
    radiators to recover material for the last
    fill-in production at Münster. Please check at
    your site!
  • Field-cages
  • Some 10 field cage pcb sets are missing, could
    improvise refurbishing other sizes or order new

6
Production Status
448 out of 540 15 (spares) are in production,
an overall of 81
Extrapolation (555 448) / (3,21 ch/week) 33
i.e. beginning Nov. 2008
7
TRD Chamber Production
Target !
August 2008
8
TRD ROC Momentary Production Rates
Observed History and Future Demand
Needed Rates!
9
Individual Issues at Production Sites
  • Bucharest is stalled, waiting for material
  • Dubna received material to pick up on 22 L2C1
    chambers only very recently. Dubna targets to
    finish production end of November 2008!
  • Frankfurt just reached their average again,
    production will not be finished until December
    2008!
  • GSI was stalled on testing in order to realize
    leak tests but kept production rate up
  • Heidelberg stalled on testing to set up
    underpressure leak-test-stand but kept chamber
    production up as well. August 2008 will
    nevertheless be very ambitious!

10
Summary
  • We see land in leak fixing but a lot of carefully
    instructed personal is needed
  • Four channel leak test stand with alternated
    Oxygen sensor proved very helpful at GSI
  • We should be able to prepare SM3, SM4 and SM5 for
    insertion before April 25th.
  • Chamber production is running in spite of the
    additional work load for fixing and testing.
  • Nevertheless, the August 1st deadline for
    finishing chamber production has by now become
    unrealistic.