Title: Photoinjector for the ILC test facility at Fermilab
1Photoinjector for the ILC test facility at
Fermilab
- Sergei Nagaitsev
- Fermilab
- May 24, 2007
2Fermilab NML plans
- Fermilab is constructing the NML facility at the
existing building (called New Muon Lab) for the
ILC tests and generic accelerator research - The NML is being constructed to address primarily
the ILC S2 RD list - However, our plans go beyond S2. We would like
to include elements of S4 RD tasks
(crab-cavities), diagnostics development,
personnel training, and accelerator RD. - The NML facility is staged (1 CM, 2 CMs etc)
when complete, it would include 1 (or 2) rf units
running ILC-like beam at 5 Hz. - 1 rf unit with beam requires building an
extension tunnel and a new cryo-plant - The progress is resource limited
3NML inside (now)
4Outline of our plans
- Cryomodule delivery
- 1st (Type 3) cryomodule is planned to be
delivered in fall, 2007 - 2nd (Type 3) CM summer 2008
- 3rd (ILC Type 4) CM Mid FY09
- Replace all three CMs with ILC Type 4 in FY2010
- The NML facility will start as a Cryomodule Test
Stand in FY07-08 - FY08 add beam start civil construction of the
building extension - Convert to an ILC RF Unit beam test facility in
FY11
5NML Schedule (Phase-1)
- Phase - 1 (FY07 thru early FY08)
- Prepare Facility for Testing of Capture Cavity II
(CCII) and 1st Cryomodule (CM1) without Beam - Building Infrastructure (AC Power, Water, Air,
Mechanical) - Electrical Infrastructure (Racks, Trays, Cables)
- Build Cave to Test these Devices ( 3/4 of Full
Cave) - RF Systems (3MW for CM and 300kW for CCII)
- Cryogenic System (1st Refrigerator, Feed Can,
Feed Cap, End Cap, Distribution) - Control Room
- LLRF, Controls, Safety Systems, Instrumentation
(non-beam) - Move CCII from Meson Detector Building (MDB) to
NML - Cool-down and Power Testing
6Phase 1 1st CM (end of CY07)
A used 3-MW Klystron, 10-MW, 1.5-ms modulator
CC2 RF system
Capture cavity 2 in its final location for the
injector
Type 3 cryomodule
7NML Schedule (Phase-2 3)
- Phase - 2 (FY08)
- Testing of 1st and 2nd Cryomodule without Beam,
Prepare Facility for Beam - Receive, Install, Power, Cool-down 1st Cryomodule
- Install New Gun and Relocate Injector to NML
- Extend Cave
- Install Beam Lines and Dumps
- Install Additional RF Systems needed for CCI and
Gun - Receive, Install, Power, Cool-down 2nd Cryomodule
- Begin Building Extension needed for Phase-3
- Phase - 3 (FY09)
- Testing of Full RF Unit with Beam
- Complete Building Extension
- Begin Testing with Beam
- Install 3rd Cryomodule
- Upgrade Cryomodule RF system to 10 MW
8Two CMs with beam
The existing building is perfect for testing two
cryomodules with ILC-like beam. The building can
be extended to fit 3 cryomodules.
9ILC-like beam?
- 3.2 nC/bunch _at_3 MHz, up to 3000 bunches _at_ 5Hz
- Bunch length 300-µm rms
- Transverse emittance not important (5 µm)
- Energy 30-40 MeV (to avoid overfocusing in the
CM operating at 31 MV/m) - Need known and frozen beam parameters at the
cryomodule entrance
10Existing Fermilab Photoinjector
The existing photoinjector and the laser will be
moved to NML in 2008.
13m
(CC-1)
11Fermilab Photo Injector
- The PhotoInjector has been in operation since
late 90s and has been a training ground for SCRF
technology - Provides 17MeV bunches (up to few hundred) at 1
MHz rate at 1 pulse/sec - Two 1.3-GHz klystron-based RF systems power the
RF Gun and Capture Cavity - RF systems will be moved to NML in 2008
Capture Cavity and beamline
12Existing rf gun
- Very high dark current
- rf break down for pulses longer than 300us
- We will not use this gun cavity at NML
RF Gun prior to solenoid installation
13Proposed NML Injector Layout
22m
(CC-1, CC-2)
(intended initially for ILC crab cavity tests)
P. Piot
14NML injector layout
6
4
8
1
2
5
3
7
- 1 Gun cavity, 2 Coaxial rf coupler, 3 dark
current kicker, 4 laser mirror cross, 5
current monitor BPM, 6 - collimator, 7 Tesla
cavity (CC1), 8 Tesla cavity (CC2)
15NML cathode system
Gun Transfer
Transport System
GUN
16Fermilab plans for the rf gun
- We are planning to copy (and improve) a DEZY-PITZ
gun - RF gun sub-systems needed at NML
- Cathode system -- need new, will be supplied by
INFN Milano - UV laser system -- exists, needs upgrades
- Gun cavity need new, will be supplied by DESY
- Focusing solenoids need new
- Coaxial coupler need new
- Dark current kicker need new
- Laser mirror cross need new
- RF system (5-MW or more, 1.5-ms modulator)
exists (needs updrades) - Water, temperature control system -- exists
17Cathode system
- The cathode system is being provided to us by
INFN-Milano. - Two sub-systems
- A stand-alone vacuum chamber for cathode
preparation with Cs and Te sources - A cathode loading chamber connected to the gun
cavity. - Discussions underway on how to redesign the
cathode socket (and spring) in the gun cavity.
Goal reduce the dark current - Would like to hide the rf contact spring
- See next slides
18RF spring contact (from D. Sertore, INFN)
- Two different spring types have been used, in
the same insert! - The insert was designed for a WELDED Watch-band
type spring.
- Cantend coil spring
- CuBe uncoated.
- Available coated with Ag, Au etc
- Welded by the manufacturer
- Watch-band type
- CuBe hard, silver coated spring
- Difficult to weld (becomes hard)
- Critical number of convolutions
19Our latest proposal to INFN and DESY
- Two springs one for centering and one locking
20UV laser system
- Already have at photoinjector
- Needs some upgrading
- Will be moved to NML in Jan 2008
- Can run a single gaussian pulse or stacked (4)
pulses at 3MHz
21Gun cavity
- Have all DESY drawings at Fermilab. Do not yet
have a complete set of procedures (brazing,
tuning etc) - Would like to make some modifications to design
cathode socket, rf probe, reduce max. fields - Will take time to develop expertise.
- DESY has agreed to make a gun cavity for us at
DESY. - Currently negotiating small changes to their
design (cathode) - We will start making our own gun cavity and the
coupler shortly after DESY will start the
manufacturing. - KEK STF has asked us to supply a gun cavity for
them. No official agreement yet.
22RF probe - possible location
23Focusing solenoids
- Will make two identical solenoids (like main
solenoid above) instead of two different ones - Present bucking coil design interferes with a
possible rf probe installation at the gun cavity
cathode wall. - Solenoids can be ordered from Danfysik (they have
drawings, fixtures) 30k each - PS needed 500A, 50V, 10 ppm 27k Eur
24Laser mirror
- Have drawings from DESY
- Laser mirror alignment will be difficult because
coaxial coupler inner diameter is small
25RF system
- Already have a 5MW Klystron at the photoinjector
- TH 2104C
- Need a new 1.5-ms modulator and a pulse
transformer - Planning to build at Fermilab
- Plan to run the gun at 40 MV/m at the cathode
- From DESY simulations gradient 23
MV/m(PMW)1/2 - For 40 MV/m need about 3 MW. For conditioning
need more power.
26Water system
- Temperature stability is crucial
- Average power at 1ms flattop, 5 Hz 15 kW
- Simulations freq. shift -23 kHz per one-degree C
- Plan temperature control to 1F (0.5 degree C)
27Overall summary
- Would like to have beam at NML in Apr 2008
- The rf gun will be capable of providing ILC-like
beams. For 4-stacked laser pulses at 40 MV/m _at_
cathode - 3.2 nC per bunch
- 4.2 MeV kinetic energy at gun exit
- 4-µm rms norm emittance
- 2.4 mm rms bunch length
- 1.2 rms momentum spread