Photoinjector for the ILC test facility at Fermilab - PowerPoint PPT Presentation

1 / 27
About This Presentation
Title:

Photoinjector for the ILC test facility at Fermilab

Description:

Electrical Infrastructure (Racks, Trays, Cables) ... The existing building is perfect for testing two cryomodules with ILC-like beam. ... – PowerPoint PPT presentation

Number of Views:53
Avg rating:3.0/5.0
Slides: 28
Provided by: mcgi45
Category:

less

Transcript and Presenter's Notes

Title: Photoinjector for the ILC test facility at Fermilab


1
Photoinjector for the ILC test facility at
Fermilab
  • Sergei Nagaitsev
  • Fermilab
  • May 24, 2007

2
Fermilab NML plans
  • Fermilab is constructing the NML facility at the
    existing building (called New Muon Lab) for the
    ILC tests and generic accelerator research
  • The NML is being constructed to address primarily
    the ILC S2 RD list
  • However, our plans go beyond S2. We would like
    to include elements of S4 RD tasks
    (crab-cavities), diagnostics development,
    personnel training, and accelerator RD.
  • The NML facility is staged (1 CM, 2 CMs etc)
    when complete, it would include 1 (or 2) rf units
    running ILC-like beam at 5 Hz.
  • 1 rf unit with beam requires building an
    extension tunnel and a new cryo-plant
  • The progress is resource limited

3
NML inside (now)
4
Outline of our plans
  • Cryomodule delivery
  • 1st (Type 3) cryomodule is planned to be
    delivered in fall, 2007
  • 2nd (Type 3) CM summer 2008
  • 3rd (ILC Type 4) CM Mid FY09
  • Replace all three CMs with ILC Type 4 in FY2010
  • The NML facility will start as a Cryomodule Test
    Stand in FY07-08
  • FY08 add beam start civil construction of the
    building extension
  • Convert to an ILC RF Unit beam test facility in
    FY11

5
NML Schedule (Phase-1)
  • Phase - 1 (FY07 thru early FY08)
  • Prepare Facility for Testing of Capture Cavity II
    (CCII) and 1st Cryomodule (CM1) without Beam
  • Building Infrastructure (AC Power, Water, Air,
    Mechanical)
  • Electrical Infrastructure (Racks, Trays, Cables)
  • Build Cave to Test these Devices ( 3/4 of Full
    Cave)
  • RF Systems (3MW for CM and 300kW for CCII)
  • Cryogenic System (1st Refrigerator, Feed Can,
    Feed Cap, End Cap, Distribution)
  • Control Room
  • LLRF, Controls, Safety Systems, Instrumentation
    (non-beam)
  • Move CCII from Meson Detector Building (MDB) to
    NML
  • Cool-down and Power Testing

6
Phase 1 1st CM (end of CY07)
A used 3-MW Klystron, 10-MW, 1.5-ms modulator
CC2 RF system
Capture cavity 2 in its final location for the
injector
Type 3 cryomodule
7
NML Schedule (Phase-2 3)
  • Phase - 2 (FY08)
  • Testing of 1st and 2nd Cryomodule without Beam,
    Prepare Facility for Beam
  • Receive, Install, Power, Cool-down 1st Cryomodule
  • Install New Gun and Relocate Injector to NML
  • Extend Cave
  • Install Beam Lines and Dumps
  • Install Additional RF Systems needed for CCI and
    Gun
  • Receive, Install, Power, Cool-down 2nd Cryomodule
  • Begin Building Extension needed for Phase-3
  • Phase - 3 (FY09)
  • Testing of Full RF Unit with Beam
  • Complete Building Extension
  • Begin Testing with Beam
  • Install 3rd Cryomodule
  • Upgrade Cryomodule RF system to 10 MW

8
Two CMs with beam
The existing building is perfect for testing two
cryomodules with ILC-like beam. The building can
be extended to fit 3 cryomodules.
9
ILC-like beam?
  • 3.2 nC/bunch _at_3 MHz, up to 3000 bunches _at_ 5Hz
  • Bunch length 300-µm rms
  • Transverse emittance not important (5 µm)
  • Energy 30-40 MeV (to avoid overfocusing in the
    CM operating at 31 MV/m)
  • Need known and frozen beam parameters at the
    cryomodule entrance

10
Existing Fermilab Photoinjector
The existing photoinjector and the laser will be
moved to NML in 2008.
13m
(CC-1)
11
Fermilab Photo Injector
  • The PhotoInjector has been in operation since
    late 90s and has been a training ground for SCRF
    technology
  • Provides 17MeV bunches (up to few hundred) at 1
    MHz rate at 1 pulse/sec
  • Two 1.3-GHz klystron-based RF systems power the
    RF Gun and Capture Cavity
  • RF systems will be moved to NML in 2008

Capture Cavity and beamline
12
Existing rf gun
  • Very high dark current
  • rf break down for pulses longer than 300us
  • We will not use this gun cavity at NML

RF Gun prior to solenoid installation
13
Proposed NML Injector Layout
22m
(CC-1, CC-2)
(intended initially for ILC crab cavity tests)
P. Piot
14
NML injector layout
6
4
8
1
2
5
3
7
  • 1 Gun cavity, 2 Coaxial rf coupler, 3 dark
    current kicker, 4 laser mirror cross, 5
    current monitor BPM, 6 - collimator, 7 Tesla
    cavity (CC1), 8 Tesla cavity (CC2)

15
NML cathode system
Gun Transfer
Transport System
GUN
16
Fermilab plans for the rf gun
  • We are planning to copy (and improve) a DEZY-PITZ
    gun
  • RF gun sub-systems needed at NML
  • Cathode system -- need new, will be supplied by
    INFN Milano
  • UV laser system -- exists, needs upgrades
  • Gun cavity need new, will be supplied by DESY
  • Focusing solenoids need new
  • Coaxial coupler need new
  • Dark current kicker need new
  • Laser mirror cross need new
  • RF system (5-MW or more, 1.5-ms modulator)
    exists (needs updrades)
  • Water, temperature control system -- exists

17
Cathode system
  • The cathode system is being provided to us by
    INFN-Milano.
  • Two sub-systems
  • A stand-alone vacuum chamber for cathode
    preparation with Cs and Te sources
  • A cathode loading chamber connected to the gun
    cavity.
  • Discussions underway on how to redesign the
    cathode socket (and spring) in the gun cavity.
    Goal reduce the dark current
  • Would like to hide the rf contact spring
  • See next slides

18
RF spring contact (from D. Sertore, INFN)
  • Two different spring types have been used, in
    the same insert!
  • The insert was designed for a WELDED Watch-band
    type spring.
  • Cantend coil spring
  • CuBe uncoated.
  • Available coated with Ag, Au etc
  • Welded by the manufacturer
  • Watch-band type
  • CuBe hard, silver coated spring
  • Difficult to weld (becomes hard)
  • Critical number of convolutions

19
Our latest proposal to INFN and DESY
  • Two springs one for centering and one locking

20
UV laser system
  • Already have at photoinjector
  • Needs some upgrading
  • Will be moved to NML in Jan 2008
  • Can run a single gaussian pulse or stacked (4)
    pulses at 3MHz

21
Gun cavity
  • Have all DESY drawings at Fermilab. Do not yet
    have a complete set of procedures (brazing,
    tuning etc)
  • Would like to make some modifications to design
    cathode socket, rf probe, reduce max. fields
  • Will take time to develop expertise.
  • DESY has agreed to make a gun cavity for us at
    DESY.
  • Currently negotiating small changes to their
    design (cathode)
  • We will start making our own gun cavity and the
    coupler shortly after DESY will start the
    manufacturing.
  • KEK STF has asked us to supply a gun cavity for
    them. No official agreement yet.

22
RF probe - possible location
23
Focusing solenoids
  • Will make two identical solenoids (like main
    solenoid above) instead of two different ones
  • Present bucking coil design interferes with a
    possible rf probe installation at the gun cavity
    cathode wall.
  • Solenoids can be ordered from Danfysik (they have
    drawings, fixtures) 30k each
  • PS needed 500A, 50V, 10 ppm 27k Eur

24
Laser mirror
  • Have drawings from DESY
  • Laser mirror alignment will be difficult because
    coaxial coupler inner diameter is small

25
RF system
  • Already have a 5MW Klystron at the photoinjector
  • TH 2104C
  • Need a new 1.5-ms modulator and a pulse
    transformer
  • Planning to build at Fermilab
  • Plan to run the gun at 40 MV/m at the cathode
  • From DESY simulations gradient 23
    MV/m(PMW)1/2
  • For 40 MV/m need about 3 MW. For conditioning
    need more power.

26
Water system
  • Temperature stability is crucial
  • Average power at 1ms flattop, 5 Hz 15 kW
  • Simulations freq. shift -23 kHz per one-degree C
  • Plan temperature control to 1F (0.5 degree C)

27
Overall summary
  • Would like to have beam at NML in Apr 2008
  • The rf gun will be capable of providing ILC-like
    beams. For 4-stacked laser pulses at 40 MV/m _at_
    cathode
  • 3.2 nC per bunch
  • 4.2 MeV kinetic energy at gun exit
  • 4-µm rms norm emittance
  • 2.4 mm rms bunch length
  • 1.2 rms momentum spread
Write a Comment
User Comments (0)
About PowerShow.com