Title: US CMS EMU FNAL


1
US CMS EMU - FNAL
  • Oct 27 1999 - Agenda
  • P2 HV Connectors Experience/Problems
    Sergei
  • HV Connectors Specifications Dick/Phil
  • Indexing Measurements on Soldering Machine Oleg
  • Nov-Dec 99 Plans Giorgio

2
US CMS EMU - FNAL
  • Factory Plans
  • Produce ME234/2 Anode Panel (Oct 4-15)
  • Travelers/Procedures debugging
  • Completed by October 11 October 22
  • To Purdue for Tensioning Machine setup
  • Produce P4 (ME1/2) (Nov 15-30) (Oct 15-30)
  • Parts prepared in MP9 (Capacitor, resistors,
    connectors)
  • Cathode Panel starting on October 15
    November 1
  • Anode Panels starting by October 30 (?)
    November 20
  • Transfer to MP9 P2 and swap Anode Panel (Nov 1
    - 7)
  • Chamber disassembly Procedure
  • Transfer to MP9 P2 (Nov 8-15)
  • Fix sector 4-3
  • Faraday Cage (?)

3
US CMS EMU - FNAL
  • Factory Plans
  • ME234/2 Anode Panel (Oct 22-Nov 7)
  • To Purdue for Tensioning Machine setup
  • Transfer to MP9 P2 and swap Anode Panel (Nov
    7- 15)
  • Chamber disassembly Procedure
  • Produce P4 (ME1/2) (Nov 15-30)
  • Parts prepared in MP9 (Capacitor, resistors,
    connectors)
  • Cathode Panel starting on October 15
    November 1
  • Anode Panels starting by October 30 (?)
    November 20
  • Transfer to MP9 P2 (either on Nov 15 or 1
    month later)
  • Fix sector 4-3
  • Faraday Cage (?)
  • Start ME234/2 Production on Dec. 20
  • All parts to be in, start with 2 chambers with
    wrong frame

4
US CMS EMU - FNAL
  • MP9 Production Readiness Reviews
  • Address FNAL ability to start producing chambers
  • Safety Oct 28 - Nov 4 - Nov 11
  • Committee in place and convened
  • Covering all toolings with moving parts or HV
    operations
  • Purdue Winding Machine
  • FNAL All the rest
  • Procedures
  • Personnel training
  • Production Readiness Review November 30 (?)
  • Starting to form committee
  • Travelers
  • Training
  • QC/QA
  • Kits
  • Incoming/outgoing
  • Manpower