200607 DPW Annual Report Presentation to the Portfolio Committee

Description:

Performance audit was carried out on main programmes of the Department and these ... have confounded the need for structural changes like the creation of fully ... – PowerPoint PPT presentation

Number of Views:69
Avg rating:3.0/5.0
Slides: 46
Provided by: siphiwem
Category:

less

Transcript and Presenter's Notes

Title: 200607 DPW Annual Report Presentation to the Portfolio Committee


1
2006/07 DPW Annual ReportPresentation to the
Portfolio Committee
  • 17 October 2007

2
Table of Contents
  • Introduction
  • Strategic Overview
  • Programme Performance
  • Asset Management
  • Operations
  • Re-Kgabisa Tshwane
  • NPWP and Policy
  • Expanded Public Works Programme
  • Financial Management
  • Human Resources Management
  • Strategic Corrective Measures
  • Conclusion.

3
Introduction
  • For the first time in the 2006/07 the Department
    reported on two sets of financial statements
    including the Trading Account
  • Performance audit was carried out on main
    programmes of the Department and these programmes
    will form the core of this presentation
  • This report is for the period of 01/04/06 to
    31/03/07

4
Strategic Overview
  • Refocusing DPW from coordination to leadership
    and implementation roles
  • Capacitating the EPWP Unit for the massification
    of the EPWP roll-out
  • Strong intergovernmental relationship and close
    cooperation with provinces and Public Entities
    (DWINIF, HOD Forums)
  • Presentation and Gazetting of the Construction
    charter to the Minister of Trade and Industry
  • DPW Lekgotla and adoption of key strategic
    imperatives
  • Increasing DPW contribution to ASGISA / JIPSA,
    (NIMS, NYS, Professional skills audit and Cuban
    experience)
  • Budget Devolution in line with the PFMA ethos of
    transparency and accountability.
  • Maximizing the performance of our assets in
    relation to their value to service delivery

5
Programme PerformanceAsset Management
6
Draft Turn-Around Strategy
  • Revenue generation and cost reduction measures
  • Financing and restructuring
  • Integrated approach to decommissioned and/or
    un-utilised assets
  • Value enhancement
  • Institutional reform and
  • Implementation plan (to be finalised in 2007/08)

7
Pan African Parliament (PAP)
  • Completion of the options analysis and
    identification of Randjesfontein, Midrand as the
    preferred location for PAP
  • Options analysis skills transfer to the
    department through the options analysis process
    by the private sector
  • Approval of the procurement option and budget for
    the PAP by the IMC.
  • Approval of the jury members and technical team
    structures by the IMC
  • The website address is www.papcompetition.co.za .

8
National Infrastructure Maintenance Strategy
(NIMS)
  • This strategy was approved by Cabinet and DPW
    appointed as a lead department and
  • Covers infrastructure owned by State SOE, and
    Municipalities
  • The following institutional structure to manage
    the implementation of the strategy was proposed
  • An institutional framework for the management of
    NIMS comprising political oversight function and
  • A steering committee up whereby key
    infrastructure departments are represented was
    also proposed.

9
Prioritized Capital Works and Planned Maintenance
2006/07
  • For the second consecutive year, DPW rolled out
    prioritized capital works and planned maintenance
    over the MTEF period as opposed to year on year.
  • Also the determining principles and factors in
    the prioritisation of maintenance were reviewed
    in order to make a significant socio-economic
    impact on governments programmes such as
  • EPWP ( Must ask - Why is a Project not linked to
    EPWP?)
  • NYS
  • Project Consolidate
  • ASGISA
  • For monitoring and evaluation purposes, a Planned
    Maintenance Budget Committee (PMBC) was
    established

10
User Asset Management Plans (UAMP)
  • Match the service delivery objectives with
    accommodation
  • Verify the accommodation occupied by the user.
  • Determine functional performance of
    accommodation
  • Determine utilization of accommodation
  • Conduct a gap analysis
  • Determine new accommodation requirements
  • Determine the need for refurbishment or
    reconfiguration of existing accommodation
  • Determine surplus accommodation to be
    relinquished
  • Determine repairs that need to be conducted and
  • Prepare a budget for accommodation occupied by
    the user.

11
Investment Analysis Framework
  • To be used in the evaluation of clients
    proposals for fixed property acquisitions,
    refurbishments, exchanges, demolitions and
    disposals
  • To implement the options analysis process that
    has been developed by the department and the
    National Treasury
  • To provide relevant stakeholders with information
    required for investment analysis process and
  • To provide a clear picture of existing business
    processes.

12
Service Delivery Standards (SDS)
  • The production of the SLAs require the definition
    of SDS. DPW has developed more than 300 SDS that
    serve as a base for the conclusion of the SLAs
    with client departments. These SDS are split into
    head office service standard performance and
    regional offices service standard performance
    include but not limited to
  • Acquisition of fixed property (buying and
    leasing)
  • Disposal of State Owned Property
  • Facilities management
  • Property payments and
  • Utilisation and contracts.

13
Border Control Operational Coordinating Committee
(BCOCC)
  • DPW Chairs the BCOCC Development Committee whose
    value of work is R4bn
  • 43 of the 54 Land Ports of Entry were under
    various repair and maintenance programmes
    including the construction of residential
    accommodation at certain bases
  • ICT Upgrading worth R204 million was spent at
    certain sea, land, and air ports of entry in
    2006/07

14
Conclusion Asset Management
  • In compliance with GIAMA and Strategic Asset
    Management Life Cycle, DPW continuously
    implement
  • NIMS
  • Draft Turnaround Strategy On-Going
    Consultations
  • UAMP
  • AREP (Phase II)
  • SDS (300)
  • PAP 2010.
  • All of these initiatives have been done for the
    first time in managing State immovable property
    portfolio.

15
Operations
16
Purpose and Objectives
  • Execute all operational activities related to
    provision and management of state owned property
    on behalf of government and its
    departments/institutions
  • Align and utilize expenditure to promote BEE and
    influence ownership partners in the property and
    construction industries.
  • Coordinate Service Delivery Improvement Programme
    (Zimisele Give it Your Best programme).
  • Achieve Expanded Public Works Programme goals
    using capital and maintenance budgets.
  • Comply with regulatory and statutory requirements.

17
Achievements
  • Debt reduction by regional offices is improving.
    The outstanding debt was 24 million and has been
    reduced to date to 6 million rands.
  • The design and tender documentation for the
    Foreign Affairs embassies in Addis Ababa, Lesotho
    and Nigeria was completed in January 2006 and
    November 2006 respectively and is in an advanced
    stage of commencement with construction.
  • Draft property management strategy for BEE,
    Poverty alleviation and job creation has been
    developed.
  • The Zimisele call centre for unplanned
    maintenance was implemented in March 2007 at 3
    pilot sites (PE, KBLY, JHB).

18
Achievements
  • In Kimberley the R 35 million pipeline contract
    was completed, using EPWP guidelines.
  • In Mmabatho 6 projects were identified for CIP
    and the contractor moved on site.

19
Challenges
  • BEE participation in the construction and
    property sector.
  • Skills shortage in the built environment
    industry.
  • Registration of professionals in the built
    environment industry.

20
Challenges Legislation/Regulation
  • Special attention must be given to the
    requirement to ensure that all DPW owned
    buildings are complying with the National
    Building Regulations and Building Standards Act,
    regarding facilities for the disabled.
  • The cost to make the DPW buildings compliant is
    roughly estimated at R600 million as it involves
    the installation of lifts in some buildings.

21
Re-Kgabisa Tshwane Programme
22
Purpose and objectives
  • Development of a conceptual framework for long
    term accommodation solutions for government in
    partnership with the city of Tshwane.
  • Improving the standard of physical accommodation
    of national departments head offices in the
    inner city of Tshwane
  • Integrating the RKTP with the City of Tshwane
    Metropolitan Municipality (CTMM) inner city
    development strategies in order to assist CTMM to
    improve the urban environment around government
    accommodation
  • Cost management and quality improvement
  • Promoting governments socio-economic goals
    including BEE

23
Achievements
  • 13 departments needs, location and procument
    strategies have been generated and approved by
    the clients departments.
  • Developed a draft multimodal transport strategy.
    A study tour to South America by CTMM to
    benchmark the Bus Rapid Transit models within the
    RKTP was taken in January 2007.
  • A database of the status of land and building
    management within the inner city was developed
    and has been finalised.

24
Achievements
  • Land identified for the 13 departments is to the
    value of 120 million mainly from propnet
    properties within the inner city.
  • The RKTP branding has grown and became part of
    the citys landscape a tangible proof of the
    growing stature of the programme.
  • Four projects initiated through RKTP are at
    implementation stage by our operations branch.

25
Challenges
  • Capacity problems both in the Department and
    external consultants to understand and implement
    Options Analysis processes have confounded the
    need for structural changes like the creation of
    fully staffed entity to drive the Programme.
  • The viability of the RKTP affects other
    portfolios and therefore there is a growing need
    to involve other Ministries of Transport, Local
    and Provincial Government, Housing and Foreign
    affairs.
  • In turn, the viability of the Programme is
    impacted upon, among others, by the complex and
    slow site acquisition processes as well as the
    ability of the Municipality to fast track
    municipal town planning processes. Also the
    availability of sites around the preferred nodal
    areas remains a key challenge.
  • In line with the precinct development, it is
    advisable that another precinct be considered
    around Marabastad area.

26
NPWP Policy
27
Purpose and Objective
  • Management and regulation of the property and
    construction sectors for transformation, growth
    and development
  • Promotion of good governance in the management of
    public immovable assets - GIAMA.

28
Highlights
  • Draft Charters were submitted to the Minister of
    Trade and Industry for gazetting Construction
    Charter was gazetted in February 2007.
  • Successful facilitation between the private
    sector and graduates of the departmental Military
    Skills Development Programme, for placement and
    academic scholarships.
  • Successful hosting and implementation of the
    maiden annual National Construction Industry
    Development Week campaign August 2006.
  • GIAMA passed by National Assembly 30 March 2007
  • SADC Forum of Public Works Ministers
    successfully launched and hosted April 2006.

29
Challenges
  • With the gazetting of transformation Charters,
    the department needs to align its procurement
    processes to BEE contained in and stipulated by
    Charters.
  • There is a need to establish a value-chain of
    bursary management processes and alignment to
    successfully absorb relevant bursary requests and
    graduates of the Military Skills Development
    Programme.
  • The continued effective functioning of the SADC,
    DPW Forum Need to resuscitate Forum

30
Expanded Public Works Programme
31
Purpose and Objective
  • The EPWP is to create work opportunities (coupled
    with training) for a minimum of one million
    people so that the unemployed and marginalized
    can gain productive employment and work
    experience.

32
Highlights
  • Shift from Co-ordination to strategic leadership
    New Structure approved by the Minister
  • Alignment of EPWP Guidelines to DPW Maintenance
    and Capital Works Programmes
  • Vukuphile Programme Additional allocation to
    roll-out Programme to meet overall target of 3
    000 learnerships
  • More Departments/Public Bodies are now
    participating in the EPWP Created more work
    Opportunities
  • Kamoso Awards launched in February In
    recognition of best performing Public Bodies
  • Additional R4.2bn and R3.2bn to upscale Social
    Sector and access roads, respectively.

33
Highlight
  • Total wages paid amounted to at least R917m
  • At least 6 290 person-years of training and 85
    700 person-years of work had been completed and
    created on EPWP projects
  • 320 694 gross work opportunities (i.e. at least
    316 814 net work opportunities) were created for
    the period under review
  • Approved Plans to initiate NYS.

34
(No Transcript)
35
Challenges
  • Improve the quality of data and reporting by
    public bodies
  • Increase the labour intensity of the projects
  • Improve the training and exit opportunities
  • Mobilize more public bodies to implement the
    programme.

36
Financial Management
37
Expenditure Report DPW
  • The department was allocated R5.63 billion
  • R99 million remained unspent by year-end due to
    delays in site acquisitions of the properties
    identified for the RKTP projects, R68M of which
    has been rolled over with Treasury approval

38
Revenue and Expenditure report of the Trading
Account
  • R3.9 billion revenue generated through the agency
    work of the Trading Account
  • Actual expenditure amounted to R4, 095 billion
    resulting in the deficit of R165 million the
    deficit is as a result of services rendered by
    3rd parties and paid for by the Trading Account,
    but were subsequently recovered from clients
    after year-end

39
Budget Devolution Results
  • For the first time, DPW Annual report, contained
    audited financial statements of the Trading
    Account
  • The Trading Account obtained an unqualified audit
    report from the AG a positive sign of the
    departments stewardship on the funds of its
    clients.

40
Significant Audit Issues
  • Asset Management Furniture Equipment
  • Property register
  • Completeness
  • Valuations
  • Vesting
  • Rental Debtor Management
  • Classification of Maintenance Expenditure
  • Failure to pay service providers within 30 days.

41
Human Resources Management
42
DPW Employment Profile
  • Overall vacancy Rate throughout DPW including
    regions 17 (995)
  • Among critical professional occupations including
    SMS 39 (220)
  • Women (all) 45 (Men 55)
  • African 69
  • Whites (all) 14, (SMS-25 )
  • Coloureds 15
  • Indians 2
  • Disability - 1 (29)
  • Learnership programmes on various occupational
    classes.

43
Strategic Corrective Measures
  • Addressing audit concerns and other matters of
    emphasis through a comprehensive action plan
  • Implementing turn around strategy refocusing the
    mandate and functions of the department
  • Capacitating the organization for increasing
    contribution to ASGISA, JIPSA and service
    delivery
  • Vacancy rates- reduced from gt900 in April to lt400
    currently (DDGs Operations and Corporate
    Services)
  • Cuban experience- replenishing professional
    skills
  • External bursaries launched and internship
    programme in place
  • Built environment and industry related skills
    improvement drive
  • NIMS operationalised and EPWP up scaled
  • Transformation charters

44
Strategic Corrective Measures
  • Improving corporate governance
  • Anti fraud and corruption measures-known cases
  • Cooperation with Public Entities, Provinces and
    Public Representative bodies
  • Devolution of budgets and Trading Account
  • GIAMA implementation
  • Audit and Risk Management committee

45
Conclusion
  • Audit opinion on DPW a concern, Trading Account a
    positive start
  • EPWP exceeding targets
  • Asset register- work in progress, end in sight
    (intersite and servcon)
  • Alignment of RKTP and Operations
  • HR Retention strategy
  • Property Transformation Charter- gazetted.