Title: Stage III: Project Execution and Control


1
Stage III Project Execution and Control
  • Earned Value Analysis
  • B Chapter 8 pages 10-13
  • B Chapter 12 the entire chapter

2
Recitation
  • What does RAM stand for in the context of HR
    Management?
  • What was the name of the guy who categorized all
    job satisfaction factors into two categories?
  • What were those two categories?

3
Freeze Requirements???
  • What are the PROS?
  • What are the CONS?

4
Freeze those requirements!!
  • Late-project creeping requirements are the most
    common source of cost and schedule overruns
  • Late-project creeping requirements are a major
    factor in project cancellations

5
Rather than freezing, use some kind of change
control system
  • Allows for some changes to happen, depending upon
    contractual considerations
  • Allows for the system to reject some proposed
    changes
  • Use of a CCB is considered a modern BEST PRACTICE

6
Forces pushing for late-project requirements
change
  • Competition intros new version of competitive
    product with unanticipated KILLER features
  • New work is undiscovered late in the project
  • A Wouldnt It be Great if scenario happens
  • End-users want changes because they now know more
    about their requirements than they did 18 months
    ago
  • Developers want changes because they have a great
    emotional and intellectual investment in all of
    the systems details

7
Processes utilized in Stage III
  • Integration management
  • Project plan execution integrated change control
  • Scope management
  • Scope change control
  • Time management
  • Schedule control
  • Cost management
  • Cost control
  • Quality management
  • Quality control

8
Processes utilized in Stage III, Continued
  • Communication management
  • Information distribution, Performance reporting
  • Risk management
  • Risk monitoring and control
  • Procurement management
  • Contract administration

9
Controlling Changes to the Project Schedule
  • Perform reality checks on schedules
  • Allow for contingencies??
  • Dont plan for everyone to work at 100 capacity
    all the time
  • Hold progress meetings with stakeholders and be
    clear and honest in communicating schedule issues

10
Execution
  • Focus and leadership are keys to success in
    execution
  • Poor execution leads to losses in the business
    world just as it does in sports

11
Factors leading to poor Execution
  • Multitaskingdoing several things at once
  • Procrastination (student syndrome)putting things
    off until the last minute
  • Others we will discuss later

12
Multitasking
Task A
Task B
Task C
Task D
A finishes
A
B
C
D
A
B
C
D
A
B
C
D
A
B
C
D
A finishes
B finishes
13
Cost Control
  • Project cost control includes
  • monitoring cost performance
  • ensuring that only appropriate project changes
    are included in a revised cost baseline
  • informing project stakeholders of authorized
    changes to the project that will affect costs
  • Earned value analysis is an important tool for
    cost control

14
Earned Value Analysis (EVA)
  • EVA is a project performance measurement
    technique that integrates scope, time, and cost
    data
  • Given a baseline (original plan plus approved
    changes), you can determine how well the project
    is meeting its goals with EVA
  • You must enter actual information periodically to
    use EVA. Figure 6-1 shows a sample form for
    collecting information

15
Figure 6-1. Cost Control Input Form for Business
Systems Replacement Project
16
Earned Value Analysis Terms
  • Budgeted cost of work performed (BCWP), also
    called earned value, is the percentage of work
    actually completed multiplied by the budget for
    the activity
  • Budgeted cost of work scheduled (BCWS), also
    called planned value, is that portion of the
    approved total cost estimate planned to be spent
    on an activity during a given period
  • Actual cost of work performed (ACWP), also called
    actual cost, are the total direct and indirect
    costs incurred in accomplishing work on an
    activity during a given period

17
Earned Value analysis--EVA
  • Earned value Budgeted Cost of Work Performed
    (BCWP)
  • Planned value Budgeted Cost of Work Scheduled
    (BCWS), and
  • Actual Cost Actual Cost of Work Performed
    (ACWP)
  • When you complete an activity, you earn the
    budgeted value of that activity

18
Schedule Variance (SV)
  • Defined as the difference between the budgeted
    cost of work performed and the budgeted cost of
    work scheduled
  • BCWP - BCWS
  • Indicates the deviation between the work content
    performed and the work content scheduled for the
    control period

19
Cost Variance (CV)
  • Defined as the difference between the budgeted
    cost of work performed and the actual cost of
    work performed
  • BCWP - ACWP
  • A positive CV indicates a lower actual cost than
    budgeted for the control period, while a negative
    CV indicates a cost overrun

20
Schedule Performance Index (SPI)
  • Defined as the ratio BCWP/BCWS
  • A value close to 1 indicates an activity that is
    on schedule
  • Values greater than 1 suggest the activity is
    ahead of schedule
  • Values less than 1 indicate a schedule overrun

21
Cost Performance Index (CPI)
  • Defined as the ratio BCWP/ACWP
  • A value close to 1 indicates an activity that is
    on budget
  • Values greater than 1 suggest the activity is
    below budget
  • Values less than 1 indicate a budget overrun

22
Table 6-7. Earned Value Formulas
23
Table 6-6. Earned Value Calculations for One
Activity After Week One
24
Rules of Thumb for EVA Numbers
  • Negative numbers for cost and schedule variance
    indicate problems in those areas. The project is
    costing more than planned or taking longer than
    planned
  • CPI and SPI less than 100 indicate problems

25
Figure 6-2. Earned Value Calculations for a
One-Year Project After Five Months
26
In the Figure above
  • Budget at Completion BAC original budget at
    the planned completion date
  • Time at Completion TAC original completion
    time
  • In the figure above, 100,000 in month 12
  • Estimate at completion EAC BAC/CPI
  • Estimate at completion 100,000/.83 120,455
  • Estimated time to complete ETAC TAC/SPI
  • Estimated time to complete 12/.96 12.55 mos.

27
Why Earned Value Analysis??
  • You cant tell what your true cost variance is
    because you dont know where you are relative to
    schedule
  • Suppose you are behind schedule but also you have
    spent less than what the schedule has called for.
    Are you really under budget?

28
Updating cost estimates
  • BAC Budget at completion total budget of the
    project activities based on the original project
    plan
  • Assuming the original budget (the BAC) was
    200,000 and the CPI is 1.12, what is EAC?
  • EAC BAC / CPI 200,000 / 1.12
  • 178,571

29
Updating schedule estimates
  • TAC Time at completion total time required to
    complete the schedule
  • ETAC Estimated (revised) time to complete
  • Assuming the TAC was 12 months what is the ETAC?
  • ETAC TAC / SPI 12 / .77
  • 15.6 months
  • Project will be delayed almost 4 months

30
Updating, Contd
  • WR Work Remaining budgeted cost of the work
    not yet accomplished by the end of the reporting
    period
  • WR BAC - BCWP
  • ETC updated estimate of the cost of work
    remaining COST(WR)
  • EAC updated estimate of the total project cost
    ACWP ETC

31
Figure 6-3. Earned Value Chart for Project After
Five Months
EAC
32
Using Software to Assist in Cost Management
  • Spreadsheets are a common tool for resource
    planning, cost estimating, cost budgeting, and
    cost control
  • Many companies use more sophisticated and
    centralized financial applications software for
    cost information
  • Project management software has many cost-related
    features

33
Using MS Project for Execution Control
  • First, make certain your project plan is complete
    and final
  • Second, save it as a baseline
  • Begin entering actual information
  • Actual costs
  • Percentage complete

34
Tracking MS Project will track
  • Task start dates
  • Task finish dates
  • Task duration
  • Task cost work
  • Percentage of task that is complete

35
Getting Earned Value Data Visible
  • You can go to view and replace the entry table
    with the Earned Value table
  • Or, you can enter the earned value columns into
    your existing table through the Insert Column
    facility.
  • The columns are BCWP, BCWS, ACWP, CV, SC, SPI,
    CPI, etc.
  • You can also request the Tracking Gantt Chart off
    the LHS side of MS Project

36
Entering actual start Finish dates for a task
  • On the view bar, click Gantt chart
  • In the task name field select the task to update
  • On the Tools menu, point to tracking and click
    Update Tasks
  • Under Actual, type the dates in the Start and
    Finish boxes

37
Indicating progress on a task as a percentage
  • In the task name field of the Gantt Chart
  • Double clickthis brings up the task information
    sheet
  • Select the general tab
  • In the percentage complete box type a whole
    number between 0 and 100

38
Entering actual costs for a resource assignment
  • On the Tools menu, click options, then click the
    calculation tab
  • Clear the Actual costs are always calculated by
    MS Project check box
  • Click OK
  • On the view bar, click Task usage
  • On the view menu, point to the Table, and click
    Tracking
  • Drag the divider bar to the right to view the
    Activity Cost field
  • In the activity cost field, type the actual cost
    for the assignment for which you want to update
    costs

39
(No Transcript)
40
(No Transcript)
41
(No Transcript)
42
Recitation
  • What are two of the four Myers/Briggs dimensions?
  • What are the other two?
  • To what Myers/Briggs category do most IT
    professionals belong?
  • Who is the motivation guru?
  • What are his five levels?
  • Who gave us Theory X and Theory Y??

43