Title: Briefing for Risk Analysis for Dam Safety Field Review Group
1Probability of Failure for Gates, Equipment and
Early Warning Systems
- Briefing for Risk Analysis for Dam Safety Field
Review Group - 19 March 2002
- Stuart Foltz
- ERDC-CERL
2Probability of Failure for Gates, Equipment and
Early Warning Systems
- Briefing Topics
- Dam Gate Risk Overview
- Activities
- Products
- Funding
3Probability of Failure of Gates
- Risk analysis studies
- Gates were not part of Alamo Dam risk analysis
- Gates were not part of Hills Creek risk analysis
- Bureau of Reclamation doesnt focus on gates
- Corps (dam safety) focuses on seismic, PMF, and
spillway erosion
- Huntington portfolio includes a gate focus
- Ft Worth portfolio includes a gate focus
4Probability of Failure of Gates
- Common perception
- Failure of a gate presents a much smaller risk
than dam failure. - Based on risk analyses reported by Dr. David
Bowles (Utah State University) - Smaller, more frequent events can have greater
cumulative consequences than large events
5Probability of Failure of Gates
- Unknowns
- Anchorage deterioration
- LRL, NWD
- Trunnion friction
- Folsom
- ASCE, USCOLD,
- ICODS
- NWD (Omaha, Kansas City), Table Rock
- Untested gates
- No load
- Not operated under load
- Operational issues
6Probability of Failure of Gates
- August 2001 gate inspections by Jack Lewin and
Greg Ballard - Hills Creek (Portland)
- Ft.Worth
- Huntington
- Inspection and thorough review of gate function,
performance, and operations.
7Probability of Failure of Gates
- Issues raised by Lewin and Ballard
- Emergency Preparedness of Project personnel
- Knowledge of flood charts
- Access to project by District personnel
- Gate exercising
- Maintenance of gates
- Incident records
8Probability of Failure of Gates
- Consultant visits (continued)
- Many gates are in need of repairs and
rehabilitation. - Deterioration beyond what is deemed acceptable by
the consultants - Equipment below code and accepted standards
- Questioned readiness of backup power
- Consultants noted instances where small repairs
necessary for reliable gate operation were
delayed or not performed
9Probability of Failure of Gates
- Consultant visits (continued)
- You may like to draw Stuart's attention to the
methodology of creating a condition index as used
by Scottish Hydro (now Scottish Southern
Energy).
10Probability of Failure of Gates
Huntington Portfolio Priorities
11Probability of Failure of Gates
- FY02 milestones
- Identify critical components and generic events
lists - Assess gate incident databases
- Summarize EWS survey results
12Probability of Failure of Gates
- Cal. State Univ. Fullerton (CSF) Research
Effort - Develop generic lists of gate related faults and
events (phase III) - Develop a criticality index to help identify the
risk associated with those events
13Spillway Condition Evaluation
- Hydro Quebec, Bureau of Reclamation, Manitoba
Hydro, Ontario Hydro - Condition evaluation procedures for
- Lift gates, Tainter gates
- Mechanical equipment
- Electrical equipment
- Operation
- Develop procedure to evaluate relative risk of
gate related infrastructure components - As of FY01, this effort is funded outside this
work unit.
14Failure of Electrical/Mechanical Gate Components
- http//www.mvr.usace.army.mil/failuredata
- Collecting data on performance of components that
fail (Censored data) - We need to determine how to uncensor the data to
account for all the components that never failed
or were replaced before failure.
15Probability of Failure of Gates
- Failure data
- Rock Island web site
- NPDP data
- USACE tainter gate problems
- European data
- Inventory data
- EWS survey
- USBR
16Probability of Failure of Gates
- Early Warning Systems
- Components
- Flood prediction
- Flood management
- Emergency identification
- Emergency notification
- Evacuation
17Probability of Failure of Gates
- Early Warning Systems
- What impact does EWS have on risk?
- Are there common deficiencies?
- What are the mitigation methods?
- Can EWS improvements be used to mitigate other
risks?
18Probability of Failure of Gates
- Three primary areas of concern for EWS
- 1 - Readiness of local authorities
- 2 - Testing of EWS
- 3 - Access vulnerabilities during flood events
- ? Are we over-confident in our abilities?
- Survey did not evaluate security or the impact of
deferred maintenance on dam safety
19Products FY02
- Conference presentations and paper
- ICODS Dam Safety Workshop (Feb 2002)
- Survey of USACE Early Warning Systems
- Portfolio assessment
- Review of gate assessment sub-contractor report
- Continuing process
20Products FY02(Incomplete)
- EWS Survey
- Combine with FY00 USBR survey report
- Publish report
- Criticality Analysis and Fault tree report
- Revise, expand, and improve draft report
- Draft inspection procedure for gate operational
adequacy and electrical operating equipment - (no longer funded by this work unit)
21Probability of Failure for Gates, Equipment and
Early Warning Systems
- Milestones FY03
- Complete framework for simplified comparison of
relative risk - Complete risk criteria for inspection
maintenance scenarios - Summarize and report existing gate failure data
22Funding