Title: DO Timeline
1DO Timeline
2000
2001
J
F M A M J J A S
O N D J F M
D
ICD
CFT install/hookup
SMT install/ hookup
Roll in
Remove shield wall
FPS
1/2 VLPCs installed
All VLPCs installed
Beam-ready
Lum (L0)
Platform moves
Install silicon front-end
Install final CFT electronics
1st CFT crate operational
Hookup ECS
Run II begins Mar 1, 2001
Install/checkout CAL BLS
Waveguide production
ECN cosmics
CC cosmics
Forward m MDT pixel planes install/survey (AB)
End toroids installed
Forward m MDT pixel planes install/survey (C)
Assemble/install/ align EMC
Cosmic Ray Commissioning
Phase II Fiber tracker, trigger,
preshowers, VLPCs, CTT, forward muon
Phase III Full Cosmic Ray Run
(add TRIG, SMT, CAL)
Phase I Central muon, DAQ, RECO,
trigger, silicon front-end
2D0 Commissioning Timeline Commissioning/Integratio
n Goals
2000
2001
J
F M A M J J A S
O N D J F M
D
Forward muon C-layer MDTs/pixels
installed/commissioned
Half of CFT, CPS hooked up, checked out
Silicon front-end installed/commissioned
Roll in
Beam-ready
Forward muon AB layer MDTs/pixels
installed/commissioned
DAQ/online system running in user mode
Run II begins Mar 1, 2001
SMT, CAL fully added to commissioning chain,
exercise full triggering with all major systems
Integration Goal 1 dual muon crates,
initial muon triggering/filtering, ship data to
farm, run reconstruction, online event display
Integration Goal 2 Initial triggering on L1
CFT/CPS, begin linking tracks in CFT/CPS/CMuon,
begin Level 2 trigger integration
Integration Goal 4 Full detector in
steady-state Cosmic Ray Commissioning
Integration Goal 3 Add Central
Calorimeter to commissioning stream, most major
systems being commissioned
Begin full central muon system, integrate Level 2
muon trigger at DAB test stand
3Current Detector ConfigurationDecember, 1999
- South calorimeter on sidewalk
- Run 1 Central Tracking removed
- End toroids on sidewalk, Run 1 detectors (PDTs)
removed - Central iron in open position to allow access
- Solenoid, Central Preshower installed in central
bore - Shield wall up
- Hi-Bay clear for staging, other work in Assembly
Hall
4Current Detector ConfigurationDecember, 1999
- End irons prepared for mounting A- and B-layer
detectors (MDTs, pixels) on faces - Most of Central Muon PDTs, A-f, cosmic cap
installed - Commissioning Level 1 trigger, muon system,
online, silicon front-end, solenoid
5Current Detector ConfigurationPhase I
- A-layer MDTs, Pixels being mounted, surveyed onto
faces of end irons - C-layer truss and shielding has arrived in
Hi-Bay, being dressed - Remainder of detector remains open for access
6Current Detector Configuration
- Commissioning continues, using Central Muon as
prototype system - Multi-crate readout of full central muon system
- Event monitoring, crate control, steady DAQ
running, filtering - Exercise reconstruction, online event display (on
cosmic ray muons)
7Forward Muon B-Layer InstallationMay-June, 2000
- A-layer planes installed
- B-layer MDTs, Pixels being mounted, surveyed onto
faces of end irons - C-layer trusses and shielding continue to be
dressed in Hi-Bay
8Forward Muon B-Layer InstallationMay-June, 2000
- End irons moved toward center of Assembly Pit to
allow access for B-layer installation/surveying - Commissioning continues
9Install Fiber Tracker in SolenoidJune, 2000
- Fiber Tracker being installed in central bore
- A- and B-layer detectors installed on end irons
- B-layers Pixels open to allow access for
hookup/commissioning - Commission Fiber Tracker (and Silicon) as they
arrive
10Install Fiber Tracker in SolenoidMay, 2000
- Fiber Tracker Cart/I-Beam system lowered into
gap between South End Calorimeter and Central
Calorimeter - Rolled into solenoid bore along I-Beam
Cart System
Fiber Tracker
11Move Platform West, Pick Up End IronsNovember
3-15, 2000
- Silicon and Fiber Tracker both installed
- South End Calorimeter back in place on platform
- Platform moves west to pick up two end irons, now
loaded with A- and B-layer detectors - C-layer MDTs and Pixels installed and surveyed
onto trusses in Hi-Bay, ready to move down to
sidewalk
12Move Platform West, Pick Up End IronsNovember
3-15, 2000
- Detector buttoned up during move central iron,
calorimeters closed - A- and B-layer detector planes shut
- No commissioning during this period (detector
disconnected from services) - Movable Counting House moves with detector during
pick up
13Platform Returns to East Position Beginning
Phase II
- Detector returns to east position with end irons
installed - Central irons, calorimeters in open position
- Ready for trusses to be brought down to sidewalk
- Commissioning resumes
- gradual integration of all detectors for Cosmic
Ray Commissioning Silicon, Fiber Tracker,
Calorimeters, Central and Forward Muons, Trigger
14North EMC Truss Moves to North SidewalkNovember
20-28, 1999
- North C-layer truss, with MDTs and Pixels
mounted, moves to north sidewalk - End irons, calorimeters closed to allow clearance
to shield wall - Central irons open
- EMCs, shielding re-assembled on sidewalk to
prepare for rolling in
15EMCs Installed in Collision Hall December 11,
2000 - January 11, 2001
- Shield wall is broken down, moved to now free
space in Hi-Bay - North and South C-layer trusses/shields, having
been assembled on sidewalk, rolled into Collision
Hall - surveyed into place - Detector will be rolled into place to meet trusses
16EMCs Installed in Collision Hall
- Full Cosmic Ray Commissioning of all systems
continues during most of this period - End irons, calorimeters can be opened for access
17Detector Rolled in and Hooked UpFebruary 6, 2001
- Full detector rolled in to final closed position
hooked up, ready for beam - Shield wall back up
- Movable Counting House travels with detector,
cable bridge down - Commissioning with cosmic rays will continue
until beam is delivered (March 1, 2001)
18Access to Detector in Collision Hall
Closed Position - Data-Taking
Open Position - Detector Access
North B-layer pixels open
North end iron closed
South calorimeter open
South end iron open
Shielding retracted
19Detector Rolled In, Hooked UpPhase III
- Detector installed in compact space
- Access to internal tracking detectors, end muon
detector planes must be carefully coordinated
20South EMC Truss Moves to South SidewalkNovember
29- December 5, 1999
- South C-layer truss moves to south sidewalk
- EMCs, shielding re-assembled on sidewalk to
prepare for rolling in
21South EMC Truss Moves to South SidewalkNovember
29- December 5, 1999
- South C-layer truss moves to south sidewalk in
two pieces, reassembled - Preparing to take down shield wall for roll in
22The DØ Upgrade Tracking System
Charged Particle Momentum Resolution ?pT/pT 5
_at_ pT 10 GeV/c
23Management of D0 detector upgrade for Run II
24(No Transcript)