Title: Drilled Shaft Construction Issues in Caving Ground and Rock Sockets
1Drilled Shaft Construction Issues in Caving
Ground and Rock Sockets
Case Histories on Drilled Shaft Projects Designed
for Seismic and Lateral Loads. A Contractors
Perspective Solutions Offered for Improvements
on Design and Means and Methods to Produce a More
Constructible Project PRESENTED BY TERRY
TUCKER President, Malcolm Drilling Company,
Inc. www.malcolmdrilling.com
2- Drilled Shaft Construction Issues in Caving
Ground and Rock Sockets - Methods to control and prevent caving
- Designs with constructability issues
3Drilled Shaft Construction Issues in Caving
Ground and Rock Sockets
4Caving Soil and Rock Sockets
- Solutions
- Slurry Head
- Drill Casing
- Temporary casing withdrawn during concrete
placement - Permanent casing left in place during concrete
placement
5Drilled Shaft Construction Issues in Caving
Ground and Rock Sockets
- Slurry Head
- Economical Solution
- Can be used with Conventional Drill Equipment
- Higher Production
- Fast drill rates possible
- Pouring shafts could also be completed quickly
- Care must be taken to ensure integrity of shaft
- Choosing the right product
- Must monitor properties of slurry Density, sand
content, etc. - Fluid Exchange is recommended
- Replace dirty slurry with slurry that is free of
suspended solids
6Drilled Shaft Construction Issues in Caving
Ground and Rock Sockets
7Drilled Shaft Construction Issues in Caving
Ground and Rock Sockets
8Drilled Shaft Construction Issues in Caving
Ground and Rock Sockets
9Drilled Shaft Construction Issues in Caving
Ground and Rock Sockets
- Slurry Head
- Disposal
- Calculated Risk
- Factors such as soil conditions, groundwater
level, surcharges from equipment and roadways
must be considered when using a drill slurry - Effectiveness of slurry diminishes as hole
diameter increases - Stability of shaft may be compromised by small
changes to slurry head - Potential Problems
- Increased concrete take
- Increased time cleaning out shaft
- Soil and rock intrusions into shaft / caving
soils - Sinkholes resulting in unsafe conditions
10Drilled Shaft Construction Issues in Caving
Ground and Rock Sockets
Use of a drill slurry is typically the fastest,
most economic solution to caving ground. However,
as conditions become more difficult there is a
higher chance of shaft defects. Some soils and
rock can be impossible to keep open with a drill
slurry (i.e. sloped, fractured rock with lenses
of rock decomposed to a silty clay)
11Drilled Shaft Construction Issues in Caving
Ground and Rock Sockets
- Temporary/Permanent Casing
- Benefits and Drawbacks
- Installation Methods of casing
- Telescoping / Freefall Method
- Vibratory method
- Rotational (vibration free) method
12Drilled Shaft Construction Issues in Caving
Ground and Rock Sockets
-
- Advantages of Temporary Casing
- Better chance of achieving a dry hole
- Generally only a water head is required with full
depth casing (no mineral or synthetic slurry
required) - Mechanical control of substrata materials,
removing the potential for caving during shaft
construction, specifically during concrete
placement - Shaft can remain open for extended construction
periods during the removal if obstructions are
encountered or during drilling rock sockets. - Positive control to ensure no loss of ground if
contractor is allowed to advance casing to any
depth he deems necessary to control caving.
13Drilled Shaft Construction Issues in Caving
Ground and Rock Sockets
-
- Disadvantages of Temporary Casing
- Slower Drill Rates
- Can easily get into multiple shifts to construct
a single shaft - Extended Concrete Pours
- Pouring concrete while removing casing
- Casing can get stuck
14Drilled Shaft Construction Issues in Caving
Ground and Rock Sockets
- Installation Methods
- Telescoping / Freefall casing
- Does not require specialized equipment
- Quick installation
- May require multiple shaft diameters
(telescoping) - In some situations casing is installed after hole
is drilled - Doesnt eliminate risk of ground loss
- This method has the highest risk of resulting in
a stuck casing
15Drilled Shaft Construction Issues in Caving
Ground and Rock Sockets
- Installation Methods
- Vibratory Methods
- Very Quick installation
- Care must be taken to keep casing straight
- Difficulty going through hard rock, cobbles and
boulders
16Drilled Shaft Construction Issues in Caving
Ground and Rock Sockets
17Drilled Shaft Construction Issues in Caving
Ground and Rock Sockets
- Installation Methods
- Rotational Methods
- Best method for going through varying ground
conditions - Sands, gravels, cobbles, boulders, hard rock,
etc. - Provides best chance for avoiding a shaft defect
- Requires specialized equipment
- Top drive drills
- Rotator / Oscillator
- Slower than conventional methods
18Drilled Shaft Construction Issues in Caving
Ground and Rock Sockets
19Drilled Shaft Construction Issues in Caving
Ground and Rock Sockets
20Drilled Shaft Construction Issues in Caving
Ground and Rock Sockets
21Drilled Shaft Construction Issues in Caving
Ground and Rock Sockets
22Drilled Shaft Construction Issues in Caving
Ground and Rock Sockets
- Temporary Vs. Permanent Casing
- Temporary Casing Flexible
- Case as much or as little as needed
- Permanent Casing Rigid
- Becomes an obstacle if there is caving below its
tip - Care should be taken if a Permanent Casing is
specified to prevent caving, an alternative to
use temporary casing should also be specified.
23Installation of Permanent Casing
24Drilled Shaft Construction Issues in Caving
Ground and Rock Sockets
-
- A. Problem Zone Transition from Drilled Shaft to
above Grade Column - Design Approaches Used By Various Designers
- One size column/drilled shaft with pour joint at
grade. - Embedded column steel with lap length greater
than 15 feet, with pour joint allowed at bottom
of column steel or at grade. - Reduced column size transitioned over 10 feet in
top of drilled shaft. - Pour Joint allowed at bottom of column steel or
at grade. - Alternate Design Approaches by Designers
- Transition with a pile cap or cap beam.
- Transition with a pin connection at top of
drilled shaft
25Drilled Shaft Construction Issues in Caving
Ground and Rock Sockets
- Constructability issues with these design
approaches - Single size solution (commonly used by Caltrans
and other DOTs) - Typically requires full length column steel or a
minimum of 20 feet above grade due to no splice
zone requirements - Makes it difficult to remove temporary casing(s).
- Difficult to maintain cage alignment.
- Difficult to tremie pour concrete
- Difficult to set long rebar cages
26Drilled Shaft Construction Issues in Caving
Ground and Rock Sockets
- Constructability issues with these design
approaches (continued) - Column embedded steel with long lap length
(greater than 15 feet). - Requires either to set a deep permanent casing to
allow for a low construction joint (lap length
with column steel), or double cage (shaft and
column) to be set and poured to grade. - If low cut off is provided with permanent casing,
additional issues with high groundwater table/cut
off below slurry head. - Need for telescoping casing or other means to
allow temporary casing construction below
permanent casing (oversized permanent casing)
27Drilled Shaft Construction Issues in Caving
Ground and Rock Sockets
- Column embedded steel with long lap length
(greater than 15 feet) Cont. - Difficulty of concrete cover between shaft and
column cage within the embed length, specifically
if pour is brought to grade without the use of
permanent casing if not allowed. - Flow of concrete impeded by additional rebar and
inspection pipes. - When Gamma-Gamma testing is used by Caltrans,
they specify an inspection tube (2 diameter)
located as close as 2 from nearest vertical
reinforcement. - Very tight window for 1/2 or 3/8 aggregate
considering horizontal reinforcement is typically
very tight in these embed zones. - Contractor required to repair defects associated
with this issue - Overpouring to achieve sound concrete at cold
joint is problematic. - Lots of chipping!
- In the absence of a construction joint,
remediation of any defective shaft concrete is
extremely difficult in this double cage zone.
28Removing Contaminated Concrete from Top of Pile
29Embedded Column Cage
30Drilled Shaft Construction Issues in Caving
Ground and Rock Sockets
In summary the above described common Caltrans
solutions present the Contractor with many issues
to overcome in order to provide the Owner with an
adequate product. There is a high
potential for many disputes.
31Drilled Shaft Construction Issues in Caving
Ground and Rock Sockets
- Approach using a reduced column size with short
transition (10-12) - Commonly used by WSDOT
- Reduced column size transitioned over 10 feet in
top of drilled shaft. Pour Joint allowed. - Requires an approximately 12 foot permanent
transition casing to remain in ground from grade
to concrete cut off. - This solution works very well for work below the
groundwater table whereby this transition casing
is extended above water levels to act as a
cofferdam - Transition casing can be either oversized to
allow for specified shaft diameter installation
through the inside of the transition casing or,
if sufficient cover is specified (6 inches) then
transition casing could be installed in this
annulus (between the shaft and the potential
temporary casing.
32Plastic Hinging Zone
Casing Shoring
Column to Shaft Connection
Permanent Casing
Stepped Shaft 6 oversize for shafts larger than
5 Dia. 12 oversize for shafts 5 Dia.
smaller.
Temporary Casing
Shaft Terminology
33- Preliminary selection of column size.
- Select minimum shaft size based on column size.
MAXIMUM SHAFT SHORING DIAMETER
Max. Col. Dia. (Shaft Dia.) - 2(Conc.
Cvr.) - 2(Constr. Tol.) - 4(Thickness
Cage) Max. Shaft Shoring Dia. Based on 1-0
min. clr. to column for forming. Therefore, Shaft
Shoring Dia. (Shaft Dia.) 2(1-0 clr.) -
2(Conc. Cvr.) 2.1 Cage Thickness assumes a
11 vert. 4 spiral 2.6 Cage Thickness assumes
a 14 vert. 5 spiral 3.3 Cage Thickness
assumes a 18 vert. 16 spiral Construction
tolerances and concrete cover for shafts are per
WSDOT Special Provisions.
34(No Transcript)
35Slip Casing with Oscillator Method
36Drilled Shaft Construction Issues in Caving
Ground and Rock Sockets
In summary, the above described (WSDOT) solutions
have been successfully used over the last 10
years with excellent results yielding
significantly lower remediation or concrete
defects in the embed zone.
37Drilled Shaft Construction Issues in Caving
Ground and Rock Sockets
- Alternate Design Approach by Various Designers
- Transition with a pile cap or cap beam.
- Easier solution from the perspective of
installation of drilled shafts. - However, this requires special design
considerations and/or potential need for
installation of cofferdams and/or temporary
shoring to install pile caps. - This method is particularly useful for bents
where loads require multiple piers. - Transition with a pin connection at top of
drilled shaft - Requires different design approach generally
columns are pinned at the top of the drilled
shaft and rigidly connected to the bridge
structure. - Typically limited to columns that are of average
length less than 30 feet. - Setting of pin connection can be problematic
38Drilled Shaft Construction Issues in Caving
Ground and Rock Sockets
In summary the above described design
approaches may work well, but require additional
design consideration in the event of seismic
loading, and may not work well where site
constraints limit the use of cofferdams and
temporary shoring.
39Drilled Shaft Construction Issues in Caving
Ground and Rock Sockets
- Construction Considerations for Drilled Shafts
with Rock Sockets - Problem Zone -Transition from overburden to
rock socket. - Is overlying material prone to caving?
- Where does the rock socket start? Is there
potential for boulders overlaying rock and/or
inclined rock surface (sloped rock). What is
bedrock? - Log of test borings
- What do the test borings indicate for materials
to be encountered in the transition between
overburden and the rock socket.
40Drilled Shaft Construction Issues in Caving
Ground and Rock Sockets
- Problem Zone -Transition from overburden to rock
socket (continued) - Rock and soil classifications
- If the rock behaves or has the consistency of
soil it should not only be classified as a soil,
but also treated as a soil from a
constructability standpoint. - If the potential for caving in the overburden and
weathered rock exists, consider specifying the
use of temporary casing
41Drilled Shaft Construction Issues in Caving
Ground and Rock Sockets
- Construction Considerations for Drilled Shafts
with Rock Sockets - Problem Zone - Transition from overburden to rock
socket. (continued) - Example of unconstructable specification(s)
- Provide permanent casing (in intimate contact
with ground) - Do not disturb surrounding soil
- Install permanent casing to a specified bedrock
tip elevation regardless of material encountered
at tip of casing, either too soft (caving) or too
hard (continuation of casing through hard rock) - Specifying minimum casing diameter that does not
provide clearance to step down casing if
required. - Requirement that permanent casing be installed
prior to construction of rock socket - Installation of seal concrete at the bottom of
the casing for dewatering purposes
42Drilled Shaft Construction Issues in Caving
Ground and Rock Sockets
- Construction Considerations for Drilled Shafts
with Rock Sockets (continued) - Rock Socket Construction
- Provide sufficient rock data immediately adjacent
to the shaft, or at the location of the drilled
shaft - Consider the implementation of a full size test
shaft. (ADOT) - Can be done in conjunction with a full scale load
test - Test shafts with various agencies and owners has
resulted in a reduction of the frictional
transfer area of approximately 25 - Continuous coring of rock samples
- Proper classification of rock, including the
transition from overburden to the rock socket.
Note no ambiguous geologic descriptors in lieu
of proper geotechnical terms, but accurate
descriptions as to how the rock will behave
during construction.
43Drilled Shaft Construction Issues in Caving
Ground and Rock Sockets
- Construction Considerations for Drilled Shafts
with Rock Sockets - Rock Socket Construction (continued)
- Rock Strength as a minimum, one compressive
break every 5 feet of core length. - Unconfined Compressive strength test only.
- Provide clear and concise reference as to what
logging methods were used. - Consider and evaluate potential of slip surfaces
as causing mass caving (block failures for large
diameter shafts 5 foot diameter and greater). - Provide onsite geotechnical engineer to determine
actual rock contact may not be required if
sufficient data is provided for each shaft
location - Drilling equipment should not be used a guideline
to determine the quality or strength of the rock
(refusal or too soft rock issues)
44Drilled Shaft Construction Issues in Caving
Ground and Rock Sockets
- Construction Considerations for Drilled Shafts
with Rock Sockets - Rock Socket Construction ( continued)
- Provide an in-depth constructability review
taking into consideration the actual conditions
encountered during the site investigation. - Blanket disclaimers as to
- The potential of caving or need of temporary
casing. - High water inflow rates, if not verified
- However it should be evaluated that 6 or 8 foot
shaft will behave differently as compared to a
2.5 diameter cored hole - Provide mechanism under the contract to shorten
or extend pile length if certain defined strength
parameters are not encountered or encountered at
an elevation other than anticipated
45Drilled Shaft Construction Issues in Caving
Ground and Rock Sockets
- Construction Considerations for Drilled Shafts
with Rock Sockets - Rock Socket Construction (continued)
- Consider the use of end bearing capacity in rock
sockets, by specifying more strict slurry clean
out methods or values, e.g. maximum sand content
0.5, full replacement of drill slurry prior to
concrete placement, use of S.I.D. (shaft
inspection device camera)
46Drilled Shaft Construction Issues in Caving
Ground and Rock Sockets
47Drilled Shaft Construction Issues in Caving
Ground and Rock Sockets
- Construction Considerations for Drilled Shafts
with Rock Sockets (continued) - In Summary
- It is absolutely imperative to perform a state of
the art soils investigation to provide the best
information to the Engineer and the Contractor to
successfully construct the deep foundations as
designed. - Unfortunately, soils are made by nature and not
by man, and the products of nature are always
complex Natural soil is never uniform. Its
properties change from point to point while our
knowledge of its properties are limited to those
few spots at which the samples have been
collected (Karl Terzaghi) - However, regardless of the extensiveness of the
geotechnical investigation. a differing site
condition still may be encountered. A thorough
subsurface investigation will provide the best
opportunity to minimize the risk of cost and time
overruns to both the Contractor and the Owner.
48Drilled Shaft Construction Issues in Caving
Ground and Rock Sockets
Closure Details of shaft / column transitions
and construction problems related to caving
ground and rock sockets have been presented for
consideration to achieve a successful completion
of drilled shafts in this very difficult
application. Big steps have been made in the
construction of deep foundations over the past 10
years. A new generation of very powerful top
drive hydraulic drill units is now in use
throughout the United States. Additionally, big
vibratory hammers, rotators and oscillators have
proven their effectiveness in caving and
difficult ground conditions.
49Drilled Shaft Construction Issues in Caving
Ground and Rock Sockets
- It benefits all members involved in the design
and construction of these specialty deep
foundations to become familiar with these new
types of equipment. - Often, a poorly written specification is the
biggest hurdle to the successful completion of a
deep foundation drilling project.