Title: Fundamentals of Project Management Part 1d
1Fundamentals of Project Management Part 1d
- APEGGA Annual Conference
- April 24 25, 03
- Dr. George F. Jergeas PEng.
- University of Calgary
2Schedule
- Day 1a
- Introduction
- 5-Step PM
- Planning and definition
- Day 1b
- Estimating cost and time
- Video
- Organize project team
- Selecting PM and team
- Effective teams
- Day 2 c
- Project procurement
- Bidding process
- Building sustaining project team
- Contract administration
- Day 2 d
- Schedule control
- Cost control
- Project Close-out
- Claims and disputes
3Step 4. Control the Project
45-Step Project Management PLANNING
IMPLEMENTATION
CONTROL
ORGANIZE
DEFINE
PLAN
CLOSE
Identify project activities
State the Problem
Determine Personnel Needs
Define Management Style
Obtain Client Acceptance Install Deliverables
and Commissioning Document the Project Issue
Final Report Conduct Post- Implementation Audit
Identify Project Goal
Estimate time and cost
Recruit Project Manger
Establish Control Tools
List the Objectives
Prepare Status Reports Review
Project Schedule, cost, team report Issue
Change Orders
Recruit Project Team
Quality and Communication management
Determine Preliminary Resources
Organize Project Team Bidding
Identify Risks and stakeholders Success
criteria
Assign Work Packages
Write Project Proposal
Decision
Project charter WBS
Recruit Criteria
Variance Reports Final Report
Project network
Define Work packages Status Reports
Audit Reports
Project proposal Assign Work
Packages
5Schedule Control
6Schedule Control
- Use
- Regularly update Gantt chart
- Frequency
- Performance reports, change requests, time
management plan, corrective action, lessons
learned - Control techniques e.g. meetings, 11
7Schedule Control Steps
- To Control Schedule
- Incorporate any additional tasks and revise
duration estimates - Add activities that were overlooked when the
original plan was developed - Add new activities due to unanticipated events
- Analyse the schedule to determine which areas may
need corrective action
8Approaches to Schedule Control
- Decide what specific corrective actions should be
taken - Revisit the plan to incorporate the chosen
corrective actions - Recalculate the schedule to evaluate the effects
of the planned corrective actions - If the planned corrective actions do not result
in an acceptable schedule, repeat the previous
steps - A new baseline plan is established and used as
the benchmark for comparison - Obtain client approval before proceeding
9Approaches to Schedule Control
- Each time a schedule is recalculated
- Identify the critical path
- Identify any activities that have a negative
slack - Compare paths where slippage have occurred (Slack
got worse) - Apply acceleration to the paths with negative
slack - The most negative slack should be given top
priority - Focus on activities that are in progress or to be
started in the immediate future - Focus on activities that have long duration
estimates
10Acceleration
- To reduce schedule
- Apply more resources to speed up an activity
- Add more people
- Increase hours per day or increase days per week
- Assign person(s) with greater expertise or more
experience - Reduce the scope or eliminate the activity if
possible - Increase productivity through improved methods or
technology
11Acceleration
- Trade-off in the form of an increase in costs or
a reduction in scope - This could jeopardise elements of the overall
project objective scope, budget, schedule,
and/or quality - There may be a dispute over who should absorb any
increased cost to accelerate - Bonus provision if project is completed early
- Liquidated damages
- Project meetings are a good forum for addressing
schedule control issues
12Cost Control
13Cost Control System (Earned Value)
- Any cost control system should enable a project
manager to observe current perfomance levels,
compare them with budget levels and institute
corrective actions to keep performance, and
ultimately costs, within acceptable range
14Elements of Effective Cost Control System
- Observation
- Comparison of observation with budget
- Corrective action to take if necessary
- Can also serve as
- A basis for a productivity improvement program
- A measure of productivity loss caused by adverse
factors and changed conditions such as winter
work, acceleration, design changes, etc.
15Cost Control System
- Compares actual man-hours expended to earned
hours - Actual man-hours come from contractors daily
time sheets - Earned hours are calculated by multiplying the
completed quantities during a period by estimated
man-hours per unit quantity - See figure following as an example
16Labour Productivity Report
17Budget
Money
Time Now
Actual Expenditure
Cost overrun
Earned Value
Time
Delay
18Money
Budget
Ahead of schedule
Earned Value
Making Money
Actual
Time
19Conclusion
- You can draw immediate attention to significant
deviations from what was planned - Indicate what corrective action is necessary and
by whom -
- Dependent on accurate reporting and correct
allocation of hours expended
20Step 5 Close the Project
215-Step Project Management PLANNING
IMPLEMENTATION
CONTROL
ORGANIZE
DEFINE
PLAN
CLOSE
Identify project activities
State the Problem
Determine Personnel Needs
Define Management Style
Obtain Client Acceptance Install Deliverables
and Commissioning Document the Project Issue
Final Report Conduct Post- Implementation Audit
Identify Project Goal
Estimate time and cost
Recruit Project Manger
Establish Control Tools
List the Objectives
Prepare Status Reports Review
Project Schedule, cost, team report Issue
Change Orders
Recruit Project Team
Quality and Communication management
Determine Preliminary Resources
Organize Project Team Bidding
Identify Risks and stakeholders Success
criteria
Assign Work Packages
Write Project Proposal
Decision
Project charter WBS
Recruit Criteria
Variance Reports Final Report
Project network
Define Work packages Status Reports
Audit Reports
Project proposal Assign Work
Packages
22Purpose
- To ensure that the works have been completed as
specified, and that all facilities work properly - To provide a record of the actual execution,
together with operating instructions - To train staff in the use of the works
23Purpose
- To formally close out contractual relationships
- Obtain sign off on final report to show
contracted deliverables have been successfully
implemented - To formally terminate project team assignments
- To ensure adequate project documentation and
baseline information for changes that may need to
occur in the future - To obtain clients acceptance of project work and
deliverables
24Deficiency Lists
- These are lists of required repairs or completion
of deficient/incomplete items. - Schedule for completion of deficiencies.
- Need a sign-off procedure.
- Need a handover process to turn project over to
Owner in organized way.
25Records
- During implementation, difficulties may arise
which result in changes to the original design.
Records of these changes will be kept during
implementation, mainly for financial and
engineering reasons. These must be brought
together to make a complete record of the actual
execution.
26As-built Drawings
- Mandatory on some projects.
- Should be provided on all projects.
- Reflect what was actually built.
- Contract documents must set a date for completion
of as-built drawings. - Make sure they are worked on as the project is
built . . . do not wait for the end of the job.
27Termination Process
- Project termination can be complicated
- A systematic approach
- Stay in close contact with the client and
administration to ensure close down meets with
the clients satisfaction.
28Termination Process
- Generally the termination phases include
- 1. Prepare termination logistics
- 2. Document project
- 3. Conduct post implementation audit and
prepare and submit final report - 4. Obtain client approval
- 5. Close operation
29Prepare Termination Logistics
PROJECT TERMINATION PHASES
Close Operation
Document The Project
Project Termination Phases
Obtain Client Approval
Conduct Post- Implementation Audit Prepare and
Submit Final Report
30Final Report
- Memory or history of the project.
- File others can refer to, study progress and
impediments of the project. - Can follow many formats.
- Should answers the following questions
- Was the project goal achieved?
- Was the project work done on time?
- Was it done within budget?
- Was it done by specifications?
- Was the client satisfied with the project
results?
31Final Report
- Usually includes the following elements
- Overall success and performance of the project
- Organisation and administration of the project
- Techniques used to accomplish project results
- Assessment of project strengths and weaknesses
- Recommendation of project manager and team for
continuation or extinction of project
32Rewarding Successes and Learning From Failures
- Closing a project is a celebration of effort.
- Brings resolution to the process.
- Project manager should bring the team together to
review their journey. - Way of closing formal and informal relationships.
- Way to re-enforce learning that occurred.
- Final get together brings project full circle.
33Concluding Remarks
- Projects - an increasingly important way of
working - Project management is challenging, rewarding
- Keep it simple, use aspects of project management
that make sense - Dont be an Accidental Project Manager
- Its OK to make mistakeslearn from them to
improve project management practices
34Claim and Disputes on Projects
35Agenda
- Claims
- Causes of claims
- Dealing with changes
- Claim avoidance and resolution
- Quantification workshop
- Summary
36 Is CONFLICT INEVITABLE?
37Claim is
- The assertion of a right
- A demand for something due
- Filed by Contractor or Owner
- A claim need not become a dispute
- A dispute need not develop into litigation
38Causes of Claims
- Claims Pertaining to Quantity
- Claims Pertaining to Quality
- Claims Pertaining to Methods or Schedule of the
Work
39Claims Pertaining to Quantity
- Change In Design
- Change In Site/subsoil Conditions
- Increased Quantities
- Extra Work
- Measurement Of Work Performed
40Claims Pertaining to Quality
- Ambiguous Specification
- Unreasonably Demanding Inspection
- Design Enhancement Via The Shop Drawing Approval
Process - Deficiencies
41Claims Pertaining to Methodsor the Schedule of
the Work
- Delay
- Disruption
- Interference
- Acceleration
42Change Order
- Is a written agreement to modify, add to, or
alter the work from that set in the contract
documents at the time of opening bids, provided
that such alteration can be considered to be
within the scope of the original project. - It is the only legal means available to change
the contract provisions after the award of
contract
43Change Order
- Could be addition to or deletion from the work
- changes in the method of execution or manner of
work performance - change in owner-furnished materials or facilities
- change in the contract time or order of the work
- correct errors in the plans or specifications
- direct results of contractor suggestions that are
approved by the owner and its agents - Changes may involve
- a price change in the contractors favor
- cash credit to the owner
- no price change at all
44Impact Costs
- Changes in the work may well exceed the cost of
the immediate change itself. - Many change order forms contain an exculpatory
(disclaimer) clause that precludes a contractor
from recovery of impact costs. - Parties sometimes agree on the price of a change
in both time and money, but the contractor wants
to reserve the right to file for impact costs. - Contractor would be ill-advised to sign off on a
change order without a clear reservation, if it
expects to claim any future impact costs. - if owner refuses to accept reservation,
contractor should perform the changed work under
protest without signing the change order or
agreeing to a price
45Reservation by contractor
- This proposal is based solely on the usual cost
elements such as labour, material, and normal
markups, and does not include any amount for
changes in the sequence of work, delays,
disruptions, rescheduling, extended overhead,
acceleration, and/or impact cost. The right is
expressly reserved to make claim for any and all
of these, and related items of cost, prior to any
final settlement of this contract. - How would you react?
46If a change becomes a dispute
-
- Estimate the the impact costs
47Electrical And Mechanical Work
48Basic Principles in Handling Change Orders
- No work should be included beyond the scope of
the base contract. - The identity of the individuals authorized to
request and approve change orders should be
established early. - During the kick-off meeting, discuss the change
order handling procedures. - All changes in the work must be authorized in
writing prior to the execution of any change. - The scope of a change order must be clear, and a
request for a change order proposal should
contain enough information to enable the
contractor to make a realistic estimate.
49Basic Principles in Handling Change Orders
- The contractor should submit its proposal to
execute a change order as soon as possible after
receiving the request and the owners approval or
rejection should follow as soon as possible. - The proposal should be fair. It should recognize
the contractors right to include - overhead and profit percentages
- compensation for legitimate time-delay claims
- compensation for legitimate impact costs if any
50Types of Changes
- Directed changes
- Owner directs the contractor to perform work that
differs from that specified in the contract - Easy to identify, mutually recognized
- Disagreements tend to center on questions of
financial compensation and the effect of change
on the schedule
51Types of Changes
- Constructive Changes
- Is an informal act authorizing or directing a
modification to the contract caused by an act or
failure to act - defective plans and specifications
- engineers interpretation
- higher standard of performance than specified
- improper inspection and rejection
- change in method of performance
- change in the construction sequence
- owner nondisclosure
- impossibility/impracticability of performance
- Must be claimed in writing within time specified
- Major source of disputes
52Sample of a change order
- PROJECT TITLE
- PROJECT NO. CONTRACT NO. CONTRACT DATE
- CONTRACTOR
- The following changes are hereby made to the
Contract Documents - Construction of access bridge abutment No. 1
drainage system and - Reset two penstock bearing plates. All in
accordance with revised DWG S-17209 - Revision 3, dated 28 August 1991.
- Justification
- Unforeseen soil conditions
- CHANGE TO CONTRACT PRICE
- Original Contract Price
- Current contract price, as adjusted by previous
change orders - The Contract Price due to this Change Order will
be (increased) (decreased) by - The new Contract Price due to this Change Order
will be - CHANGE TO CONTRACT TIME
53Avoidance Of Claims
- 1. Contracting Strategies
- 2. Risk Allocation
- 3. Project Administration
54 1. Contracting Strategies
55Partnering
- Partnering
- Tries to instil co-operation amongst project
participants - Focuses on teamwork, communication and alignment
of goals - A partnering workshop is usually conducted at
start of project - Used extensively on US government projects with
good results
562. Risk Allocation
- No Time Extension
- No Damage For Delay
- Changed Soil/Soil Conditions
- Engineering Work
- Quantity Variation
- Notice Provisions
57Disclaimer Clauses
- No damage for delay
- Examination of the work
- Examination of engineering work
58No Damage for Delay
- ....., the contractor shall not have any claim
for compensation for damages against the owner
for any stoppage or delay from any cause
whatsoever.
59Examination of Work
- The bidder is required to investigate and
satisfy himself of every thing and every
condition affecting the work to be performed and
the labour and material to be provided, and it is
mutually agreed that submission of tender shall
be conclusive evidence that the bidder has made
such an investigation.
60Examination of Engineering Work
- Any representations in the tender documents
were furnished merely for the general information
of bidders and were not in any way warranted or
guaranteed by or on behalf of the Owner or the
Owners consultants and its sub-consultants
employees, and neither the Owner nor its
consultants or its employees shall be liable for
any representations, negligent or otherwise
contained in the documents
61Changed soil/site conditions
- Most common claims
- Innocent misrepresentation
- Duty of contractor to ascertain if practical to
execute work - Contractor cannot abandon the contract
- Disclaimer clause bind contractor
- Compensation within framework of contract
62Notice Provisions
- Any claims which the contractor may have against
the Owner shall be presented to the Engineer in
writing not later than seven (7) days after the
occurrence of the delay. - Failure by the contractor to present any claim
within the seven (7) day period shall be deemed
to be an absolute waiver of such claim. - Strict Compliance
- Any reasonable form of written notice is
sufficient
633. Project Administration
- 3.1 Planning/Scheduling
- 3.2 Record Keeping
- 3.3 Project Monitoring
643.1 Planning
65Scheduling
66Planning/Master Schedule
- Design
- Site Availability
- Purchase/Delivery of Process Equipment
- Purchase/Delivery of Owner-supplied Materials
- Interfacing of Various Packages
67Planning/Master Schedule
- Tender Call for Various Packages
- Contract Award of Packages
- Completion of Packages
- Commissioning
- Commercial Operation
683.2 Record Keeping
- Do not proceed with the extra work and changes
without written authorization - Object to biased minutes
- Document delays and impacts
- Request appropriate extension of time and make
clear who pays for additional cost - Make clear who pays for acceleration
- Respond to complaints
69Records to Keep
- Daily job reports
- Photographs and video films and digital pictures
- All correspondence
- Minutes of site job meeting
- Schedules and updates
- Change orders
- Cost/labour reports
- Diaries
70BUILDER OR BUSINESS PERSON
713.3 Project Monitoring Updating Schedules
- Non-adversarial notification tool
- Illustrate and quantify cost and schedule impact
of changes or other delays to the plan - Watch for
- Early completion schedule
- Your commitment
723.3 Project Monitoring Usual Pitfalls
- Defective (Ambiguous) Specifications
- Incomplete/Unclear Drawings
- Design Enhancement Throughout The Shop Drawing
Approval Process - Failure To Provide Proper Instructions
733.3 Project Monitoring Usual Pitfalls
- Use of Inapplicable Standard Drawings
- Ineffective Expediting
- Ineffective Store Management
743.3 Project Monitoring What to Watch Out For
- Timely Response to Queries
- Shop Drawing Turnaround Time
- Unduly Harsh (Demanding) Inspection
- Personality Conflict
- Payment for Changes and extras
- Front-end loading
753.3 Project Monitoring Active Interference
- Improper Rejection of an Equally Suitable
Alternative - Interference with Method of Construction
- Interference with Sequence of Construction
763.3 Project Monitoring Constructive Acceleration
- Contractor is Entitled to Extension of Time
- Contractor Requested Extension in a Timely Manner
- Owner Refused Request
77Claims by Owners Contractor Refuses to Sign The
Contract
- Mistake in Bid
- Cannot be Bonded
- Left Too Much on the Table
78Claims by Owners Contractor Late in Completion
- Liquidated Damages
- General Damages
79Obstacle to Resolution
- Owners bias
- Contractors bias
- Total cost claims
80Owners Bias
- Loss is vastly overstated by contractor
- Underbidding
- Inadequate supply of resources
- Mismanagement
- Strike, inclement weather, default of subs...
81Contractor Bias
- Causes of loss
- Late supply of equipment, drawings
- Changed conditions
- Acceleration
- Design changes
82Total Cost Claims
- Contractor submits without notification a claim
for additional costs - Actual minus estimated
- This means
- no underbidding
- all causes owners responsibility
- damages were mitigated
- no other practical method
83Successful Settlement
- Get the facts
- Keep good records
- Know your contract
- Preserve your rights
84 CLAIM COMPONENTS
ENTITLEMENT (CONTRACT)
CAUSE
EFFECT
LINK OF CAUSE TO EFFECT
FACTS
DAMAGE / COST INCURRED
85HAVING AN HONEST DISPUTE IS NOT SHAMEFUL
- UNWILLINGNESS TO RESOLVE IT
- IS
86Resolution of Disputes
- During Construction
- Post-Construction
87During Construction
- Negotiation
- Face to face by parties themselves
- Cheapest quickest method
88During Construction
- Joint Performance Evaluation
- Specific criteria to evaluate effectiveness
- Progress meetings
- Forum for identifying a problem
- Periodic survey
- Compare of survey responses
- identify areas of improvement and potential
problems
89Example Joint Evaluation
1. Communications between the
owner/contractor personnel are 2. Top
management support of partnering process
is 3. Problems, issues or concerns
are 4. Cooperation between owner
and contractor personnel is 5. Responses
to problems, issues, or concerns frequently
become
Difficult, guarded
Easy, open, up front
1 2 3 4 5
Not evident, Inconsistent
Obvious, consistent
1 2 3 4 5
Attacked promptly
1 2 3 4 5
Ignored
Cool, removed, detached,
Genuine, unreserved, complete
1 2 3 4 5
Personal issues
Treated as project problems
1 2 3 4 5
90During Construction
- Problem Resolution Mechanism
- Lowest level with time limit
- Escalated to the next level of management
- No action is not an option
91Problem Resolution Mechanism
92During Construction
- Project Neutral Adjudicator
- Appoint an impartial professional to offer
unbiased advice and decisions - Some contracts/contracting processes based on
this principle - New Engineering Contract (NEC) by the UK
Institute of Civil Engineers
93During Construction
- Dispute Resolution Board (DRB)
- Three members
- Established at the beginning of project
- Non-binding
94Post-Construction
- Negotiation
- Mediation
- Mini-Trial
- Arbitration
95Mediation
- Voluntary
- Economical
- Uses impartial mediator to facilitate
conciliation process - Assist negotiation
- Relies on communication to achieve resolution
- Problem solving approach
- Decision is not binding
- Some contracts include mediation clauses
96Mini-trial
- Presentation of both sides arguments before an
advisory panel and executives of both sides. May
include a judge - Used to predict the likely outcome and the
strength and weakness of the case - Voluntary and non-binding
97Arbitration
- Provisions for arbitration are included in most
contracts - May or may not require mandatory arbitration
- Most contracts stipulate that the process will be
governed by the arbitration act
98Arbitration
- Uses impartial arbitrator(s) as trier of facts
- 1or 3 arbitrators
- Selection of arbitrators
- Each party selects one arbitrator
- Both select a chairperson
- Decision is mostly binding
- Could be expensive
99Litigation
- Outcome decided by the courts
- Not private
- Dirty linen is hung out!
- Very adversarial
- Not recommended!
100Litigation
- Too adversarial
- Outcomes unpredictable
- Very expensive and lengthy
- Cost of a 100,000 litigation was shown to be
140,000 for each
101COST OF A 100,000 CONSTRUCTIONLITIGATION Fees
Disbursements
Plus 6,000 for Transcripts Plus
15,000 for Experts Fee _at_ 1,500 per day
102Voltaire
- I have only been ruined twice in my life. The
first time was when I lost a lawsuit the second,
when I won one!
103 BE FAIR
104Conclusions
- Pay attention to risk allocation
- Understand contractual terms
- Even unpalatable terms are enforceable
- Work within terms of contract
- Understand causes of claims
- Nip problem in the bud
- Early non-adversarial communication
- Keep negotiating
- Work with people
- Proper project management
- New approaches
105Key Points
- TRUST is the key to effective contracting and
project delivery - Beware of the practical impact law of contract
- Read and understand your contract
- Apportion risks on a business basis
- Changes are inevitable, so accommodate it
106(No Transcript)