21CN Mass Migration Methodology: queries to: tom.saville@bt.com - PowerPoint PPT Presentation

1 / 10
About This Presentation
Title:

21CN Mass Migration Methodology: queries to: tom.saville@bt.com

Description:

queries to: tom.saville_at_bt.com. Consult21. 2 ... Install, configure, cable & commission MSAN, 21CN Test Access Matrix (TAM), Test ... – PowerPoint PPT presentation

Number of Views:114
Avg rating:3.0/5.0
Slides: 11
Provided by: British66
Category:

less

Transcript and Presenter's Notes

Title: 21CN Mass Migration Methodology: queries to: tom.saville@bt.com


1
21CN Mass Migration Methodologyqueries to
tom.saville_at_bt.com
2
Forward Looking Statements Caution Advised
  • Certain statements in this presentation are
    forward-looking and are made in reliance on the
    safe harbour provisions of the US Private
    Securities Litigation Reform Act of 1995. These
    statements include, without limitation, those
    concerning BT's plans for transformation of its
    networks benefits to customers of the 21CN
    programme key milestones and expected timetable
    for delivery of 21CN and the benefits in
    relation to, for example interconnect,
    convergence and broadband.
  • Although BT believes that the expectations
    reflected in these forward-looking statements are
    reasonable, it can give no assurance that these
    expectations will prove to have been correct.
    Because these statements involve risks and
    uncertainties, actual outcomes may differ
    materially from those expressed or implied by
    these forward-looking statements.
  • Factors that could cause differences between
    actual outcomes and those implied by the
    forward-looking statements include, but are not
    limited to material adverse changes in economic
    and financial markets conditions in the markets
    served by BT supplier arrangements future
    regulatory actions and conditions in BTs
    operating areas technological innovations
    developments in the convergence of technologies
    and the anticipated benefits and advantages of
    new technologies, products and services,
    including broadband, not being realised.

3
  • This presentation should be viewed in
    conjunction with the PSTNMass Migration
    Methodology Presentation presented at the IMWG on
    15/11/05 by Alan Cameron (ref SLOT 6 slides16
    23)
  • This presentation is designed to inform
    Communication Providers of
  • the migration activities which will be undertaken
    by BT including
  • Pre-Transfer activities (identified as Configure
    Verify phase)
  • On the night Transfer activities
  • Post Transfer activities (identified as Monitor
    phase)
  • the impacts on End Customers of mass migration
    for PSTN VOICE SERVICES

4
E-side MDF Pre-Transfer
Pre-Transfer Activities Install, configure, cable
commission MSAN, 21CN Test Access Matrix (TAM),
Test Heads Comms Cable 21CN TAM to MDF fit
Transfer Connectivity Point (TCP) modules on
E-side blocks TCP module installation
checks 21CN Call Server MSAN data build PSTN
pre-transfer checks
5
Pre-Transfer Activities - Detail
  • TCP installation
  • Install Commission phase incorporates a 100
    end to end test of all 21CN equipment.
  • Pre Post TCP installation checks ( BAU /
    Non-intrusive)
  • 5 pair module Target 30 seconds customer outage
  • 5 pair module includes Over Voltage Protection
  • Trials 100 pair block 15 - 20 minute TCP
    installation
  • PSTN Pre-Transfer Tests
  • Check connection from 21CN TAM to TCP (Existing
    line)
  • Business as Usual test / Non-intrusive
  • Check Pre-build MSAN services
  • Non-intrusive test
  • Activity Freeze before Transfer
  • Aiming for maximum 12 hours

6
E-side MDF Transfer in progress
Transfer Activities Command Control confirm
transfer Go/No Go Disconnect PSTN concentrator
Switch 21CN TAM Sync with changeover from DLE
to Call Server
7
Transfer Activities detail
  • Transfers will happen overnight in periods of low
    network activity but may be scheduled for any
    night of the week
  • Transfer Go / No Go Decision
  • Various defined decision points along Transfer
    timeline
  • Final decision approximately 10pm
  • Calls in Progress
  • Calls in progress will be lost, however, special
    measures to prevent disruption of 999 calls will
    be implemented
  • PSTN Disconnection
  • Number of options under consideration
  • Testing to determine most suitable to minimise
    service outages
  • 21CN TAM Switching
  • 21CN TAM suite (Max. 14400 lines) lt10 seconds
    (Outgoing calls)
  • PSTN to 21CN re-routing minutes (Incoming
    calls)
  • Alignment of both to minimise total service outage

8
Transfer Activities - End User Experience
  • Outgoing calls
  • Short break in dial tone during 21CN TAM switch
  • No service interruption announcement during
    switch
  • Incoming Calls
  • Precise detail of service capability will become
    known upon completion of transfer engineering end
    to end trials phase.
  • Incoming call capability will be dependant upon
    size of number range and customer position within
    it.
  • For those at the front of the number range
    restoration of service capability will be
    instant, for those further along the range, the
    duration will be longer.
  • A range of options are being considered as part
    of the transfer engineering solution to improve
    these timings.
  • Principle is to achieve the shortest service
    capability interruption possible
  • Dial Tone
  • There will be no perceptible change in the dial
    tone heard by the end user once transfer has been
    completed.

9
E-side MDF Post Transfer
MDF
Test Head
D
E
POTS
PSTN DLE
PSTN CONC
OVP
Customer lines
OVP
OVP
21CN TAM
MSAN
21CN Voice
Post Transfer Activities Switch from PSTN Test
Access to 21CN TAM Test Access Post transfer
checks Monitor network for fallback period
Decommission Redundant Equipment Hand-over to
Operations
21CN T/TH
10
Post Transfer Activities - detail
  • Post Transfer Checks
  • PSTN disconnection tests (Every Line)
  • MSAN connection (Non-intrusive) tests
  • Review Monitoring
  • Assess network performance against Fallback
    criteria (eg on the night test results /
    faults)
  • 7 day monitoring period
  • Fault Reporting
  • Special measures will be in place for fault
    reporting for 7 day period.
  • Additional resource available to deal with any
    reports