TM 665 Project Planning - PowerPoint PPT Presentation

About This Presentation
Title:

TM 665 Project Planning

Description:

South Dakota School of Mines and Technology, Rapid City. 4th Session 2/09 ... Flow Diagram for SPAR-1, Fig. 9-19. Frank Matejcik SD School of Mines & Technology ... – PowerPoint PPT presentation

Number of Views:44
Avg rating:3.0/5.0
Slides: 20
Provided by: SDS6
Category:
Tags: planning | project | spar

less

Transcript and Presenter's Notes

Title: TM 665 Project Planning


1
TM 665Project Planning Control Dr. Frank
Joseph Matejcik
4th Session 2/09/04 Chapter 9 Resource
Allocation File 2
  • South Dakota School of Mines and Technology,
    Rapid City

2
MSP Gantt with Resources, Fig. 9-10
3
MSP Load Diagram, Showing Resource Conflict,
Figure 9-11
4
MSP Load Diagram, Leveled, Figure 9-12
5
Network for Resource Load Simulation, Figure 9-13
6
Load Chart, Figure 9-14
7
Task a Decomposed, Figure9-15
8
Hierarchy of Gantt Charts, Figure 9-16
9
Sources and Uses of Resources, Figure 9-17
10
Project Life Cycles, Figure 9-18
11
Flow Diagram for SPAR-1, Fig. 9-19
12
Goldratts Critical Chain
  • There are systemic problems that plague project
    schedule performance
  • These problems are not randomly distributed
  • If they were random, there would be as many
    projects finishing early as late

13
Some Systemic Causes of Late Projects
  • 1. Thoughtless Optimism
  • Overpromising at project start
  • Success-oriented schedules
  • Lack of management reserves
  • 2. Setting capacity equal to demand
  • Ignoring concepts of resource loadingand leveling

14
Some Systemic Causes of Late Projects (contd)
  • 3. The Student Syndrome
  • Delaying start of non-critical tasks
  • Parkinsons Law Work expands to fill the time
    available
  • 4. Multitasking to reduce idle time
  • Switching back and forth between projects
    creates delays

15
Some Systemic Causes of Late Projects (concluded)
  • 5. Complexity of schedule drives delay
  • Uncertainty and complex paths join to make
    trouble
  • 6. People need reason to strive
  • Theres often no advantage seen to finishing
    early
  • 7. Game playing
  • E.g., lower levels pad estimates, senior
    management slashes them
  • Both can be equally arbitrary

16
Summary
  • The critical path method (CPM) is a network
    constructed in the same manner as PERT but
    considers the possibility of adding resources to
    tasks to shorten their duration
  • The resource allocation problem is concerned with
    determining the best trade-offs between available
    resources, including time, throughout the
    duration of the project

17
Summary
  • Resource loading is the process of calculating
    the total load from project tasks on each
    resource for each time period of the projects
    duration
  • Resource leveling is concerned with evening out
    the demand for various resources required in a
    project by shifting tasks within their slack
    allowances

18
Summary
  • There are two basic approaches to addressing the
    constrained resources allocation problem
  • Heuristic methods
  • Optimizing methods
  • For multiproject scheduling, three important
    measures of effectiveness are schedule slippage,
    resource utilization, and level of in-process
    inventory

19
Summary
  • When a new project is added to a multiproject
    system, the amount of slippage is directly
    related to the average resource load
  • Mathematical programming models for multiproject
    scheduling aim to either minimize total
    throughput time for all projects, minimize the
    completion time for all projects, or minimize
    total lateness for all projects
Write a Comment
User Comments (0)
About PowerShow.com