GLAST Proposal Review - PowerPoint PPT Presentation

About This Presentation
Title:

GLAST Proposal Review

Description:

... qualifications should be provided describing the estimate, such as quotes or ... Submit baseline material October 15. ... Documentation and instruction (October) ... – PowerPoint PPT presentation

Number of Views:39
Avg rating:3.0/5.0
Slides: 22
Provided by: peterfmi
Category:

less

Transcript and Presenter's Notes

Title: GLAST Proposal Review


1
GLAST Large Area Telescope Baseline Review
Preparations Tanya Boysen Stanford Linear
Accelerator Center LAT Project Controls
Manager tkb_at_slac.stanford.edu
2
Baseline Review Preparations
  • Outline
  • Baseline Preparations
  • Technical (Scope)
  • Schedule
  • Cost
  • Recommendations from February Review
  • Plan for Completion

3
Baseline Preparations
  • Technical (Scope)
  • WBS complete for 12 subsystems 1 still to be
    confirmed.
  • Subsystem managers responsible for technical
    baseline documents. All subsystem L2 and L3
    requirements written and reviewed.
  • Schedule
  • All inputs have been received from subsystem
    managers.
  • Half are completed, half are being actively
    iterated with PMCS team.
  • Cost
  • All cost estimates received from subsystem
    managers.
  • 4 complete the rest are being actively iterated
    (most of these iterations concern some final
    detail).

4
February Review Recommendations
  • Management Recommendation 4
  • Develop an integrated, resource loaded schedule
    and cost estimate.
  • Current statistics
  • 6080 Schedule Activities
  • 6300 Schedule Relationships
  • 200 Work Packages

5
Status of PMCS Inputs
6
Status of PMCS Inputs (contd)
7
Monthly Status Cycle
  • Have established and communicated a plan for the
    monthly cost/schedule status cycle.
  • Have been collecting actual cost information
    since March.
  • First complete cycle conducted (data for June).
  • Educated the participants on the process and the
    reports.
  • Examined variances to plan.
  • Status as of August 30 will support the baseline
    review.

8
June, 2001 Status
9
June, 2001 Status
10
February Review Recommendations
  • Schedule Funding Recommendation 1
  • Continue to formalize and complete the
    integrated schedule, focusing on establishing the
    critical paths for each subsystem.
  • Currently in the last stages of schedule
    development
  • Identifying key milestones/levels
  • Creating linkages between subsystems
  • Checking schedule logic
  • Critical path analysis has begun, and will be
    fully realized by mid-September

11
February Review Recommendations
  • Schedule Funding Recommendation 2
  • Include all activities in the integrated
    schedule, including non-costed and foreign
    activities.
  • Entire project scope in the schedule.
  • Schedule Funding Recommendation 3
  • Ensure that sufficient slack exists for the
    individual subsystem schedules.
  • Six-month launch delay
  • LAT integration delayed by three months

12
February Review Recommendations
  • Schedule Funding Recommendation 4
  • Introduce a milestone hierarchy into the Project
    Management Control System.
  • L1, L2, L3 milestones identified and agreed upon
    by Althouse, Lambros, Valle.
  • L4 milestones identified by subsystem managers,
    being reviewed by the IPO.

13
Milestones to Level 3
14
Milestones to Level 3, contd
15
February Review Recommendations
  • Cost Estimate Recommendation 1
  • Core members of PMCS team in place as quickly as
    possible to allow adequate time to transfer
    technology and information from the consultants
    to the permanent team, and to provide a smooth
    transition into the implementation phase of the
    project.
  • Will develop a blended team of AIM consultants
    and regular SLAC employees, to optimize issues of
    continuity, expertise, and cost.
  • Currently recruiting for two Project Controls
    Analyst positions at SLAC.
  • AIM presence will not decrease until transition
    to a blended team is achieved.

16
GLAST/LAT PMCS Organization
Tanya Boysen SLAC Project Controls Manager
Jeff Chan AIM
17
February Review Recommendations
  • Cost Estimate Recommendation 2
  • Complete a bottoms-up resource loaded cost and
    schedule estimate for the GLAST project to
    support the baseline review. Estimate
    qualifications should be provided describing the
    estimate, such as quotes or engineering estimates
    for MS costs, or fully loaded institutional
    labor rates for manpower costs.
  • Labor rates confirmed with all institutions.
  • Basis of estimate complete for 4 subsystems.

18
February Review Recommendations
  • Cost Estimate Recommendation 3
  • Perform a bottoms-up contingency analysis based
    upon the appropriate parameters at the lowest WBS
    for the LAT project to support the baseline
    review. Resulting contingencies should be
    explicitly identified and easily viewed.
  • 6 subsystems have completed contingency analyses.
  • Using same contingency method as BABAR, weighting
    technical, design, cost, and schedule risks.

19
February Review Recommendations
  • Cost Estimate Recommendation 4
  • Manpower should be tracked explicitly as FTEs
    in the Project Management Control System.
  • Developing plans for manpower via the
    resource-loaded schedule development, for both
    funded and contributed manpower.
  • 3 of the subsystems have completed manpower
    plans, the remainder are iterating or on one
    last little detail.
  • Working with participating institutions to enable
    monthly reporting of actual manpower levels. 3
    are successfully reporting manpower.

20
Plan for Completion
  • LAT budget meeting August 15
  • Cost schedule inputs received and incorporated
    into PMCS by August 31
  • Work package planning
  • Schedule integration
  • Critical path analysis mid-September
  • Receive August actual cost information -
    September 17
  • Identify and review variances
  • Set Performance Measurement Baseline first week
    of October.
  • Schedule Performance Actuals (for historical
    data)
  • Submit baseline material October 15.

21
Looking Forward
  • Documentation and instruction (October).
  • Work authorization agreements to communicate and
    formalize annual expectations from the top down
    (October).
  • LAT Project Controls web page (November).
Write a Comment
User Comments (0)
About PowerShow.com