Title: GLAST Proposal Review
1GLAST Large Area Telescope Baseline Review
Preparations Tanya Boysen Stanford Linear
Accelerator Center LAT Project Controls
Manager tkb_at_slac.stanford.edu
2Baseline Review Preparations
- Outline
- Baseline Preparations
- Technical (Scope)
- Schedule
- Cost
- Recommendations from February Review
- Plan for Completion
3Baseline Preparations
- Technical (Scope)
- WBS complete for 12 subsystems 1 still to be
confirmed. - Subsystem managers responsible for technical
baseline documents. All subsystem L2 and L3
requirements written and reviewed. - Schedule
- All inputs have been received from subsystem
managers. - Half are completed, half are being actively
iterated with PMCS team. - Cost
- All cost estimates received from subsystem
managers. - 4 complete the rest are being actively iterated
(most of these iterations concern some final
detail). -
4February Review Recommendations
- Management Recommendation 4
- Develop an integrated, resource loaded schedule
and cost estimate. - Current statistics
- 6080 Schedule Activities
- 6300 Schedule Relationships
- 200 Work Packages
5Status of PMCS Inputs
6Status of PMCS Inputs (contd)
7Monthly Status Cycle
- Have established and communicated a plan for the
monthly cost/schedule status cycle. - Have been collecting actual cost information
since March. - First complete cycle conducted (data for June).
- Educated the participants on the process and the
reports. - Examined variances to plan.
- Status as of August 30 will support the baseline
review.
8June, 2001 Status
9June, 2001 Status
10February Review Recommendations
- Schedule Funding Recommendation 1
- Continue to formalize and complete the
integrated schedule, focusing on establishing the
critical paths for each subsystem. - Currently in the last stages of schedule
development - Identifying key milestones/levels
- Creating linkages between subsystems
- Checking schedule logic
- Critical path analysis has begun, and will be
fully realized by mid-September
11February Review Recommendations
- Schedule Funding Recommendation 2
- Include all activities in the integrated
schedule, including non-costed and foreign
activities. - Entire project scope in the schedule.
- Schedule Funding Recommendation 3
- Ensure that sufficient slack exists for the
individual subsystem schedules. - Six-month launch delay
- LAT integration delayed by three months
12February Review Recommendations
- Schedule Funding Recommendation 4
- Introduce a milestone hierarchy into the Project
Management Control System. - L1, L2, L3 milestones identified and agreed upon
by Althouse, Lambros, Valle. - L4 milestones identified by subsystem managers,
being reviewed by the IPO.
13Milestones to Level 3
14Milestones to Level 3, contd
15February Review Recommendations
- Cost Estimate Recommendation 1
- Core members of PMCS team in place as quickly as
possible to allow adequate time to transfer
technology and information from the consultants
to the permanent team, and to provide a smooth
transition into the implementation phase of the
project. - Will develop a blended team of AIM consultants
and regular SLAC employees, to optimize issues of
continuity, expertise, and cost. - Currently recruiting for two Project Controls
Analyst positions at SLAC. - AIM presence will not decrease until transition
to a blended team is achieved.
16GLAST/LAT PMCS Organization
Tanya Boysen SLAC Project Controls Manager
Jeff Chan AIM
17February Review Recommendations
- Cost Estimate Recommendation 2
- Complete a bottoms-up resource loaded cost and
schedule estimate for the GLAST project to
support the baseline review. Estimate
qualifications should be provided describing the
estimate, such as quotes or engineering estimates
for MS costs, or fully loaded institutional
labor rates for manpower costs. - Labor rates confirmed with all institutions.
- Basis of estimate complete for 4 subsystems.
18February Review Recommendations
- Cost Estimate Recommendation 3
- Perform a bottoms-up contingency analysis based
upon the appropriate parameters at the lowest WBS
for the LAT project to support the baseline
review. Resulting contingencies should be
explicitly identified and easily viewed. - 6 subsystems have completed contingency analyses.
- Using same contingency method as BABAR, weighting
technical, design, cost, and schedule risks.
19February Review Recommendations
- Cost Estimate Recommendation 4
- Manpower should be tracked explicitly as FTEs
in the Project Management Control System. - Developing plans for manpower via the
resource-loaded schedule development, for both
funded and contributed manpower. - 3 of the subsystems have completed manpower
plans, the remainder are iterating or on one
last little detail. - Working with participating institutions to enable
monthly reporting of actual manpower levels. 3
are successfully reporting manpower.
20Plan for Completion
- LAT budget meeting August 15
- Cost schedule inputs received and incorporated
into PMCS by August 31 - Work package planning
- Schedule integration
- Critical path analysis mid-September
- Receive August actual cost information -
September 17 - Identify and review variances
- Set Performance Measurement Baseline first week
of October. - Schedule Performance Actuals (for historical
data) - Submit baseline material October 15.
21Looking Forward
- Documentation and instruction (October).
- Work authorization agreements to communicate and
formalize annual expectations from the top down
(October). - LAT Project Controls web page (November).