Restoration of a 1964 Chevrolet Corvair Monza Spyder - PowerPoint PPT Presentation

1 / 32
About This Presentation
Title:

Restoration of a 1964 Chevrolet Corvair Monza Spyder

Description:

Restoration of a. 1964 Chevrolet Corvair Monza Spyder. By. Ananthanarayan Subramanian ... Procurement of a restorable car subject to available finances ... – PowerPoint PPT presentation

Number of Views:191
Avg rating:3.0/5.0
Slides: 33
Provided by: ksana
Category:

less

Transcript and Presenter's Notes

Title: Restoration of a 1964 Chevrolet Corvair Monza Spyder


1
Restoration of a 1964 Chevrolet Corvair Monza
Spyder
  • By
  • Ananthanarayan Subramanian
  • Bradley Hollingsworth
  • Meghana Parthasarathy

2
Key Details
  • Project Deadline
  • August 30th 2003.
  • In time for Labor Day Car Show.
  • Returns
  • 15000 for on-time delivery.
  • 10000 otherwise.
  • Regular Customer

3
Need of the Hour ?
  • A Project Plan to
  • Enable successful on-time completion
  • Effectively manage available resources
  • Maximize returns

4
Project Parameters
  • The car
  • 1964 Chevrolet Corvair Monza Spyder
  • Resources
  • People
  • Finances
  • Equipment

5
Project
  • Resources

6
Resources Available - People
  • Engineers
  • General supervision and planning
  • Meghana, Brad and Anti
  • Mechanic
  • Assembly and Repair
  • Machinist
  • Repair
  • Fabricator
  • Sheet metal work on external parts
  • Upholstery Contractors
  • Internal upholstery

7
Resources - Manpower
8
Resources Available - Equipment
  • Machine Shop
  • Available whenever required by Machinist.
  • Sheet metal Fabrication Shop
  • Available whenever required.
  • Garage with appropriate equipment.

9
Project
  • Schedule

10
Key Tasks
  • Research on Corvairs.
  • Budgetary Analysis.
  • Procurement of a restorable car subject to
    available finances
  • Disassembly and in-depth study of the car
  • Procurement and repair of appropriate spare parts
  • Assemble car and test.
  • Delivery.

11
Project Schedule (Main Tasks)
12
Network Diagram (Main Tasks)
13
Schedule for Restoration
14
Gantt Chart (critical path)
15
Crystal Ball
16
Paths for Risk Analysis
17
Crystal Ball Output
18
Project Schedule Simulation
19
Schedule Simulation Statistics
  • Summary
  • Number of Trials 1000
  • Mean 156.69 days
  • Standard Deviation 4.224 days
  • Range Minimum 146.072 days
  • Range Maximum 178.594 days

20
Project
  • Budget

21
Budget Breakdown
22
(No Transcript)
23
Labor Cost Simulation (Frequency Chart)
24
Labor Cost Simulation Statistics
25
Crash Costs
  • To meet 8/29/03 due date for bonus
  • Identified all paths (18 total)
  • Excel Solver minimize project duration
  • Project Crash Cost 3,571.88
  • Crashing accelerates project 30 days
  • Majority procuring replacement parts
    repairing original parts

26
Cost Analysis
27
Resource Usage - Unleveled
28
Resource Usage - Leveled
29
Risk Analysis Resource Allocation
30
Resource Allocation Simulation Statistics
Summary Display Range is from 299.859 to 368.471
Days Entire Range is from 299.859 to 368.471
Days After 1,000 Trials, the Std. Error of the
Mean is 0.378
31
Anticipated Problems
  • 50 chance of not completing the project on time.
  • Increase the upper bound on the critical time.
  • Problems for budget and resources.

32
Questions??