Title: Integrated Civil Engineering Design Project (Building Structure Design Example) CIVL 395
1Integrated Civil Engineering Design
Project(Building Structure Design Example)
CIVL 395
By Ir. K.S. Kwan Date 4/07
2Architectural Consideration
- Limitation (plot ratio, height, public
facilities, slope) - View/light/Wind climate
- Flat size, Number of Blocks
- Podium (Other Facilities Cube house/ Carpark/
Commercial complex) - Budget estimation
- Other considerations
3Structural Engineer Consideration
- Any site construction difficulties
- Site Access
- Construction platform
- Foundation option
- Time for completion
- Tower Design
- To provide a cost-effective solution
4Case A 45 storey
Lack of flexibility by structural element
End wall should be effectively used as shear wall
to provide better stiffness
5- To enhance the stiffness of building by linking
the walls as much as possible
6Lack of flexibility by structural element
Too much wall
No support for slab
7Wall not allowed in front of stairs
Beam ahead bedroom
Too much wall
End wall should be effectively used as shear wall
to provide better stiffness
8Structural Framing Plan
Secondary Beam for gravity load only
Aspect ratio 45x3/19 7.0
Lintel Beam For both wind load and gravity load
9Case B 15 storey
10Aspect ratio 15x3/60 0.75
Column structure used
11Case C 57 storey
12Aspect ratio 57x3/24.3 7.03
13Podium Structure
- To confirm the column layout under transfer
structure - To confirm the transfer plate/column layout
- To confirm the size of transfer structure (e.g.
thickness of transfer plate) - Evaluate the tower loading and estimate the size
of transfer structure size
14(No Transcript)
15Tower Framing plan
16Transfer Structure under tower
17Supporting columns under transfer structure
18Other beam/column structure below
19Other beam/column structure below
20Other beam/column structure below
21Preliminary Computer Model
- Use the effective members for first model
- Estimate the member size for model input based on
gravity load first and provide some reserve for
wind load (say 20 40 of wind load) - Check top deflection lt H/500
22- Only analysis the critical wind direction
- Only use the effective members for modeling
Minor wall not selected for preliminary modeling
Width of building to calculate the wind load
23- For preliminary model, only typical floor is used
to simulate the whole tower. - Building height should be maintained
Tower model
Podium model
24Element Checking
- Check critical lintel beam force (e.g. check wind
shear stress vV/bd ) - Check critical element force (e.g. wall element
under high compression/tension)
25Loading Schedule Checking
Check average gravity load (Total DL/Gross Floor
Area 1520 KN/m2
Total axial force 0
Check total wind shear force total wind force
applied at the building
26Q A
27(No Transcript)