Title: An Examination of some Road Based B.O.T Projects in India with Special Reference to Traffic Forecasting
1An Examination of some Road Based B.O.T Projects
inIndia with Special Reference to Traffic
Forecasting
National Seminar on PPP in Road and Transport
Infrastructure
- Dr S. L Dhingra Institute Chair
Professor Emeritus FellowTransportation
Systems EnggCivil Engineering Department, IIT
Bombay
2Contents
- Challenges of Urbanization
- PPP
- Private Sector Interest
- Transportation Infrastructure Projects From
Conception to Implementation - Fund Sources
- Risks and Uncertainty in Projects
- Effects of Toll rates in traffic projections
- B.O.T projects based on government support and
guarantees. - Conclusion
3Challenges of Urbanization
4Urbanisation
- Urban areas contribute 75 of GDP and more than
50 of our population to live in urban areas by
2050. - Rurbanisation of the countryside to pose newer
challenges. - Cities would be the key drivers to our economy
but - unless a focused approach coupled with heavy
investment in urban infrastructure is put in
Urban areas would keep presenting 100000 problems
which in essence are 100 problems multiplied 1000
times
5Growing Demand for Urban Infrastructure
6(No Transcript)
7Multifarious Responsibilities Limited Resources
- Local Government Expenses vary between 20-29 in
developed countries while they are only 7-8 in
India - Limited revenue base and dependent fiscal
Jurisdiction - Fairly Large Capital Investment decisions being
thrust upon municipalities
8Infrastructure Bottleneck
- Infrastructure is the biggest bottleneck in
India Growth Story - Transport system has severe capacity constraints
highways, city roads, airports, seaports and
railways - Urban and Utility infrastructure Huge
demand-supply gap in drinking water, sewerage
system, drainage and power supply - India needs US 480 billion investment in the
coming Five Year Plan to meet current
Infrastructure needs, at least 20 of this would
be for the Urban Sector
9Existing Scenario
- Most towns and cities are growing Like this!
10Quality of life
11How we cope, presently
Premji raps Karnataka Govt for bad roads, power
situation in Sarjapur Our Bureau Bangalore ,
July 18
12Private Sector Interest?
- Urban Infrastructure, has not yet found investor
interest in the absence of clear directions on
various aspects - Risk, social/ political,
Regulatory, cost recovery mechanisms, etc. - Various attempts are being made to convert Urban
Service (water, waste-water, Solid waste, etc)
into Bankable projects - This is likely to open a new area for
investments - And a new breed of Operating companies to
provide these services - But proper PROJECT DEVELOPMENT is the key here
13Total Private Sector Investments in Indias
Infrastructure
- Year of Investment Energy Telecom Transport
Water and sewage Total - 1990 0 0 2 0 2
- 1991 614 0 0 0 614
- 1992 13 0 0 0 13
- 1993 1,051 0 0 0 1,051
- 1994 311 97 125 0 533
- 1995 1,008 683 0 0 1,691
- 1996 1,553 1,229 108 0 2,890
- 1997 970 3,827 405 0 5,201
- 1998 1,066 673 296 0 2,035
- 1999 2,500 1,045 467 0 4,012
- 2000 2,357 682 100 0 3,139
- 2001 45 3,445 211 2 4,004
- 2002 380 4,615 558 0 5,553
- 2003 825 1,968 505 0 3,298
- 2004 4,144 3,731 1,117 0 8,992
- 2005 755 6,201 1,449 0 8,405
14Beginnings made
- May not be all success stories, but
- Tamil Nadu
- Tirupur, Alandur, TNUDF Pooled Finance
- Municipal Bond issues
- Ahmedabad, Hyderabad, Nashik
- Urban infrastructure funds IFCG, Feedback
U-Fund and MUIF - Not Successful
- BATF in BangaloreBangalore Agenda Task Force
- The Bangalore Agenda Task Force is meant to be a
partnership between the citizens, corporates and
the administrative agencies the BMP, BDA, BMTC,
... - Water OM PSPs (attempts!) in Pune, Goa,
Bangalore, Hyderabad
15Pooled Finance
- TNUDF sponsored issue, successful in Tamil Nadu
- USAID (DCA) guarantee for 50 of principal
- Karnataka (KUIDFC) pursued similar issue
- Government of Indias proposed PFDF, also a
pointer in this direction - Yet to take off
- Issues of listing Trust-financed Bonds (SEBI),
would have to be addressed to ensure a market for
these instruments
16Pooled Finance (2)
17Viability Gap Funding
- Proposed by Government of India
- To Prop-up marginally viable projects
- Established and clear guidelines for allocation
- Problem may be in the lack of developed and
structured projects, that are eligible to claim
this assistance
18Capital Market Access
- Bond issues of Ahmedabad, Hyderabad, BMP, Nashik
etc., have not led to large-scale replication - Issues of market appetite, end-use
- Limited number of ULBs which can access financing
on a standalone basis - Pooled Finance seems a more appropriate structure
for small ULBs
19Access to Domestic Financial Institutions
- For the Local Body
- Reluctance of Local bodies to accept FI
conditions typically stipulated to mitigate
project risks - ULBs have option of (a) FIs assistance (cash flow
basis with conditions) Vs (b) MLA funding/ Govt.
Institutions ( GoI/ State guaranteed soft push,
if any) - ULB prefers the latter to the former (obvious!)
- For the Domestic Institution
- Guaranteed lending (state/ central) is no more
risk-free, from regulatory considerations
20PPP Some reasons to be optimistic
- Realization of need for improvement of Urban
Services, and concurrently, the finance needed
for doing so - Various precedents are being tried and tested,
and experience is maturing - But yet a long way to go
- Key Words
- Not Finance, but Developed Bankable Projects
- Not Willingness to Pay, but Unwillingness to
Charge
21PPP Approach
Goal
- Attract private investments for infrastructure
projects
- Lack of Budgetary Resources
- Need to improve efficiency in service delivery
Need
PPP approach
- Private Sector contribution for
- - Financial investments
- - Best Management practices
- - Efficiency in service delivery
- - Efficient use of capital resources
- Public Sector contribution limited to
- - Providing institutional commitment to
project - - Project Development Selection of
Developer - - Viability gap funding (VGF), if any
22Background Issues
- Ability to create a shelf of projects?
- Project development requires funds and continuous
support - Strengthening the capabilities of the mandated
agency to create experiential learning - Standardized processes for Viability support for
projects not viable on stand alone basis - No need to reinvent the wheel every time, learn
from peers
Debate has shifted from financing of
infrastructure projects to creation of a shelf of
projects.
23Structure
24A PPP is not a transfer of responsibility
- A PPP project DOES NOT Mean that the Government
has little or no onus - Its objective has to be synergy between the
private public sectors - Areas such as land acquisition, clearances,
utilities, etc., can still be best done only by
the Government
25What are the advantages of private sector
participation ?
- If properly structured and incentivized, the
private sector can provide a more efficient or
cost-effective service. - The private sector often has better access to
capital financing and so it is able to use more
efficient equipment. - The private sector may have easier access to
specialist skills. For example companies can form
joint ventures with international specialist
firms.
26Putting the projects on shelf
Project Preparation
Partnership Management
Project Identification
Viability
Structuring
Do-ability
Procurement Strategy
Bid Process Management Pre-bid
Bid Process Management Post-bid
Identification/ Assessment
- Requires Project Preparation Partnership
Management - Inca is the nodal agency mandated to do the above
State need to enhance the involvement of private
sector need a PPP! The challenge is the right
model and right process for engagement of private
sector!
27Identification Stage
- To convert wish list into a list of projects that
are viable and amenable for PPP.
Objective
- Prelim assessment of the opportunity
- Prelim assessment of possibility of a PPP
- Presence of necessary ingredients land, land
use, basic approvals
Activities
28Preparation Stage
- Assessing feasibility and structuring the PPP
(Value for Money) (Risk Return Ratio)
Objective
- Assessment of Market opportunity
- Technical Financial Feasibility
- Financial structuring
- Sharing of risk and Structuring PPP
Activities
29Partner Selection Stage
- To select Private Sector Partner in an open and
transparent manner
Objective
- Technical and financial capability criteria
- Equal information sharing and support to all
bidders - Rigorous specifications Contract
- Efficient and time bound bidding process
Activities
30Project Development Process
Track 2
- PROJECT DEVELOPMENT
- Techno-Economic Market Assessment
- Legal Documentation
- Policy amendments and notification
- Contractual and Institutional Framework
- DEVELOPER SEARCH
- Expression of Interest
- Request for Proposal (RFP)
- Pre-Bid Conferences
- Proposal Evaluation
- Finalisation of Developer
- Finalisation of Agreements
- MARKETING COMMUNICATION
- One-to-one meetings
- Direct Mailers
- Media release
- Road Shows
- Investors Conferences
- Facilitating Consortia formation
Government Approvals, Facilitation Decision
Making
31Different Structures
32Transportation Infrastructure Projects From
Conception to Implementation
33The Stages
- Conception
- Identification of project alternatives
- Selection of the best alternative
- Implementation
- Construction of the project
- Operation and Maintenance
34(No Transcript)
35Classic Four-Stage Sequential Travel Demand Model
Trip Generation
Trip Distribution Demand
Modal Split
Traffic Assignment Supply
Considering Environmental Protection Economy
36Travel Demand Modeling Planning Variables
- Study area
- Internal zones
- External zones
- Plan Periods
- Demographic and Socio-economic data
- Protection of planning variables
- Transport network
- Origin and Destination Survey
37Tij
38Travel Demand Modeling Other Approaches
- Equilibrium Demand Modeling
- Traveler as consumer of transit trips
- Micro Economics - Utility Maximization
- Activity based analysis (Factors)
- Individual Traveler Level
- Type and Time of Activity
- Community Level
- Social Level
- Destination by mode
- Congestion
39Transport Priority Indices (TPI) in a Systems
Framework
- The Need -
- Huge investments involved and priority needs to
be given to villages with higher population and
potential market surplus. - The proposals discussed are those initiated by
- the State Government of Karnataka
- the Indonesian rural roads study group
- the ARD (Accelerated Rural Development) road
network of Thailand
40Organizational Setup for Planning and Prioritizing
- Formation of Technical Advisory Committee (TAC)
- Preparation of proposal/tender document
- Guidelines for selection of tenders
- Pre-bid selection
- Selection of PMC
- Selection of contractors
- Proof consultants
41UNDP - Government of India Project on Pro-poor
Globalisation
- Aim
- Informed and participatory pro-poor policy
making, strategy and programme formulation - Methodology
- Review of already conducted research on pro-poor
and anti-poor impacts of globalisation - Additional research and analysis
- Involvement of the poor in the policy dialogue
- Making information accessible to lay- person
42Methodology for Selection of Proposal
- Organisations short-listed on the basis of
initial proposals - Selection of 3 top-ranked proposals based on
their presentations - Initial contract awarded to these 3 organisations
to further refine and detail their proposal, work
plan and project strategy. - Review of final proposals by a panel
- Project awarded to the highest ranked proposal
43Decision Making
- Importance of decision making at every stage
during the project - Two important steps in the decision making
process - Course of action, which contains recognition,
discovery and contraction of ideas - Finding alternative strategies
- Decision making is complex due to multiplicity of
attributes
44Multiple Criteria Decision Making (MCDM)
- Importance in design and planning
- Some MCDM techniques
- Analytical Hierarchy Process (AHP)
- Fuzzy Set Methodology
- Metagame Theory
45Analytical Hierarchy Process
- Basic principles of AHP
- Hierarchic representation and decomposition
- Priority discrimination and synthesis
- Logical consistency
- Series of pair-wise comparisons carried out to
obtain the preference order - Each decision alternative assigned a weight
- Weights represent the alternatives desirability
46- Applications in fields like
- conflict analysis
- operations research
- portfolio selection
- bid evaluation
- capital budgeting
47FUZZY SET ANALYSIS
Transportation planning involves Qualitative and
quantitative analysis including uncertain
Attributes and Characteristics. Fuzzy Analysis
takes care of this important aspect of
transportation planning.
48- FUZZY LOGIC
- Fuzziness in Transportation Analysis
- In the study of transportation problems,
fuzziness is - found in many aspects of analysis
- Perception of data and information,
- Knowledge base,
- Statement of goals and objectives, and
- Problem definition.
49METHODOLOGY
The following are the steps of the methodology
1. Identifying the modes which will form
attributes (i,e., factors) of those
coordinated modes.
2. Categorizing different interest groups.
3. Forming termed rating matrix, with columns as
modes and rows as factors.
4. Constructing of different rating matrices as
per the views of respective interest groups
5. Aggregation of rating matrices
6. Forming dominance matrix from the dominance
of one mode over the other mode
7. Calculating the share of service by each
mode in a coordinated system.
50Case Study
The city of Calcutta, with five different mass
transit modes, is considered for the case
study.
51Case Study
The attributes considered for each mode are
52Case Study
Rating matrix for commuters opinion
53Case Study
Rating Matrix for Planners Opinion
54ADVANTAGES
- helps in the resolution of conflicts between
parties having a difference of opinion. - a non-quantitative method of analysis
- LIMITATIONS
- quite complicated in case of multi player and
multi choice conditions - May not always lead to a stable solution
55CASE STUDIES
- The following case studies will be discussed
- Mumbai - Pune Expressway Project
- The 50 Flyovers Project (Mumbai Traffic
Improvement Mega-Project) - Western Freeway Sea Link Project
- Bandra - Worli Sea Link Project, etc.
56Fund Sources
57Funding Sources
- Public funds derived from general taxation
- Funds from Debt
- Long term debts
- Short term debts
- Funds from Equity
- Funds from users charges
58Funding Sources
- Debt used around 60-90
- Equity used is 10-40
- Nearly the D/E ratio is more than 21
Sources of funding for BOT project ( Source
Malini 1997)
59Funding Sources
- Schaufelberger Et.Al. (2003) has reported an
alternate financial strategies for BOT Funding - Using Equity to finance the construction work
- Refinancing with Debt after major completion of
construction work
60Various schemes for implementation
- BOT (Build/Operate/Transfer)
- BOOT (Build/Own/Operate/Transfer)
- BOO (Build/Own/Operate)
- BLOT (Build/Lease/Operate/Transfer)
- BOLT (Build/Operate/Lease/Transfer)
- LOT (Lease/Operate/Transfer)
- COT (Cooperate/Operate/Transfer)
- Annuity and Service Outsourcing
61BOT
A Conceptual Model for the Operation of BOT
Scheme ( Source Malini 1997)
62Government Funding
- Entire investment, construction, operating, and
maintenance is by government - Direct budgetary devolution (tax-payer money)
- Debt raised against government guarantees, (and
letters of comfort) - Financing primarily by HUDCO and LIC
- Financial requirements are increasing way beyond
direct budgetary/ guarantee capacity - State budget deficits and statutory guarantee
limits constraining State Gov. funding capacity
63Local Authority Funding
- After the 74th Amendment, there is increasingly,
funding generated by the ULB - Escrowing revenues such as property tax, entry
tax/ octroi - Selling/ securitizing land
- But there is a limit to these numbers
64Multilateral/ Bilateral Funding
- World Bank, ADB, DFID
- Based on reform agenda
- Fairly detailed appraisals done
- Sectoral or project-wise
- Generally addresses needs of urban poor
- However, for commercial loans, based on
Government of India Guarantees as security - Very elaborate and complex processes
65(No Transcript)
66JNNURM
- Excellent scheme to lead reform-based financing
- Presents a new opportunity to
- Establish key reforms
- And thereby draw investment into key
infrastructure - But the scheme is available only to some cities
- Also focus towards commercial finance, which will
be a significant percentage of the project
investment PPPs are envisaged to be the way
forward
67Risks and Uncertainty in Projects
68Risk and Uncertainty
- Risk and Uncertainty is always there for both the
Government and Private Sector - Risk is mainly of three types
- Financial Risk
- Political risk
- Currency Devaluation Risk
69Risk and Uncertainty
- Financial Risk includes
- Termination Risk
- Regulation Risk
- Construction Risk
- Information Risk
70Risk and Uncertainty
- Political risk arouse due to
- Change in government
- Change in policies
- Currency Devaluation risk is aroused when
- Finance/debt is been done by foreign companies
71Treatments of Risks and Uncertainty in Projects
- The availability of partial or imperfect
information about a problem leads to two new
category of decision-making techniques - Decisions under risk (In terms of a probability
function) - Decisions under Uncertainty (No probability
function is secure)
72Decisions under risk
- Decisions under risk are usually based on one of
the following criteria - Expected Value
- Combined Expected value and variance
- Known Aspiration level
- Most likely occurrence of a future state
73Expected Value Criterion
- Expressed in terms of either actual money or its
utility - Decision Makers attitude towards the worth or
utility of money is important - The final decision should ultimately be made by
considering all pertinent factors that affect the
decision makers attitude towards the utility of
money - The drawback of this is that use of expected
value criterion may be misleading fro the
decisions that are applied only a few number of
times i.e small sample sizes
74Example 1
- A preventive maintenance policy requires making
decisions about when a machine (or a piece of
equipment) should be serviced on a regular basis
in order to minimize the cost of sudden breakdown - The decision situation is summarized as follows.
A machine in a group of n machines is serviced
when it breaks down. At the end of T periods,
preventive maintenance is performed by servicing
all n machines. The decision problem is to
determine the optimum T that minimizes the total
cost per period of servicing broken machines and
applying preventive maintenance
75- Let pt be the probability that machine would
break down in period t - Let nt be the random variable representing the
number of broken machines in the same period. - C1 is the cost of repairing a broken machine
- C2 the preventive maintenance of the machine
- The expected cost per period can be written as
- Where Ent is the expected number of broken
machines in period t. - nt is a binominal random variable with parameter
(n,pt), Entnpt - The necessary condition for T to minimize EC(T)
are - EC(T-1)gt EC(T) and EC(T1)gt EC(T)
76- To illustrate the above formulation, suppose
c1Rs.100, c2Rs.10 and n50 - The values of pt and EC(T) are tabulated below
- T
T pt Cumulative pt EC(T)
1 0.05 0 500
2 0.07 0.05 375
3 0.10 0.12 366.7
4 0.13 0.22 400
5 0.18 0.35 450
77Multi-Modal International Hub Airport at Nagpur
78 MIHAN
- MASTER PLAN
- INTERNATIONAL HUB AIRPORT
- STATE OF ART AIRPORT
- RAIL ROAD TERMINAL
- SPECIAL ECONOMIC ZONE
- Health City
- Captive Power Plant
- IT Park
- INTERNATIONAL SCHOOL, HOTELS,
- ENTERTAINMEMNT AND RESIDENTIAL AREA
- Mahrashtra Airport Development Company Company
Established By Government Of Mahrashtra - Expansion of airport at Nagpur
- Development of Special Economic Zone (SEZ)
DEVELOPMENT CREATES JOBS, COMMERCE, TRADE AND
STABILTY.
79International Hubbing Concept
80OBJECTIVES
- An attractive hub Airport
- Financially viable bankable project
- Minimum social and environmental impact
- Develop self-generating traffic
81Aerial view of Airport
82AIRSIDE VIEW
83SALIENT FEATURES OF THE PROJECT
- MIHAN project area 2535 Hectares
- Runways Existing runway to be extended to 4000m
length and 60m width Provision made for an
additional parallel runway 4000mx60m - Terminal facilities a semi-circular terminal
building 3,00,000 sqm area with an outer diameter
of 810m. Separate international and domestic
cargo terminals. - Aircraft Parking - 50 aircrafts in the Terminal
50 aircrafts remote. - Projected Traffic 14 million passengers a year
(70 international) and 8,70,000 tons of cargo
(90 international) a year. - Type of Airport International Hub Airport for
Passengers Cargo - Type of connectivity - Multi-Modal Airport,
Railway Terminal for Passengers Goods, Truck
Terminal, MRTS Terminal all in one Project - Special Economic Zone
84MAJOR BENEFITS
- Various types of tax and duty concessions within
SEZ - Efficient operating norms for the
Airport-Aircraft turn-around time, Passenger
walk-through time, cargo clearance time etc. - All infrastructure facilities available - power
, water, telecommunications, computer
connectivity etc. - Economic benefits to the Vidarbha Region and
Nagpur City and the overall Country through the
International and Domestic Hub. - Development of Hinterland through multi-modal
connectivity to the other parts of the Country.
85Economic Benefits
- Increase in Exports
- Wealth Creation
- Employment creation
- Increase in revenues from tourists
- Value addition
- Fiscal benefits to the Central and State
Government
86Economic Fiscal Benefits
87FINANCIAL ECONOMIC HIGHLIGHTS
- The total project cost is Rs.25810 million over
30 years - The total investment required in various
facilities in the MIHAN Project area by other
agencies is approximately Rs.26000 million till
2035 - The project is viable with an IRR of 15.8
- The Net Economic Value added to the region till
2035 will be Rs.522,254 million, apart from the
creation of thousands of jobs - Employment generated in airport, allied
activities and tourism
88Aspiration Level Criterion
- This method does not yield an optimal decision in
the sense of maximizing profit or minimizing cost - It is a means of determining acceptable courses
of action - Most Likely Future Criterion
- Converting the probabilistic situation into
deterministic situation by replacing the random
variable with the single value that has the
highest probability of occurrence
89Decisions under uncertainty
- They assume that there is no probability
distributions available to the random variable. - The methods under this are
- The Laplace Criterion
- The Minimax criterion
- The Savage criterion
- The Hurwicz criterion
90Laplace Criterion
- This Criterion is based on what is known as the
principle of insufficiency - ai is the selection yielding the largest expected
gain - Selection of the action ai corresponding
- where 1/n is the probability that
91Example 2
- A recreational facility must decide on the level
of supply it must stock to meet the needs of its
customers during one of the holiday. The exact
number of customers is not known, but it is
expected to be of four categories200,250,300 or
350 customers. Four levels of supplies are thus
suggested with level i being ideal (from the view
point of the costs) if the number of customer
falls in category i. Deviation from these levels
results in additional costs either because extra
supplies are stocked needlessly or because demand
cannot be satisfied. The table below provides the
costs in thousands of dollars - a1, a2, a3 and a4 are the supplies level
Customer Category Customer Category Customer Category Customer Category Customer Category
q1 q2 q3 q4
a1 5 10 18 25
a2 8 7 8 23
a3 21 18 12 21
a4 30 22 19 15
92- Solution by Laplace Criterion
- Ea1 (1/4)(5101825) 14.5
- Ea2 (1/4)(87823) 11.5
- Ea3 (1/4)(21181221) 18.0
- Ea4 (1/4)(30221915) 21.5
- Thus the best level of inventory according to
Laplace criterion is specified by a2.
93Minimax (Maxmini) Criterion
- This is the most conservative criterion since it
is based on making the best out of the worst
possible conditions - If the outcome v(ai,?j) represents loss for the
decision maker, then, for, ai the worst loss
regardless of what ?j may be is max ?j v(ai,?j) - The minimax criterion then selects the action ai
associated with min ai max ?j v(ai,?j) - Similarly if v(ai,?j) represents gain, the
criterion selects the action ai associated with
max ai min ?j v(ai,?j) - This is called the maxmini criterion
94- Applying this criterion to the Example 2
- Thus the best level of inventory according to
this criterion is specified by a3
Customer Category Customer Category Customer Category Customer Category Customer Category Max
Supply q1 q2 q3 q4 Max
a1 5 10 18 25 25
a2 8 7 8 23 23
a3 21 18 12 21 21
a4 30 22 19 15 30
Minimax value
95Effects of Toll rates in traffic projections
- Traffic and revenue (TR) forecasts - typically
point estimates - Bond investors, rating agencies, etc. prefer
rigorous sensitivity/risk assessments in toll
road TR forecasts - Risk analysis helps to
- Quantify uncertainties in inputs
- Determine impacts of inputs on output
- Analyze output sensitivities
- Quantify uncertainties of the output
- Multi-agency toll project financing negotiations
- Evolving risk analysis processes in TR
estimation
96Typical TR Process
Planned
Existing
Forecasted
Existing
(MTP, CIP, etc.)
Demand
Supply
Toll Diversion
Model
Toll Traffic/Transactions
Transponder Shares, Revenue Recovery, Truck
Shares, Revenue Days, Toll Rates
Sensitivity Analysis
Toll Revenue
96
97TR Risk Analysis Process
97
98 Uncertainties in Input Variables
Transaction Variables
Population (Census vs. Forecast)
Employment (Census vs. Forecast)
VOT (SP Survey, CPI)
Toll Rates, Vehicle Operating Costs (AAA, CPI)
General Uncertainty/Safety Factor
Revenue Variables
Truck Shares (based on observed trends on similar toll facilities)
Revenue Days (based on observed trends on similar toll facilities)
Transponder Shares (based on observed trends on similar toll facilities)
98
99 Impacts of Population on Toll Traffic
99
100 Impacts of Employment on Toll Traffic
100
101 Impacts of Value of Time on Toll Traffic
101
102 Impacts of Vehicle Operating Cost on Toll Traffic
102
103 TR Uncertainties
Year Traffic Distributions Traffic Distributions Traffic Distributions
Year Lower Bound (P5) Mean Upper Bound (P95)
2011 96 100 104
2030 80 100 122
Year Revenue Distributions Revenue Distributions Revenue Distributions
Year Lower Bound (P5) Mean Upper Bound (P95)
2011 83 100 111
2030 69 100 141
103
104Contd.
- Quantification of TR uncertainties very
important given the inherent uncertainties/imperfe
ctions in inputs and models - Possible ways to quantify TR uncertainties
- Discrete sensitivity analysis
- Risk analysis to create probability ranges for
the outputs - Combined sensitivity analysis, risk analysis and
extreme event impacts (recommended)
105B.O.T projects based on government support and
guarantees
106(No Transcript)
107(No Transcript)
108(No Transcript)
109(No Transcript)
110(No Transcript)
111(No Transcript)
112(No Transcript)
113SUMMARY
- Traditional four stage Transportation Planning
methodology is discussed. - Fundamentals behind the various techniques
adopted in decision making for mega
transportation infrastructure projects are
discussed. - An insight is provided into the procedure
involved from conception to implementation stage
supported by case studies of various
transportation projects.
114CONCLUSIONS
- Projects should be well-conceived and
economically efficient, using latest tools for
decision analysis. - Decision analysis should be through PMC , TAC as
well as conflict resolution, for different stages
in the projects. - It is necessary to have appropriate institutional
set up for effective conception, planning,
prioritization, decision analysis, PMC/contractor
selection and effective implementation through
Q/A checks.
115Thank You