SPI - PowerPoint PPT Presentation

1 / 4
About This Presentation
Title:

SPI

Description:

Schedule Performance Index (SPI): It tells you how efficiently you are actually progressing compared to the planned progress. Schedule Performance Index = (Earned ... – PowerPoint PPT presentation

Number of Views:1
Avg rating:3.0/5.0
Slides: 5
Provided by: engg157
Category:
Tags: spi | plan | project

less

Transcript and Presenter's Notes

Title: SPI


1
SPI
  • Schedule Performance Index (SPI) It tells you
    how efficiently you are actually progressing
    compared to the planned progress.
  • Schedule Performance Index (Earned
    Value)/(Planned Value)
  • SPI EV/PV
  • With the above formula you can conclude that
  • If the SPI is greater than one, this means more
    work has been completed than the planned work. In
    other words, you are ahead of schedule.
  • If the SPI is less than one, this means less work
    is completed than the planned work. In other
    words, you are behind schedule.
  • If the SPI is equal to one, this means all work
    is completed.
  • Ensure that noncritical activities are not
    ignored for right result of SPI.

2
CPI
  • The Cost Performance Index helps you analyze the
    efficiency of the cost utilized by the project.
  • It measures the value of the work completed
    compared to the actual cost spent on the project.
  • In simple words, the Cost Performance Index
    informs you of how much you are earning for each
    dollar spent on the project.
  • Cost Performance Index (Earned Value)/(Actual
    Cost)
  • CPI EV/AC
  • With the above formula you can conclude that
  • If the CPI is less than one, you are earning less
    than the spending. In other words, youre over
    budget.
  • If the CPI is greater than one, you are earning
    more than the spending. In other words, you are
    under budget.
  • If the CPI is equal to one, this means earning
    and spending are equal. Or you can say that you
    are proceeding exactly as per the planned budget
    spending, although this rarely happens.

3
Problem of SPI and CPI
  • You have a project to be completed in 12 months
    and the total cost of the project is 100,000
    USD. 06 months have passed and 60,000 USD has
    been spent, but on closer review you find that
    only 40 of the work is completed so far.
  • Solution
  • Actual Cost (AC) 60,000
  • Planned Value (PV) 50 of 100,000 50,000
  • Earned Value (EV) 40 of 100,000 40,000
  • Now, SPI EV / PV 40,000 / 50,000 0.8
  • Since the Schedule Performance Index is less than
    one, you are behind the planned schedule.
  • Cost Performance Index (CPI) EV / AC 40,000
    / 60,000 0.67
  • Since the Cost Performance Index is less than
    one, this means you are earning 0.67 USD for
    every 1 USD spending. In other words, you are
    over budget.

4
Reference
  • http//pmstudycircle.com
Write a Comment
User Comments (0)
About PowerShow.com