Report on the Challenges in the Planning and Procurement of Services - PowerPoint PPT Presentation

About This Presentation
Title:

Report on the Challenges in the Planning and Procurement of Services

Description:

Report on the Challenges in the Planning and Procurement of Services for the Ceres and van Rhynsdorp Correctional Facilities Portfolio Committee on Correctional Services – PowerPoint PPT presentation

Number of Views:151
Avg rating:3.0/5.0
Slides: 23
Provided by: Melik151
Category:

less

Transcript and Presenter's Notes

Title: Report on the Challenges in the Planning and Procurement of Services


1
  • Report on the Challenges in the Planning and
    Procurement of Services
  • for the Ceres and van Rhynsdorp Correctional
    Facilities
  • Portfolio Committee on Correctional Services
  • 5 September 2012

2
Purpose
  • To respond to observations made by the DCS
    Portfolio Committee during their meeting of 22
    February 2012 regarding the procurement of the
    contractor and details of the contract for both
    Ceres and Van Rhynsdorp Correctional Facility

.
3
Projects Initiation Professional Team
  • DCS requested provision of additional
    accommodation for administration and inmates to
    address congestion in various prisons in the
    Western Cape and in the Country. Hence VAN
    RHYNSDORP AND CERES PRISONS were registered as
    projects by DPW.
  • Registered Departmental Project Manager was
    appointed to lead the professional team which
    comprises of Private Engineers, Architect and
    Quantity Surveyor .

4
Projects Initiation Professional Team -
continues
  • The appointment of the professional team was done
    through routine assignment of consultants
    Roster
  • Each project had a dedicated professional team in
    order to maximize performance and focus
  • The professional team members involved on the
    project are registered with their relevant
    professional councils

5
ObservationPROCUREMENT PROCESS VAN RHYNSDORP
  • DPW advertised this tender on open procedure on
    27 July 2007.
  • Procurement Strategy included inter alia the
    following requirements
  • CIDB grading of 8GB or 8CE
  • Minimum Contract Participation Goal percentage of
    20 was required

6
ObservationProcurement Process Van
Rhynsdorpcontinue
  • Cost analysis and pre tender estimates were done
    by professionally registered Quantity Surveyor
  • Pre-tender Estimate was R 219,989,562.00
  • The estimate was based Kimberley Prototype
  • Contract Price Adjustment was included
  • Tender Amount R 192,876,930.64
  • Variance is R 27,112,631.36

7
ObservationProcurement Process Van Rhynsdorp
Continued
  • 3 Tenders were received on 12 September 2007
  • 1 tenderer was declared non-compliant due to not
    meeting the minimum points for quality
  • 1 tenderer was disqualified as they did not have
    the required CIDB grading

8
ObservationProcurement Process Van Rhynsdorp
  • Highest point scored tenderer was recommended as
    the bid adhered to all requirements set and the
    tenderer had the required cidb grading.
  • Cidb grading 8GBPE
  • Contract Participation Goal Percentage tendered
    47.41
  • Tender recommendation was accepted by the Bid
    Adjudication committee and tender was awarded on
    12 October 2007
  • The site was handed over to the contractor on 7
    November 2007

9
Van Rhynsdorp - Cost Analysis
  • Actual Tender Amount is R 192,876,930.64
  • Current Expenditure R 275 695 477.39
  • Variance between tender Amount and Expenditure to
    date R 82,818,546.75 (30.04)
  • Costing model applied by was based on Historical
    Information(Kimberley) and Cost for Resources
  • The variance increased due to the following
  • Additional work requested by the User Department,
    outside the original scope of works.
  • Change of specifications for materials to meet
    client needs and enhance compliance, post
    sign-off of project deliverables.
  • Failure to account for topography and
    geographical location of facilities

10
ObservationProcurement Process Ceres
  • DPW advertised this tender on open procedure on
    25 April 2008.
  • Procurement Strategy included inter alia the
    following requirements
  • CIDB grading of 8 GB
  • Minimum Contract Participation Goal percentage of
    20

11
ObservationPROCUREMENT PROCESS CERES- Continue
  • Cost analysis and pre tender estimates were done
    by professionally registered Quantity Surveyor.
  • Pre-tender Estimate was R 212,646,407.00
  • The estimate was based Kimberley Prototype
  • Contract Price Adjustment was also included
  • Costing model applied by Historical Information
    (Kimberley) and Cost for Resources
  • Actual Tender Amount R 182 712 542.62
  • Variance is R 29 933 864.38

12
OBSERVATIONPROCUREMENT PROCESS CERES
CONTINUED
  • 7 Tenders were received on 28 May 2008
  • 3 Tenders were disqualified as they did not have
    the correct cidb grading
  • Highest point scored tenderer was recommended as
    the bid adhered to all requirements set and the
    tenderer had the required cidb grading.

13
ObservationProcurement Process Ceres
continued
  • CIDB grading of 8 GBPE
  • Contract Participation goal percentage tendered
    43.7
  • Tender recommendation was accepted by the Bid
    Adjudication committee and tender was awarded on
    11 July 2008
  • The site was handed over to the contractor on 5
    August 2008

14
Ceres - Cost Analysis
  • Actual Tender Amount R 182 712 542.62
  • Current Expenditure R 193 229 166.23
  • Variance between tender Amount and Expenditure to
    date R 10 516 623.61 (5.44)
  • The variance increased due to the following
  • Additional work requested by the User Department,
    outside the original scope of works.
  • Failure to account for topography and
    geographical location of facilities

15
Form of contractsDetails of contracts
  • Most of the activities on both projects related
    to buildings and civil works. The form of
    contract found to be suitable and relevant to
    both projects was
  • Standard JBCC 2000 Edition 4.1 March 2005 this
    document is not part of the documentation, but is
    referred to as the basis of the contract
  • Special conditions of Contract DPW 04 EC

16
Shortcomings identified in contracts and how to
overcome in future
  • Shortcomings in processes have been identified
  • Sketch plan approval was duly obtained before
    tenders were invited user client changes still
    occurred due to the fact that these facilities
    were of the first new generation facilities to be
    built and lessons learnt at Kimberley was
    incorporated in the building during construction
    phase
  • Enough time must be allocated for the planning
    phase of a project
  • Risk assessment of tenders to be comprehensive as
    the cidb grading is correct, but experience in a
    specific field may be limited

17
Planning Phase
  • Challenge Time frame between approval of sketch
    plans and tender documentation is often too
    short. Often due to pressure to get on site and
    show an expenditure. The result is detail
    planning must be done during the contract
  • Proposal Realistic time frames must be set and
    communicated. Expectations must not be created
    where delivery cannot take place

.
18
Planning Phase
  • Challenge The geotechnical survey completed at
    the beginning of the planning was not
    comprehensive enough to indicate problems on soil
    conditions resulting in delays and extras due to
    rock, high water table levels, etc.
  • Proposal The DPW must ensure a comprehensive
    geotechnical survey and increase the amount of
    trial holes required in order to ensure that
    surprises in site conditions do not occur.

19
Planning Phase
  • Challenge The standard drawings and documents
    that existed were not comprehensive enough to
    allow planning without changes required. The
    lessons learned from Kimberley was incorporated
    during the construction phase
  • Proposal The DPW with assistance of DCS must
    develop comprehensive standard drawings and
    specifications that must only be adapted to suite
    a specific site.

20
Procurement Phase
  • Challenge At time of the evaluation of these
    tenders the method of risk assessment of
    contractors implemented was restrictive mainly
    based on the CIDB grading of the contractor and
    quality criteria set that did not include for all
    issues
  • Proposal The DPW has introduced a risk
    assessment concentrating on technical and
    contractual ability as well doing a commercial
    risk in line with the CIDB prescriptions. This
    must be further enhanced by developing of quality
    (functionality) criteria that are fair and
    objective

21
Procurement Phase
  • Challenge Contractors that are responsive in all
    criteria and will pass a risk assessment, but can
    be over committed if too many projects are
    simultaneously awarded to such companies.
  • Proposal A difficult challenge to resolve! The
    DPW to engage with National Treasure and the CIDB
    to develop criteria that can be used to ascertain
    if a proposed contractor will be over committed
    if more projects are awarded

22
THANK YOU
Write a Comment
User Comments (0)
About PowerShow.com