Title: Report on the Challenges in the Planning and Procurement of Services
1- Report on the Challenges in the Planning and
Procurement of Services - for the Ceres and van Rhynsdorp Correctional
Facilities - Portfolio Committee on Correctional Services
- 5 September 2012
2Purpose
- To respond to observations made by the DCS
Portfolio Committee during their meeting of 22
February 2012 regarding the procurement of the
contractor and details of the contract for both
Ceres and Van Rhynsdorp Correctional Facility
.
3Projects Initiation Professional Team
- DCS requested provision of additional
accommodation for administration and inmates to
address congestion in various prisons in the
Western Cape and in the Country. Hence VAN
RHYNSDORP AND CERES PRISONS were registered as
projects by DPW. - Registered Departmental Project Manager was
appointed to lead the professional team which
comprises of Private Engineers, Architect and
Quantity Surveyor .
4Projects Initiation Professional Team -
continues
- The appointment of the professional team was done
through routine assignment of consultants
Roster - Each project had a dedicated professional team in
order to maximize performance and focus - The professional team members involved on the
project are registered with their relevant
professional councils
5ObservationPROCUREMENT PROCESS VAN RHYNSDORP
- DPW advertised this tender on open procedure on
27 July 2007. - Procurement Strategy included inter alia the
following requirements - CIDB grading of 8GB or 8CE
- Minimum Contract Participation Goal percentage of
20 was required
6ObservationProcurement Process Van
Rhynsdorpcontinue
- Cost analysis and pre tender estimates were done
by professionally registered Quantity Surveyor - Pre-tender Estimate was R 219,989,562.00
- The estimate was based Kimberley Prototype
- Contract Price Adjustment was included
- Tender Amount R 192,876,930.64
- Variance is R 27,112,631.36
7ObservationProcurement Process Van Rhynsdorp
Continued
- 3 Tenders were received on 12 September 2007
- 1 tenderer was declared non-compliant due to not
meeting the minimum points for quality - 1 tenderer was disqualified as they did not have
the required CIDB grading
8ObservationProcurement Process Van Rhynsdorp
- Highest point scored tenderer was recommended as
the bid adhered to all requirements set and the
tenderer had the required cidb grading. - Cidb grading 8GBPE
- Contract Participation Goal Percentage tendered
47.41 - Tender recommendation was accepted by the Bid
Adjudication committee and tender was awarded on
12 October 2007 - The site was handed over to the contractor on 7
November 2007
9Van Rhynsdorp - Cost Analysis
- Actual Tender Amount is R 192,876,930.64
- Current Expenditure R 275 695 477.39
-
- Variance between tender Amount and Expenditure to
date R 82,818,546.75 (30.04) - Costing model applied by was based on Historical
Information(Kimberley) and Cost for Resources - The variance increased due to the following
- Additional work requested by the User Department,
outside the original scope of works. - Change of specifications for materials to meet
client needs and enhance compliance, post
sign-off of project deliverables. - Failure to account for topography and
geographical location of facilities
10ObservationProcurement Process Ceres
- DPW advertised this tender on open procedure on
25 April 2008. - Procurement Strategy included inter alia the
following requirements - CIDB grading of 8 GB
- Minimum Contract Participation Goal percentage of
20
11ObservationPROCUREMENT PROCESS CERES- Continue
- Cost analysis and pre tender estimates were done
by professionally registered Quantity Surveyor. - Pre-tender Estimate was R 212,646,407.00
- The estimate was based Kimberley Prototype
- Contract Price Adjustment was also included
- Costing model applied by Historical Information
(Kimberley) and Cost for Resources - Actual Tender Amount R 182 712 542.62
- Variance is R 29 933 864.38
12OBSERVATIONPROCUREMENT PROCESS CERES
CONTINUED
- 7 Tenders were received on 28 May 2008
- 3 Tenders were disqualified as they did not have
the correct cidb grading - Highest point scored tenderer was recommended as
the bid adhered to all requirements set and the
tenderer had the required cidb grading.
13ObservationProcurement Process Ceres
continued
- CIDB grading of 8 GBPE
- Contract Participation goal percentage tendered
43.7 - Tender recommendation was accepted by the Bid
Adjudication committee and tender was awarded on
11 July 2008 - The site was handed over to the contractor on 5
August 2008
14Ceres - Cost Analysis
- Actual Tender Amount R 182 712 542.62
- Current Expenditure R 193 229 166.23
- Variance between tender Amount and Expenditure to
date R 10 516 623.61 (5.44) - The variance increased due to the following
- Additional work requested by the User Department,
outside the original scope of works. - Failure to account for topography and
geographical location of facilities
15Form of contractsDetails of contracts
- Most of the activities on both projects related
to buildings and civil works. The form of
contract found to be suitable and relevant to
both projects was - Standard JBCC 2000 Edition 4.1 March 2005 this
document is not part of the documentation, but is
referred to as the basis of the contract - Special conditions of Contract DPW 04 EC
16Shortcomings identified in contracts and how to
overcome in future
- Shortcomings in processes have been identified
- Sketch plan approval was duly obtained before
tenders were invited user client changes still
occurred due to the fact that these facilities
were of the first new generation facilities to be
built and lessons learnt at Kimberley was
incorporated in the building during construction
phase - Enough time must be allocated for the planning
phase of a project - Risk assessment of tenders to be comprehensive as
the cidb grading is correct, but experience in a
specific field may be limited
17Planning Phase
- Challenge Time frame between approval of sketch
plans and tender documentation is often too
short. Often due to pressure to get on site and
show an expenditure. The result is detail
planning must be done during the contract - Proposal Realistic time frames must be set and
communicated. Expectations must not be created
where delivery cannot take place
.
18Planning Phase
- Challenge The geotechnical survey completed at
the beginning of the planning was not
comprehensive enough to indicate problems on soil
conditions resulting in delays and extras due to
rock, high water table levels, etc. - Proposal The DPW must ensure a comprehensive
geotechnical survey and increase the amount of
trial holes required in order to ensure that
surprises in site conditions do not occur.
19Planning Phase
- Challenge The standard drawings and documents
that existed were not comprehensive enough to
allow planning without changes required. The
lessons learned from Kimberley was incorporated
during the construction phase - Proposal The DPW with assistance of DCS must
develop comprehensive standard drawings and
specifications that must only be adapted to suite
a specific site.
20Procurement Phase
- Challenge At time of the evaluation of these
tenders the method of risk assessment of
contractors implemented was restrictive mainly
based on the CIDB grading of the contractor and
quality criteria set that did not include for all
issues - Proposal The DPW has introduced a risk
assessment concentrating on technical and
contractual ability as well doing a commercial
risk in line with the CIDB prescriptions. This
must be further enhanced by developing of quality
(functionality) criteria that are fair and
objective
21Procurement Phase
- Challenge Contractors that are responsive in all
criteria and will pass a risk assessment, but can
be over committed if too many projects are
simultaneously awarded to such companies. - Proposal A difficult challenge to resolve! The
DPW to engage with National Treasure and the CIDB
to develop criteria that can be used to ascertain
if a proposed contractor will be over committed
if more projects are awarded
22THANK YOU