Title: Aims and Objectives - To minimise disruption to the school - To carry out the work safely - To complete the work on programme - To deliver a quality building
1Aims and Objectives- To minimise disruption to
the school- To carry out the work safely- To
complete the work on programme- To deliver a
quality building
London Borough of Merton - Pelham Primary School
Expansion Delivery Strategy
2London Borough of Merton - Pelham Primary School
Expansion Delivery Strategy
- Programme and Timescale
- Work carried out in agreed phases
- Initial preparatory Phase over the summer 2013
- Main build commences Christmas 2013
- All works complete Easter 2015
- Total main build period of 12 months
- Final four months for remaining internal
remodelling and landscape works
3London Borough of Merton - Pelham Primary School
Expansion Delivery Strategy
- Initial Phase Summer 2013
4London Borough of Merton - Pelham Primary School
Expansion Delivery Strategy
- Main Build Commencement Christmas 2013
5London Borough of Merton - Pelham Primary School
Expansion Delivery Strategy
6London Borough of Merton - Pelham Primary School
Expansion Delivery Strategy
- September 2014 to January 2015 Works
7London Borough of Merton - Pelham Primary School
Expansion Delivery Strategy
- January 2015 to February 2015 (half term)
8London Borough of Merton - Pelham Primary School
Expansion Delivery Strategy
- February 2015 to Easter holidays 2015
9London Borough of Merton - Pelham Primary School
Expansion Delivery Strategy
- Safety During the Works
- Segregation
- Contractor competence
- Site rules and protocols
- Management of deliveries
- Communication
- Monitoring procedures
10 London Borough of Merton - Pelham Primary School
Expansion Delivery Strategy
- School Wide Issues
- Noise
- Catering provision loss of kitchen
- Information updates
- Learning Possibilities and engagement
- Flexibility during the process
11London Borough of Merton - Pelham Primary School
Expansion Delivery Strategy
- Quick Case Study Hollymount School
12London Borough of Merton - Pelham Primary School
Expansion Delivery Strategy
- Quick Case Study Hollymount School
13London Borough of Merton - Pelham Primary School
Expansion Delivery Strategy
- Quick Case Study Hollymount School